382
|
Thursday, June 20, 2013, 13:47 |
Travis Cave | Spent Target Vault | Standard Operation | | | Spent Target Assay | Ten targets have been assayed or had field
measurements(they were too hot to ship but
were assayed the last time an assay was done) |
|
384
|
Tuesday, June 25, 2013, 13:20 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#6 | Electrical check | Results from the electrical check of TM#1
with the UC#6 target. See attached PDF. |
|
385
|
Tuesday, June 25, 2013, 14:24 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | UC#6 | module move | Module moves of TM#1 with Ta#39 from ITW
to SHC then TM#1 with UCx#6 from SHC to the
conditioning station moves went well. |
|
392
|
Tuesday, July 02, 2013, 10:58 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | UC#6 | module move | TM#1 with UC#6 has been moved from the
conditioning station to the west target station,
move went well. |
|
395
|
Wednesday, July 03, 2013, 10:43 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module move | TM#3 with no target and no source tray
was moved from the north east silo to the
south hot cell the move went well. |
|
403
|
Thursday, July 18, 2013, 10:08 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module move | TM#3 with no target and no source tray
has been moved from the conditioning station
to the north east silo, move went well. |
|
405
|
Tuesday, July 23, 2013, 10:55 |
Travis Cave | ITE | Standard Operation | TM4 | Ta#40 | module move | TM#4 with Ta#40 has been moved from the
east target station to the south hot cell
move went well. |
|
406
|
Tuesday, July 23, 2013, 13:33 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | Ta#40 | Electrical check | Results of electrical check on Ta#40 target
on TM#4 post beam at the south hot cell |
|
407
|
Wednesday, July 24, 2013, 08:40 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | SiC#29 | Electrical check | Electrical check on TM#4 with SiC#29 has
been done. The reading of the magnet coil
and 60kV common is low at 750 ohms, normally |
|
408
|
Wednesday, July 24, 2013, 14:40 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | SiC#29 | module move | TM#4 with SiC#29 has been moved from the
south hot cell to the conditioning station
move went well. |
|
410
|
Thursday, July 25, 2013, 09:37 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | SiC#29 | Electrical check | Electrical check of TM#4 with SiC#29 attached.
Results are pretty much the same as yesterday
for the coil to 60kV common, and anode to |
|
413
|
Monday, July 29, 2013, 14:32 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#40 | Spent target move | Spent target Ta#40 has been placed into
storage. The target was placed in pail #107
and was put into slot 5A of the vault. It |
|
414
|
Tuesday, July 30, 2013, 10:44 |
Travis Cave | ITE | Standard Operation | TM4 | SiC#29 | module move | TM#4 with SiC #29 has been moved from the
conditioning station to the east target station,
move went well. |
|
416
|
Wednesday, July 31, 2013, 11:13 |
Travis Cave | Spent Target Vault | Standard Operation | | | Spent target move | Five spent targets have been removed from
the storage vault and placed into the mini
storage. The target placed into the mini |
 |
418
|
Wednesday, August 14, 2013, 11:50 |
Travis Cave | South Hot-Cell | Maintenance | TM3 | | module move | TM#3 and its new source tray have been
both moved into the south hot cell. |
|
428
|
Tuesday, August 27, 2013, 11:54 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#6 | module move | TM#1 with UCx #6 has been moved to the
south hot cell. |
|
429
|
Tuesday, August 27, 2013, 11:56 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#7 | Electrical check | TM#1 with UCx#7 electrical check, numbers
look good, see PDF for details. |
|
430
|
Tuesday, August 27, 2013, 14:14 |
Travis Cave | ITW | Standard Operation | TM1 | UC#7 | module move | TM#1 with UCx#7 has been moved from the
south hot cell to the west target station. |
|
432
|
Wednesday, August 28, 2013, 14:17 |
Travis Cave | South Hot-Cell | Standard Operation | | UC#6 | Spent target move | Spent target move, UC#6 has been moved
from the south hot cell to the target storage.
The target is in pail 108 and in slot 8C |
|
433
|
Wednesday, August 28, 2013, 14:25 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | no target | module move | TM#3 with no target has been moved from
the conditioning station to the south hot
cell. The fields observed around the containment |
|