  RH-ISAC, Page 22 of 140  Not logged in ELOG logo
ID Date Author Category Type Module Target/Number Subjectdown
  2323   Thursday, May 19, 2022, 15:05 Frank SongITEStandard OperationTM4UCx#37UCx#37 P2N connection on TM4

 TM4 with UCx#37 was connected in ITE. Attachment available.

Attachment 1: 01_UCx37_P2N_connection_on_TM4.jpg
01_UCx37_P2N_connection_on_TM4.jpg
Attachment 2: 02_UCx37_P2N_connection_on_TM4.jpg
02_UCx37_P2N_connection_on_TM4.jpg
Attachment 3: 03_UCx37_P2N_connection_on_TM4.jpg
03_UCx37_P2N_connection_on_TM4.jpg
  2117   Friday, July 03, 2020, 08:46 chad fisherSouth Hot-CellStandard OperationTM4UcX#30UCx#30 installed onto tm4

UCx#30 has been installed onto TM4 with new high current fasteners torqued to 130 in lbs.

  77   Tuesday, March 13, 2012, 09:43 chad fisherSouth Hot-CellStandard OperationTM1UCx#3UCx#3 to spent vault

UCx#3 was packaged into a spent can, double bagged and the bag and cans filled with argon as much as possible. Lid was attached and can moved to the storage vault. The target was placed in in Pail 93, and placed into slot 1C of the vault, it was 11.7mSv/hr when removed from the south hot cell. See attached file for latest vault details

Attachment 1: Vault_Storage_March_13_2012.pdf
Vault_Storage_March_13_2012.pdf Vault_Storage_March_13_2012.pdf Vault_Storage_March_13_2012.pdf Vault_Storage_March_13_2012.pdf
  57   Friday, November 18, 2011, 09:56 chad fisherSouth Hot-CellStandard OperationTM1UCx#3UCx#3 Installation

UCx#3 has been installed on TM1.

Leak check also complete.

Base Leak Rate 0.0 x 10-9

Pressure 0.0x10-4

Two checks on upper heat shield joint - no response (2 sec spray/check)

Two checks on lower heat shield joint - no response(2 sec spray /check)

10 sec flood of all heat shield joints - no response

Electrical check coomplete.

  76   Tuesday, March 13, 2012, 09:42 chad fisherSouth Hot-CellStandard OperationTM1UCx#3UCx#3 Autopsy

An autopsy was performed on UCx#3 yesterday afternoon. This autopsy followed the plan written by Anders. Indeed, both sides of the target oven had seperated from the central block.Pictures were taken by Anders and Pierre.

After the disection the target was placed back in a can under argon. Any small piece were placed in a zip lock bag and also put in the can under argon.

  78   Tuesday, March 13, 2012, 12:24 Anders MjosSouth Hot-CellStandard OperationTM1UCx#3UCx#3 Autopsy

chad fisher wrote:

An autopsy was performed on UCx#3 yesterday afternoon. This autopsy followed the plan written by Anders. Indeed, both sides of the target oven had seperated from the central block.Pictures were taken by Anders and Pierre.

After the disection the target was placed back in a can under argon. Any small piece were placed in a zip lock bag and also put in the can under argon.

Pictures are available on DocuShare:

https://documents.triumf.ca/docushare/dsweb/View/Collection-8189

ISAC e-log entries:

https://web.accel.triumf.ca/isac_elog/Elog_shift_view.pl?shiftid=10803

See attachment for autopsy plan.

 

 

Attachment 1: Inspection_of_UCx#3_in_the_South_Hot_Cell.docx
  2059   Wednesday, February 05, 2020, 08:22 chad fisherSouth Hot-CellStandard OperationTM4UCx#29UCx#29 removed

UCx#29 has been removed from TM$ and placed in a pail backfilled with argon until it can be moved to the storage vault.

  2012   Wednesday, October 23, 2019, 07:58 chad fisherSouth Hot-CellStandard OperationTM4UCx#28UCx#28 Removed

UCx#28 has been removed from TM4. Guard screws on 5(10) pin connector had to be removed to get the connector to un-seat properly for removal.

  1976   Thursday, September 05, 2019, 11:37 chad fisherSouth Hot-CellStandard OperationTM4UCx#27UCx#27 install

Dummy Ta target has been removed from TM4 and UCx#27 installed

  1469   Tuesday, March 28, 2017, 10:44 chad fisherSouth Hot-CellStandard OperationTM4UCx#19UCx#19 Installed

UCx#19 has been installed onto TM4. High current fasteners torqued to 130 in lbs. Has been leak and electrical checked and is ready to leave hot cell.

