Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 31 of 140  Not logged in ELOG logo
Entry  Thursday, August 20, 2015, 13:48, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - Sep 08 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
 Weekly update target hall schedule.See attachment 1,2
Spring and summer run is close to the end. This will be the last update on this old schedule. See attachment3,4.    A new schedule
for TH activities after mini shut down will be posted next time.
Entry  Friday, May 01, 2015, 13:48, David Wang, South Hot-Cell, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - June 26 2015 update Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target Hall Scheduled Activities  April 07 - June 26  2015 update.      2015-05-01. All TH scheduled jobs are finished on time
this week.
Entry  Monday, April 13, 2015, 08:59, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - June 26 2015 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
See attachments 1, 2 for target hall schedule from 07 April to 26 June 2015. The first TM1 move which is scheduled on 16 April 2015 could be delayed
because of SHC operator availability. I will update the schedule once Don confirms the move date with Isaac.
Updated the schedule. The TM1 move has been re-scheduled to Friday, 17 April 2015.    See attachments 3,4.
Entry  Monday, April 20, 2015, 07:27, David Wang, ITE, Standard Operation, TM4, , Target Hall Scheduled Activities April 07 - June 26 2015 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp
Weekly target hall schedule update.2015-04-20
weekly target hall schedule update 2015-04-27 attachments 3,4.
Entry  Monday, May 11, 2015, 11:20, David Wang, South Hot-Cell, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - June 26 2015 6x
The schedule has some changes due to  new TM2 source tray coil cooling line leaking at test stand. Now,It is re-scheduled in such an estimation 
that TM2 source tray could be ready at teat stand by this Friday(May-15th). see attachment 1,2.
2015-05-12,  Changed  and updated the TH activity schedule according to Dons new beam schedule which is re-arranged after the coil line
Entry  Tuesday, June 02, 2015, 06:51, David Wang, South Hot-Cell, Standard Operation, TM4, , Target Hall Scheduled Activities April 07 - June 26 2015 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf
Target Hall schedule weekly update. All jobs are finished on time so far.
Entry  Wednesday, June 10, 2015, 13:17, David Wang, ITE, Standard Operation, TM1, , Target Hall Scheduled Activities April 07 - July 26 2015 Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
Weekly update the schedule after some jobs have been finished in this week.
Entry  Friday, June 26, 2015, 08:27, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - July 24 2015 Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mpp
Update the Target hall Schedule after some changes on TM2 refurbishment. See attachment 1,2
2015-06-30, updated the schedule after some jobs have been finished before Canada day. See attachment 3,4.
Entry  Friday, July 03, 2015, 09:41, David Wang, Conditioning Station, Standard Operation, TM2, , Target Hall Scheduled Activities April 07 - July 24 2015 Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mpp
Updated the schedule before the weekend 2015-07-03. See attachment 1,2
Updated the schedule according to present TM2 refurbishment process. See attachment 3,4
Entry  Wednesday, June 03, 2015, 11:22, David Wang, Conditioning Station, Standard Operation, , , Target Hall Scheduled Activities April 07 - July 21 2015 Target_Hall_Scheduled_Activities__Apr_07_to_July_21__2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp
I revised the Target Hall schedule to July 21 2015. It is the time new TM2 with ZrC target started at ITW.
2015-06-04, Updated the schedule with   new PDF view. See attachments 3, 4
Entry  Monday, June 15, 2015, 14:14, David Wang, South Hot-Cell, Standard Operation, , , Target Hall Scheduled Activities April 07 - July 21 2015 Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf
Weekly update Target Hall schedule 2015-06-15. See attachment 1,2
 2015-06-19, Update the schedule on  the end of the week. See attachment 3,4
Entry  Thursday, July 16, 2015, 07:38, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 07 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
Update the TH schedule according to present TM2 refurbishment process. See attachments 1,2
2015-07-20 , Update the TH schedule after some changes on TM2 and TM4 arrangement. See attachments 3,4
Entry  Thursday, July 23, 2015, 10:23, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 019 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
Update Target Hall schedule after the changing on TM2 process. See attachment 1,2
Entry  Friday, July 31, 2015, 09:47, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 019 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mpp
Weekly update of Target Hall schedule after so many jobs have been finished in this week.  See attachment 1, 2
Entry  Friday, August 07, 2015, 10:01, David Wang, ITE, Standard Operation, , , Target Hall Scheduled Activities April 07 - August 19 2015 Target_Hall_Scheduled_Activities__Apr_07_to_Aug_19.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_19.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf
Weekly update target hall schedule and activities. See attachment 1,2
Update and extend Target Hall schedule to Sep 08.  See attachment 3,4
Entry  Thursday, November 23, 2023, 11:15, Adam Newsome, Crane, Repair, , , Target Hall Crane: CW/CCW rotation mechanism failure [tripped breaker] 
It is reported that the crane's hook rotation is not working currently. It was working yesterday (Nov 22). Investigation to follow, and this e-log will
be updated. 
    Reply  Wednesday, October 09, 2013, 19:33, Grant Minor, Crane, Repair, TM4, , Target Hall Crane not operational - likely controls / PLC hardware failure (not stuck wheel) 


    
        
            
            Grant Minor wrote:
            
        
        
            
            Grant Minor
Entry  Tuesday, October 08, 2013, 18:12, Grant Minor, Crane, Repair, TM4, , Target Hall Crane Stuck in East-West Direction - Update THall_Crane_Bridge_Wheel_at_South_Rail_Splice_8Oct2013.JPGNORELCO_inv13045_joMS-064_31March2013.pdf
Grant Minor wrote this e-mail today:
***
Hello all,
Entry  Friday, January 03, 2020, 13:15, Adam Newsome, Crane, Repair, , , Target Hall Crane PLC Module/Battery Replacement 
The Target Hall Crane bridge and trolley motion was lost after a period of the crane having power disconnected over winter holidays. This is reported in
the following e-log: https://elog.triumf.ca/TIS/RH-ISAC/2039. This issue is a duplicate of what happened in 2019 at this time: https://elog.triumf.ca/TIS/RH-ISAC/1845
Entry  Thursday, April 06, 2017, 15:11, Grant Minor, Crane, Maintenance, , , Target Hall Crane 20 ton hoist - Report by Gordon Crane 5-Apr-2017 


v\:* {behavior:url(#default#VML);}
o\:* {behavior:url(#default#VML);}
w\:* {behavior:url(#default#VML);}
.shape {behavior:url(#default#VML);}








Normal
0




false
false
false
ELOG V2.9.2-2455