ID Date Authordown Category Type Module Target/Number Subject
  382   Thursday, June 20, 2013, 13:47 Travis CaveSpent Target VaultStandard Operation  Spent Target Assay

Ten targets have been assayed or had field measurements(they were too hot to ship but were assayed the last time an assay was done) done on them  over the past two days. Of those that have been assayed we have total of ten shippable targets. See the attached PDF for the latest details of the storage vault.

Attachment 1: Vault_Storage_June_20_2013.pdf
Vault_Storage_June_20_2013.pdf Vault_Storage_June_20_2013.pdf Vault_Storage_June_20_2013.pdf Vault_Storage_June_20_2013.pdf
  384   Tuesday, June 25, 2013, 13:20 Travis CaveSouth Hot-CellStandard OperationTM1UC#6Electrical check

Results from the electrical check of TM#1 with the UC#6 target. See attached PDF.

Attachment 1: TM#1_UC#6_SIS_Target_Elec_Chk.PDF
TM#1_UC#6_SIS_Target_Elec_Chk.PDF
  385   Tuesday, June 25, 2013, 14:24 Travis CaveConditioning StationStandard OperationTM1UC#6module move

Module moves of TM#1 with Ta#39 from ITW to SHC then TM#1 with UCx#6 from SHC to the conditioning station moves went well.

  392   Tuesday, July 02, 2013, 10:58 Travis CaveConditioning StationStandard OperationTM1UC#6module move

TM#1 with UC#6 has been moved from the conditioning station to the west target station, move went well.

  395   Wednesday, July 03, 2013, 10:43 Travis CaveSouth Hot-CellStandard OperationTM3no targetmodule move

TM#3 with no target and no source tray was moved from the north east silo to the south hot cell the move went well.

  403   Thursday, July 18, 2013, 10:08 Travis CaveConditioning StationStandard OperationTM3no targetmodule move

TM#3 with no target and no source tray has been moved from the conditioning station to the north east silo, move went well.

  405   Tuesday, July 23, 2013, 10:55 Travis CaveITEStandard OperationTM4Ta#40module move

TM#4 with Ta#40 has been moved from the east target station to the south hot cell move went well.

  406   Tuesday, July 23, 2013, 13:33 Travis CaveSouth Hot-CellStandard OperationTM4Ta#40Electrical check

Results of electrical check on Ta#40 target on TM#4 post beam at the south hot cell

Attachment 1: TM#4_Ta#40_SIS_Tgt_Elec_Chk_post.PDF
TM#4_Ta#40_SIS_Tgt_Elec_Chk_post.PDF
  407   Wednesday, July 24, 2013, 08:40 Travis CaveSouth Hot-CellStandard OperationTM4SiC#29Electrical check

Electrical check on TM#4 with SiC#29 has been done. The reading of the magnet coil and 60kV common is low at 750 ohms, normally this infinite. Awaiting further instruction on if this is a pass or fail. See attached PDF for the rest of the details.

Attachment 1: TM#4_SiC#29_FEBIAD_Tgt_Elec_Chk.PDF
TM#4_SiC#29_FEBIAD_Tgt_Elec_Chk.PDF
  408   Wednesday, July 24, 2013, 14:40 Travis CaveConditioning StationStandard OperationTM4SiC#29module move

TM#4 with SiC#29 has been moved from the south hot cell to the conditioning station move went well.

  410   Thursday, July 25, 2013, 09:37 Travis CaveConditioning StationStandard OperationTM4SiC#29Electrical check

Electrical check of TM#4 with SiC#29 attached. Results are pretty much the same as yesterday for the coil to 60kV common, and anode to 60kV common. See attached pdf for details.

Attachment 1: TM#4_SiC#29_FEBIAD_TgtElecChkCS_.PDF
TM#4_SiC#29_FEBIAD_TgtElecChkCS_.PDF
  413   Monday, July 29, 2013, 14:32 Travis CaveSpent Target VaultStandard Operation Ta#40Spent target move

Spent target Ta#40 has been placed into storage. The target was placed in pail #107 and was put into slot 5A of the vault. It had a field of 224mSv/hr upon removal from the south hot cell. See attached PDF for more details.

Attachment 1: Vault_Storage_July_29_2013.pdf
Vault_Storage_July_29_2013.pdf Vault_Storage_July_29_2013.pdf Vault_Storage_July_29_2013.pdf Vault_Storage_July_29_2013.pdf
  414   Tuesday, July 30, 2013, 10:44 Travis CaveITEStandard OperationTM4SiC#29module move

TM#4 with SiC #29 has been moved from the conditioning station to the east target station, move went well.

  416   Wednesday, July 31, 2013, 11:13 Travis CaveSpent Target VaultStandard Operation  Spent target move

Five spent targets have been removed from the storage vault and placed into the mini storage. The target placed into the mini storage are UO#3, UC#'s  3,4,5 and SIC#23. See attached PDFs for vault details.

Attachment 1: Vault_Storage_July_31_2013.pdf
Vault_Storage_July_31_2013.pdf Vault_Storage_July_31_2013.pdf Vault_Storage_July_31_2013.pdf Vault_Storage_July_31_2013.pdf
Attachment 2: Mini_Vault_Storage_July_31_2013.pdf
Mini_Vault_Storage_July_31_2013.pdf Mini_Vault_Storage_July_31_2013.pdf Mini_Vault_Storage_July_31_2013.pdf Mini_Vault_Storage_July_31_2013.pdf
  418   Wednesday, August 14, 2013, 11:50 Travis CaveSouth Hot-CellMaintenanceTM3 module move

TM#3 and its new source tray have been both moved into the south hot cell.

  428   Tuesday, August 27, 2013, 11:54 Travis CaveSouth Hot-CellStandard OperationTM1UC#6module move

TM#1 with UCx #6 has been moved to the south hot cell.

  429   Tuesday, August 27, 2013, 11:56 Travis CaveSouth Hot-CellStandard OperationTM1UC#7Electrical check

TM#1 with UCx#7 electrical check, numbers look good, see PDF for details.

Attachment 1: TM#1_UC#7__TgtElecChk_SHC_.PDF
TM#1_UC#7__TgtElecChk_SHC_.PDF
  430   Tuesday, August 27, 2013, 14:14 Travis CaveITWStandard OperationTM1UC#7module move

TM#1 with UCx#7 has been moved from the south hot cell to the west target station.

  432   Wednesday, August 28, 2013, 14:17 Travis CaveSouth Hot-CellStandard Operation UC#6Spent target move

Spent target move, UC#6 has been moved from the south hot cell to the target storage. The target is in pail 108 and in slot 8C of the vault. See attached PDF for details.

Attachment 1: Vault_Storage_August_28_2013.pdf
Vault_Storage_August_28_2013.pdf Vault_Storage_August_28_2013.pdf Vault_Storage_August_28_2013.pdf Vault_Storage_August_28_2013.pdf
  433   Wednesday, August 28, 2013, 14:25 Travis CaveConditioning StationStandard OperationTM3no targetmodule move

TM#3 with no target has been moved from the conditioning station to the south hot cell. The fields observed around the containment box of the module ranged from 0.80 mSv/hr to 1.8mSv/hr..