Thursday, November 19, 2020, 12:00, Adam Newsome, Spent Target Vault, Standard Operation, , C#2, Spent Target Move
|
C#2 has been moved from the south hot cell to the spent target vault. It is in spot 8A of the vault in pail # 235 and was 185 mSv/hr upon removal from
the south hot cell.
The Target Index spreadsheet has been updated on DocuShare. |
Thursday, November 19, 2020, 09:00, David Wang, Conditioning Station, Standard Operation, TM2, Nb#6, Helium pressure check on TM2 HS line at TCS.
|
LD 0.0 Xe-9 atm.cc/sec , 70 psi helium 3 minutes. No leak. |
Wednesday, November 18, 2020, 15:28, David Wang, South Hot-Cell, Standard Operation, TM2, Nb#6, electrical check and HS leak check.
|
Everything looks good. A still short to P before target installation. We will float P,Q as before on module top. |
Tuesday, November 17, 2020, 10:17, Adam Newsome, South Hot-Cell, Standard Operation, TM2, , Module Move
|
TM2 has been moved from ITW to the South Hot Cell.
Reading at ITW: 114 mSv/hr |
Thursday, November 12, 2020, 10:02, Travis Cave, Spent Target Vault, Standard Operation, , UC#31, Spent Target Move
|
UC#31 has been moved from the south hot cell to the spent target vault. It is in spot 8B of the vault in pail # 224 and was 3.71mSv/hr upon removal
from the south hot cell. |
Thursday, November 05, 2020, 10:48, Travis Cave, ITE, Standard Operation, TM4, Ta#61, Module move
|
TM#4 with Ta#61 has been moved from the south hot cell to the east target station. |
Thursday, November 05, 2020, 10:23, David Wang, Spent Target Vault, Standard Operation, , , TM2 old source tray and TM4 optic tray in vault tray#9.
|
TM2 old source tray and TM4 optic tray are stored together in vault tray#9. The fielding measurement at SHC post 0.5 meter distance:
March 1st 2019, maximum 14.6msv/hr, minimum 4.78 msv/hr |
Tuesday, November 03, 2020, 10:52, Travis Cave, South Hot-Cell, Standard Operation, TM4, UC#31, Module move
|
TM#4 with UC#31 has been moved from the east target station to the south hot cell. |
Friday, October 30, 2020, 09:02, Travis Cave, Spent Target Vault, Standard Operation, , Ta#48,51,54 SiC#35, and UC#25, Repacking of the targets.
|
Targets Ta#48,51,54 SiC#35, and UC#25 were repacked and placed in the mini vault. In the following order back to front. SiC#35 (240), Ta#54(241),
UC#25(244), Ta#48(243), Ta#51(242).
Also during this repacking Ta#60 was also placed in the Spent Target Vault in spot 7B in pail# 239. |
Tuesday, October 27, 2020, 11:46, Matthew Gareau, North Hot-Cell, Repair, , , Ratcheting repair issues with both left and right master
|
The were issues with both left and right master
ratcheting; |
Tuesday, October 20, 2020, 10:14, Travis Cave, ITW, Standard Operation, TM2, C#2, Module move
|
TM#2 with C#2 has been moved from the south hot cell to the West Target Station. |
Monday, October 19, 2020, 12:52, David Wang, South Hot-Cell, Standard Operation, TM2, C#2, TM2 electrical and leak check at SHC
|
TM2 electrical check and leak check are done at SHC with C#2 target installed. The results are good. |
Friday, October 16, 2020, 10:36, Travis Cave, ITW, Standard Operation, TM2, Ta#60, Module move
|
TM#2 with Ta#60 is now in the south hot cell. |
Thursday, October 15, 2020, 12:48, Travis Cave, ITE, Standard Operation, TM4, UC#31, Module move
|
TM#4 is now back in the east target station. |
Tuesday, October 13, 2020, 10:16, Travis Cave, ITE, Repair, TM4, UC#31, Module move
|
TM#4 is now in the south hot cell from the east target station. |
Wednesday, September 30, 2020, 09:54, Travis Cave, South Hot-Cell, Standard Operation, TM3, no target, Module move
|
TM#3 is now in the south hot cell. |
Tuesday, September 29, 2020, 14:28, David Wang, South Hot-Cell, Standard Operation, TM4, UC#31, TM4 UC#31 Electrical check and HS leak check
|
Tm4 UCx 31# electrical check result. See attachment. |
Tuesday, September 29, 2020, 12:29, Travis Cave, ITE, Standard Operation, TM4, UC#31, Module move
|
Module move of TM#4 with UC#31 was finished to today at around 10:30AM. |
Tuesday, September 29, 2020, 12:12, David Wang, ITE, Repair, TM4, , TM4 steerers staus after" left " grounding issue, and first stage investigation
|
Left (short) is switched with bottom. So on module:
"Top" is still top.
"Left" is bottom |
Thursday, September 24, 2020, 11:25, David Wang, Conditioning Station, Standard Operation, TM4, UC#31, TM4 HS line leak check at SHC and TCS.
|
Both helium spray and helium pressurize on TM4 HS line withUCx31 target are done at SHC and TCS. No leak. |
|