ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
Text |
|
|
393
|
Wednesday, July 03, 2013, 08:43 |
chad fisher | South Hot-Cell | Standard Operation | | | Ta#39 Transfered to spent target storage vault | |
|
|
394
|
Wednesday, July 03, 2013, 08:44 |
chad fisher, Travis Cave | South Hot-Cell | Standard Operation | | | Ta#39 Transfered to spent target storage vault | Ta#39 has been transferred to spent target
storage vault. Ta#39 was placed into pail
#106 and placed into spot of 4C of the spent |
|
|
395
|
Wednesday, July 03, 2013, 10:43 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | module move | TM#3 with no target and no source tray
was moved from the north east silo to the
south hot cell the move went well. |
|
|
397
|
Friday, July 05, 2013, 09:22 |
chad fisher | South Hot-Cell | Repair | TM3 | | Service Tray Water Block Inspection | I have inspected the service tray water
block and suggest that they SHOULD be cleaned/polished
before we install the new source tray. |
|
|
406
|
Tuesday, July 23, 2013, 13:33 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | Ta#40 | Electrical check | Results of electrical check on Ta#40 target
on TM#4 post beam at the south hot cell |
|
|
407
|
Wednesday, July 24, 2013, 08:40 |
Travis Cave | South Hot-Cell | Standard Operation | TM4 | SiC#29 | Electrical check | Electrical check on TM#4 with SiC#29 has
been done. The reading of the magnet coil
and 60kV common is low at 750 ohms, normally |
|
|
412
|
Friday, July 26, 2013, 11:06 |
David Wang | South Hot-Cell | Standard Operation | | | The steel shielding plug has been put on theSHC top in target hall | to reduce the radioactive shining from
SHC Ta# 40 target. |
|
|
418
|
Wednesday, August 14, 2013, 11:50 |
Travis Cave | South Hot-Cell | Maintenance | TM3 | | module move | TM#3 and its new source tray have been
both moved into the south hot cell. |
|
|
420
|
Thursday, August 15, 2013, 09:32 |
chad fisher | South Hot-Cell | Repair | TM3 | | TM3 source tray installation status |
The installation of the module
side water block jig has been successful.
During |
|
|
423
|
Wednesday, August 21, 2013, 20:36 |
Grant Minor | South Hot-Cell | Repair | TM3 | | TM3 module-side water block sealing surface inspection (post polishing) | The water block sealing surfaces on the
module-side of TM3 were polished this week
by Chad Fisher, using his air-ratchet controlled |
|
|
424
|
Thursday, August 22, 2013, 19:38 |
Grant Minor | South Hot-Cell | Repair | TM3 | | TM3 Rev 3 source tray - water blocks connected and torqued | After a great struggle with the water block
jigs, the TM3 source tray was finally advanced
fully into the service tray and all water |
6x |
|
425
|
Friday, August 23, 2013, 18:32 |
Grant Minor | South Hot-Cell | Repair | TM3 | | TM3 Rev 3 - steerer wire broken from connector on module side | While continuing on the TM3 Rev 3 source
tray installation, Chad noticed today that
one of the steerer wires is broken and has |
|
|
426
|
Monday, August 26, 2013, 18:22 |
Grant Minor | South Hot-Cell | Repair | TM3 | | TM3 Rev 3 - all connetions made except steerers, IMG, and entrance window | Today Chad finished making all connections
to the new source tray, except for:
- steerers - broken wire, must be |
8x |
|
428
|
Tuesday, August 27, 2013, 11:54 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#6 | module move | TM#1 with UCx #6 has been moved to the
south hot cell. |
|
|
429
|
Tuesday, August 27, 2013, 11:56 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#7 | Electrical check | TM#1 with UCx#7 electrical check, numbers
look good, see PDF for details. |
|
|
432
|
Wednesday, August 28, 2013, 14:17 |
Travis Cave | South Hot-Cell | Standard Operation | | UC#6 | Spent target move | Spent target move, UC#6 has been moved
from the south hot cell to the target storage.
The target is in pail 108 and in slot 8C |
|
|
435
|
Thursday, August 29, 2013, 09:08 |
chad fisher | South Hot-Cell | Repair | TM3 | | Heat Shield Circuit Leak | The heat shield circuit was pressurized
with air (15-20 psi) and snoop applied to
the water block joint and brazes. Bubbles |
|
|
436
|
Thursday, August 29, 2013, 10:09 |
Bevan Moss | South Hot-Cell | Repair | TM3 | | Heat Shield Circuit Leak |
|
|
|
437
|
Thursday, August 29, 2013, 12:03 |
Grant Minor | South Hot-Cell | Repair | TM3 | no target | Heat Shield Circuit Leak |
|
|
|
438
|
Thursday, August 29, 2013, 17:16 |
Bevan Moss | South Hot-Cell | Repair | TM3 | N/A | Heat Shield Repair | Today Chad entered the south hot
cell on work permit 2013-08-29-3 to repair
the leaking heat shield line. The heat shield |
|