  1243   Tuesday, May 24, 2016, 10:42 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 130 (Apr- Sep)Weekly update the TH schedules. See attachments
1, 2,3.
 Target_Hall_shedule_130_Apr_to_Sep_2016.xlsxTarget_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep.pdf 
  1262   Thursday, June 09, 2016, 10:04 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Sep)Weekly update .  Target_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep.pdf 
  1283   Tuesday, July 12, 2016, 12:42 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Sep)Update schedule weekly.Attachment 1,2  Target_Hall_shedule_130_Apr_to_Sep.pdfTarget_Hall_shedule_130_Apr_to_Sep.mpp 
  1285   Thursday, July 14, 2016, 10:54 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)Update TH schedule 130 according to mini-shut
down change.See attachment 1,2,3,4
 Target_Hall_shedule_130_Apr_to_Sep.pdfTarget_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep_2016.pdfTarget_Hall_shedule_129_Sep_to_Dec.xlsx 
  1303   Wednesday, August 03, 2016, 09:56 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)Update schedule weekly. See attachments
1,2
 Target_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep.pdf 
  1320   Monday, August 15, 2016, 10:15 David WangConditioning StationStandard OperationTM4 Target Hall schedule for beam schedule 130 (Apr- Oct, 2016)Weekly update target hall schedule. Everything
on schedule are finished  on time.  
See attachment.  
 Target_Hall_shedule_130_Apr_to_Sep.pdfTarget_Hall_shedule_130_Apr_to_Sep.mpp 
  1424   Thursday, January 19, 2017, 10:15 David WangConditioning StationStandard Operation  Target Hall schedule for 2017 winter shut downUpdated target hall schedule for 2017 winter
shut down. See attachments 1,2
Update schedule after Febiad beam
 2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf2017_Winter_Shut_Down_Target_Hall_Schedule.mpp2017_Winter_Shut_Down_Target_Hall_Schedule.pdf 
  1684   Wednesday, January 31, 2018, 10:32 David WangCraneStandard Operation  Target Hall crane annual inspection.Gordon crane technician Tom finished annual
TH crane inspection today. Everything is
normal. The main hoist brake gaps are checked
  
  1459   Thursday, March 23, 2017, 11:22 Grant MinorCraneMaintenance  Target Hall crane 20 ton hoist noise / smell - inspection by Gordon Crane & HoistStrange noise and a burning brake type
smell was observed yesterday by David and
Anders when running the main 20 ton hoist
 Target_Hall_crane_main_hoist_problem_-_A_Mjos_-_22_Mar_2017.pdfUpdate_-_Target_Hall_20T_Hoist_Inspection_-_G_Minor_-_23_Mar_2017.pdfRe__Update__Target_Hall_20T_Hoist_Inspection_-_David_Wang_-_23_mar_2017.pdf 
  1044   Thursday, August 20, 2015, 13:48 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - Sep 08 2015 Weekly update target hall schedule.See
attachment 1,2
Spring and summer run is close to
 Target_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Sep_08.pdf 
  908   Friday, May 01, 2015, 13:48 David WangSouth Hot-CellStandard OperationTM2 Target Hall Scheduled Activities April 07 - June 26 2015 updateTarget Hall Scheduled Activities 
April 07 - June 26  2015 update.  
   2015-05-01. All TH scheduled
 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf 
  885   Monday, April 13, 2015, 08:59 David WangITEStandard Operation  Target Hall Scheduled Activities April 07 - June 26 2015See attachments 1, 2 for target hall schedule
from 07 April to 26 June 2015. The first
TM1 move which is scheduled on 16 April 2015
 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp 
  890   Monday, April 20, 2015, 07:27 David WangITEStandard OperationTM4 Target Hall Scheduled Activities April 07 - June 26 2015Weekly target hall schedule update.2015-04-20
weekly target hall schedule update
2015-04-27 attachments 3,4.
 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mpp 
  914   Monday, May 11, 2015, 11:20 David WangSouth Hot-CellStandard OperationTM2 Target Hall Scheduled Activities April 07 - June 26 2015The schedule has some changes due to 
new TM2 source tray coil cooling line leaking
at test stand. Now,It is re-scheduled in
 6x 
  923   Tuesday, June 02, 2015, 06:51 David WangSouth Hot-CellStandard OperationTM4 Target Hall Scheduled Activities April 07 - June 26 2015Target Hall schedule weekly update. All
jobs are finished on time so far.
 Target_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_June_26_2015.pdf 
  940   Wednesday, June 10, 2015, 13:17 David WangITEStandard OperationTM1 Target Hall Scheduled Activities April 07 - July 26 2015Weekly update the schedule after some jobs
have been finished in this week.
 Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp 
  962   Friday, June 26, 2015, 08:27 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - July 24 2015Update the Target hall Schedule after some
changes on TM2 refurbishment. See attachment
1,2
 Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mpp 
  978   Friday, July 03, 2015, 09:41 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - July 24 2015Updated the schedule before the weekend
2015-07-03. See attachment 1,2
Updated the schedule according to
 Target_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_24_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_07.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_Aug_07.mpp 
  930   Wednesday, June 03, 2015, 11:22 David WangConditioning StationStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015I revised the Target Hall schedule to July
21 2015. It is the time new TM2 with ZrC
target started at ITW.
 Target_Hall_Scheduled_Activities__Apr_07_to_July_21__2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mpp 
  948   Monday, June 15, 2015, 14:14 David WangSouth Hot-CellStandard Operation  Target Hall Scheduled Activities April 07 - July 21 2015Weekly update Target Hall schedule 2015-06-15.
See attachment 1,2
 2015-06-19, Update the schedule
 Target_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdfTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.mppTarget_Hall_Scheduled_Activities__Apr_07_to_July_21_2015.pdf 