ID Date Author Category Type Module Target/Number Subjectdown
  1891   Thursday, March 14, 2019, 10:25 chad fisherSouth Hot-CellRepairTM2 Water Block Polishing status

Phase 2 (intermediate) and Phase 3 (Final) polishing is complete on all water blocks on TM2 (minus ground electrode circuit which has only had a cursory cleaning). Phase 2 with 2000 grit wet sand paper and isopropynol for 1 minute with tool at 75 psi, Phase 3 with Veltex polishing cloth for 1 minute with tool at 75 psi.

  335   Thursday, May 09, 2013, 14:23 chad fisherSouth Hot-CellRepairTM3 Water Block Jig Removal

The source tray side of the water block jig has been removed in preparation for moving the module to the  conditioning station for electrical tests.

  323   Friday, April 26, 2013, 11:20 chad fisherSouth Hot-CellRepairTM3 Water Block Jig (back half)

The back half of the water block jig (services tray side) has been sucessfully located onto the module.

About 50% of the waterblocks have centered themselfs it their respective cups and the rest look good for concentricity but will require some gentle wiggling to get them to seat.

  379   Thursday, June 13, 2013, 09:21 chad fisherSouth Hot-CellDevelopment  Warm Cell Mock-up

the warm cell mock-up has been inserted into the warm cell and final preparation for the remote test are being made.

  2420   Wednesday, March 01, 2023, 09:34 David WangCoolingMaintenance  Visual inspection of HALCW for possible small water leak or drip.

I visually inspected HALCW system including water station section, both target pits, and de-ionizer system.  No small leak and drip was found .  The inspection in both target pits will be repeated after flow sensors are replaced.

  2271   Friday, November 19, 2021, 12:48 Adam NewsomeSouth Hot-CellDevelopment  Vertical motion limit switch installation

A rotary limit switch was installed, attached to the shaft adjacent to the drive motor for the vertical drive system. This limit switch is not yet wired to the control system and operational - this will be done at a future date and the e-log will be updated.

Relevant electrical drawings: IRH2083 to IRH2085

 

Edit (2022-03-02): see e-log https://elog.triumf.ca/TIS/RH-ISAC/2309

  292   Monday, April 08, 2013, 16:16 Bevan MossConditioning StationStandard OperationTM1Ta #39Venting with Argon

 TM1 started venting at 4:15 pm with Argon. I will leave the valve open over night.

  1435   Tuesday, February 07, 2017, 15:57 Isaac EarleNorth Hot-CellDevelopment  Ventilation Ducting Gasket Installed

 Lead gasket IRH1633 was installed today according to assembly drawing IRH1618 Rev B.

  269   Monday, March 18, 2013, 15:28 Bevan MossConditioning StationStandard OperationTM4CS Test Target #1Vented With Argon

 The conditioning station has been vented with argon. Time taken is not known but it is less than 3 hours. See attached picture for convectron gauge readings. CG1A is in air.

  1950   Monday, July 15, 2019, 13:29 David WangConditioning StationDevelopmentTM4 Vacuum surge when TM4 B line iwas supplied with water.

Yesterday, TM4 B line was supplied with water at TCS for testing.  TCS: IG1 and IG2 had big response on it. See attachment. The water was disconnected right away, and line was purged. Vacuum recovered after overnight pump.

  1149   Friday, December 18, 2015, 11:42 Anders MjosConditioning StationRepair  Vacuum gauges not reading correctly

 It was found that the conversion from voltage to vacuum (Torr) in EPICS is not correct for the XGS-600 controllers in use at the TCS. EPICS did not correspond to local values displayed on the controller. An e-fault has been submitted.

  1150   Monday, December 21, 2015, 13:27 Anders MjosConditioning StationRepair  Vacuum gauges not reading correctly

Anders Mjos wrote:

 It was found that the conversion from voltage to vacuum (Torr) in EPICS is not correct for the XGS-600 controllers in use at the TCS. EPICS did not correspond to local values displayed on the controller. An e-fault has been submitted.

 EPICS conversion updated and corrected by Mike Rowe.

  1067   Friday, September 11, 2015, 14:31 Anders MjosConditioning StationMaintenanceTM2ZrC#7Vacuum gauge and EPICS read back calibration

The corelation betwenn the local value on the gauge controllers and the read back valiues in EPICS was compared. Data can be found in a previous  e-log

  481   Monday, September 30, 2013, 16:02 Bevan MossConditioning StationStandard OperationTM3NiO#2Vacuum

 The roughing pump for TCS was started at ~3:00 and the turbo's turned on at ~4:00. This is the minimum time for the module to pump down.

  1279   Friday, July 08, 2016, 16:56 Anders MjosConditioning StationRepair  VFD21 OL1 fault on Chiller

Plant Services group (Tony) will contact a service tech on Monday.

Water system will be switched off over the weekend.

  1286   Thursday, July 14, 2016, 13:25 Anders MjosConditioning StationRepair  VFD21 OL1 fault on Chiller

Anders Mjos wrote:

Plant Services group (Tony) will contact a service tech on Monday.

Water system will be switched off over the weekend.

Thursday, July 14, 2016, 13:24: Claus from Daikin is on site to troubleshoot.

The VFD driven fan motor has failed. Temporarily blocked air-flow through failed fan to improve air-flow to radiator. A new motor will be ordered (Curtis).

Thursday, July 14, 2016, 15:39: Stopped cooling system for the day


Friday, July 15, 2016, 08:16: Cooling system started

Friday, July 15, 2016, 15:00; Cooling system stopped.

  1323   Thursday, August 18, 2016, 10:35 Anders MjosConditioning StationRepair  VFD21 OL1 fault on Chiller

Anders Mjos wrote:

Anders Mjos wrote:

Plant Services group (Tony) will contact a service tech on Monday.

Water system will be switched off over the weekend.

Thursday, July 14, 2016, 13:24: Claus from Daikin is on site to troubleshoot.

The VFD driven fan motor has failed. Temporarily blocked air-flow through failed fan to improve air-flow to radiator. A new motor will be ordered (Curtis).

Thursday, July 14, 2016, 15:39: Stopped cooling system for the day


Friday, July 15, 2016, 08:16: Cooling system started

Friday, July 15, 2016, 15:00; Cooling system stopped.

 Thursday, August 18, 2016, 10:34: The motor was replaced today by Claus from Daikin. System is running normally again.

  238   Friday, January 18, 2013, 16:56 Grant MinorConditioning StationStandard OperationTM4 VAT valve btwn roughing and nuc. vent. closed

Bevan attempted to start pumping down on TM4 today remotely but there was an issue.  He will report on Monday.

I went into the Target Hall this afternoon while on the phone with Bevan and performed the following:

- Checked the knurled vent valves on the side of each turbo, both were found to be in the tightened position (all the way clockwise)

- Closed the VAT valve between the scroll pump and the nuclear ventilation

  1561   Monday, June 19, 2017, 07:29 David WangConditioning StationStandard OperationTM2 Update TH MS project schedule.

Update TH MS project schedule. See attachment 1,2.

  1433   Friday, February 03, 2017, 11:49 David WangConditioning StationStandard Operation  Update 2017 winter shutdown TH schedule.

Update 2017 winter shut down target hall schedule. See attachments