  1430   Friday, January 27, 2017, 08:50 chad fisherSouth Hot-CellStandard Operation  UCx#18 and Ta#50 autopsy and spent target move

On Thursday, January 26th UCx#18 and Ta#50 were inspected and packaged into spent target pails, move to storage vault.

  1195   Wednesday, April 06, 2016, 14:03 chad fisherSouth Hot-CellStandard OperationTM4Ta#47UCx#14 removed Ta#47 installed

UCx#14 has been removed from TM4 and Ta#47 installed. No marks on 9 pin connector on UCx#14.

  1135   Wednesday, November 25, 2015, 14:13 chad fisherSouth Hot-CellStandard OperationTM4UC#14UCx#14

UCx#14 installed onto TM4. High current fasteners torqued to 130 in lbs.

  2062   Wednesday, February 05, 2020, 11:03 David WangSouth Hot-CellStandard OperationTM4UCx 29UCx 29 post run electrical check

UCx 29 TM4 post run electrical check is done before target is removed. Everything is normal on measurements.

Attachment 1: UCx29_post_run_electrical_check..pdf
UCx29_post_run_electrical_check..pdf
  2018   Wednesday, October 30, 2019, 11:18 David WangITWStandard OperationTM4UCx 29UCx 29 connection checklist

See attachment

Attachment 1: UCx_29_connection_checklist.pdf
UCx_29_connection_checklist.pdf UCx_29_connection_checklist.pdf UCx_29_connection_checklist.pdf
  2001   Friday, October 04, 2019, 16:50 David WangSouth Hot-CellStandard OperationTM4 UCx 28 target with TM4 SHC leak check and electrical check.

TM4 HS Leak check result is good . No leak. electrical check after target installation: Bias to chassis 550 Mohm. Coils are shorted each other and shorted to 60 KV bias. ABCD to 60KV bias 500V Megga measurement are 100M at least which is good. EE to bias are OL at 500V. The electrical check result is good.

  671   Monday, June 02, 2014, 11:25 chad fisherSouth Hot-CellStandard OperationTM1UCx #9UCx #9 Installed
UCx #9 has been installed.
  2310   Tuesday, March 01, 2022, 11:51 David WangSpent Target VaultMaintenance  UCx #32 has been repacked in NHC.

UCx 32# P2N target in vault slot 1B is repacked is morning for Ferran to take out his samples( in two small plastic containers) stored in pail last July when Chad did the spent target job. The job went well.  Old pail # is 254# and new pail # is 233. It is put back to 1B in vault.

  20   Thursday, August 18, 2011, 13:12 chad fisherSouth Hot-CellStandard OperationTM1UCx #2UCx #2 Installation

UCx #2 has been installed onto TM1.

Installation went well except the left leg got bent slightly sometime between testing on the jig and installation onto the module (probably during removal for the argon filled bag). Leg was gentle offered into place and its clearance with the heat shield double checked with both a mirror and goose neck camera. Leg was close to ther heat shield but appeared to have clearance. Anders and John Wong viewed this and deemed it ok. Video images of this clearance were recorded.

Leak checking was also completed successfully:

Base pressure on the leak detector was a constant 0.0 x 10-4, Stable leak rate was an unwavering 0.0 x 10-9.

Both heat sheild circuits were checked twice (starting with the highest gland) and sprayed with a 2 second burst of helium into the test hole in the nut. No reponses were seen after 1 minute an any of the circuits.

Bevan Moss and David Wang performed an electrical check which they relayed to me that the module with target installed had passed.

 

  1428   Friday, January 27, 2017, 08:44 chad fisherSouth Hot-CellStandard OperationTM2Ta#50UCx #18 - Ta Feibiad Dummy installed. Target Change Waterline interference

On Tuesday, January 24th UCx#18 was removed from TM2 and Ta febiad dummy installed. I encountered the same issue mounting the new target as last time. Was able to determine that the issue is the routing of the waterlines to the right-hand (as viewed from the operator) high current tube heater. The lines interfer the the target mounting plate (bottom right hand corner).

Attachment 1: TM2_Waterline_interference.jpg
TM2_Waterline_interference.jpg