  2664   Friday, August 16, 2024, 15:32 Aaron TamSouth Hot-CellStandard OperationTM4Ta#68 LP-SISTarget Ta#68 loaded onto TM4  Target Ta#68 loaded onto TM4 
-leak check passed
-Target electrode conductor screws
 Ta-68_Installed.jfif 
  2665   Monday, August 19, 2024, 09:32 David WangConditioning StationStandard OperationTM4Ta#68 TM4 has been moved from SHC to TCS.TM4 has been moved from SHC to TCS. The
move is successful. 
  
  2674   Friday, September 06, 2024, 10:01 David WangSouth Hot-CellStandard OperationTM4Ta#67 back up. TM4 has been moved from SMP to SHC.TM4 has been moved from SMP to SHC. The
move is smooth. 
  
  2676   Tuesday, September 10, 2024, 12:41 Aaron TamSouth Hot-CellStandard OperationTM4TiC#9Target TiC#9 HP-SIS installed onto TM4September 9, 2024 - Aaron Tam 

    Water from waterline found
puddled on source-tray and containment box. 
 089c5872-091d-484b-9b9c-dda8444b217b.jfif566cae27-5562-4934-b23a-5c99af810900.jfifcc853ae8-5896-46f3-9f21-f6ede8c82626.jfifffdf443c-2656-499a-9d0a-01ddef2f954a.jfif 
  2677   Tuesday, September 10, 2024, 12:41 Frank SongSouth Hot-CellStandard OperationTM4TiC#9 electrical check/leak check TM4 with new target TiC#9 Surface
installed in SHC was leak/electric checked
before moving to TCS. See attached pic pls.
 TM4_with_TiC#9_Surface_electric(leak)_cheak_on_SHC_2024-09-10.pdf 
  2678   Wednesday, September 11, 2024, 07:59 David WangConditioning StationStandard OperationTM4TiC#9TM4 has been moved from SHC to TCS.TM4 has been moved from SHC to TCS. The
move is smooth. 
  
  2683   Tuesday, September 17, 2024, 11:16 David WangITWStandard OperationTM4TiC#9TM4 has been moved from TCS to ITW.TM4 has been moved from TCS to ITW. The
move is smooth.
  
  2684   Tuesday, September 17, 2024, 13:42 Frank SongITWStandard OperationTM4TiC#9 Module Connection TM4 with target TiC#9 is connected
in ITW. See attachment.
 TM4_with_TiC#9_connection_in_ITW_2024-09-17.pdf 
  2689   Monday, September 23, 2024, 11:35 David WangITWStandard OperationTM4TiC #9.vacuum leak check on TM4 service cap in ITW. vacuum leak check on TM4 service cap in
ITW was done this morning.   leak
detector leak rate 0.0XE-9 atm.cc/sec. No
  
  2710   Tuesday, November 05, 2024, 09:49 Frank SongITWStandard OperationTM4TiC#9 module disconnection TM4 with spent target TiC#9 was disconnected
in 29-10-2024 and it is being moved from
ITW to SHC.
 TM4_with_spent_target_TiC#9_disconnection_in_ITW_20241029.pdf 
  2712   Wednesday, November 06, 2024, 08:29 Aaron TamSouth Hot-CellStandard OperationTM4TiC#9Target and Parasitic assemblies removal from TiC#9November 5, 2024 - Aaron Tam
TiC#9 HP-SIS removed from TM4

    Top left fixing bolt shows
 17x 
  2713   Wednesday, November 06, 2024, 16:33 David WangSouth Hot-CellStandard OperationTM4UCX46TM4 with UCx46 electrical and leak check at SHCTM4 with UCx46 electrical and leak check
at SHC is done. Everything is good.
 TM4_UCx46_electrical_check.pdf 
  2715   Friday, November 08, 2024, 10:44 Aaron TamSouth Hot-CellStandard OperationTM4UCx#46UCx#46 Install and Parasitic Target Status November 6, 2024 - Aaron Tam 
UCx#46 Target handover from
TPO 
 Left_side_Array_Parasitic_with_floppy_spacer.jfifRight_side_Window_Parasitic.jfifLid_Parasitics_order.jfif 
  2717   Tuesday, November 12, 2024, 12:30 Frank SongITWStandard OperationTM4UCx#46Module Connection TM4 with new target UCx#46 was moved
from TCS to ITW and has been re-connected
right after. see attachment pls.
 TM4_with_new_target_UCx#46_connection_in_ITW_2024-11-12.pdf 
  2719   Thursday, November 21, 2024, 14:11 Frank Song5 Shielding BlocksStandard OperationTM4UCx#46shielding blocks transfer Shielding blocks have been moved
from ITE to ITW and MAA is secured.
  
  2739   Friday, January 03, 2025, 10:41 David WangITWStandard OperationTM4UCX46ITW primary and secondary vacuum vessel leak check for 2025 shut downITW primary and secondary vacuum vessel
leak check for  2025 shut down has been
done. Also,TM4 internal water line helium
 ITW_primary_and_secondary_vacuum_leak_check_2025.pdf 
  2741   Monday, January 06, 2025, 08:38 Frank SongITWStandard OperationTM4UCx#46module disconnection TM4 WITH UCx#46 was disconnected
in 2025-01-02 in ITW. Forms attached.
 TM4_with_UCx#46_disconnection_in_ITW_2025-01-02.pdf 
  2743   Wednesday, January 08, 2025, 07:37 chad fisherSouth Hot-CellStandard OperationTM4UCx#46UCx#46 removalUCx#46 removed from TM4 and placed into
a pail back-filled with argon. Nothing visually
unusual; no issues.
 TM4_UCx46_07012024.jpegTM4_UCx46_2_07012024.jpeg 
  2745   Thursday, January 09, 2025, 11:46 David WangSafe Module ParkingStandard OperationTM4No targetSMP is under vacuum for TM4 storage during shut down.  SMP:MP1 is started with SMP BV1 is
opened. SMP is under vacuum for TM4 storage
during shut down.
  
  129   Wednesday, June 20, 2012, 11:39 Grant MinorSouth Hot-CellDevelopmentTM3N/ATM3 Planned Activites at South Hot Cell Jun 20 to 29 2012