  58   Friday, November 18, 2011, 11:09 Travis CaveConditioning StationStandard OperationTM1UCx#3Module moveTM#1 with UCx#3 has been moved from the
south hot cell to the conditioning station.
Move went well.
  
  62   Thursday, November 24, 2011, 10:39 Travis CaveITWStandard OperationTM1UCx#3Module moveTM#1 with UCx#3 moved from conditioning
station to west target station. Move went
well.
  
  63   Thursday, November 24, 2011, 10:40 Travis CaveITWStandard OperationTM1UCx#3Module moveTM#1 with UCx#3 moved from the conditioning
station to the west target station.
  
  64   Thursday, December 15, 2011, 13:08 Travis CaveSpent Target VaultStandard Operation  Spent Target AssaySpent target assay completed. A total of
16 target were looked at, 13 were low enough
to be assayed and those 13 are at shippable
 Vault_Storage_December_14_2011.pdf 
  65   Wednesday, January 04, 2012, 13:49 Travis CaveSpent Target VaultStandard Operation  Moving the spent targets to mini storage.Well the first of this year's lucky winners
to win a fabulous one way trip to Chalk River
are as follows. UC#1, UC#2, Ta#25, Ta#26,
  
  66   Thursday, January 05, 2012, 11:40 Travis CaveSpent Target VaultStandard Operation  Target swapping Looks like the UC target s #1 and #2 were
found invalidprize winners for their all
inclusive trip to Chalk River and have thus
 Vault_Storage_January_5_2012.pdfMini_Vault_Storage_January_5_2012.pdf 
  69   Thursday, January 12, 2012, 08:43 Travis CaveSpent Target VaultStandard Operation  Spent targets to F-308sAll targets in the mini storage have been
moved to F-308s and those flasks have been
moved over to rad waste. The transfer of
  
  73   Monday, March 12, 2012, 09:19 Travis CaveSouth Hot-CellStandard OperationTM1UCx#3module moveTM#1 with UC#3 was moved from the west
maa to the south hot cell, move went well
  
  75   Monday, March 12, 2012, 11:54 Travis CaveSouth Hot-CellStandard OperationTM1no targetmodule movedTM#1 has been moved from the south hot
cell to the north east silo, move went well.
  
  82   Thursday, April 12, 2012, 09:38 Travis CaveConditioning StationStandard OperationTM1no targetMove ot TM#1TM#1 has been moved from the NE silo to
the Conditioning Station.
  
  87   Tuesday, April 17, 2012, 11:30 Travis CaveSouth Hot-CellStandard OperationTM1no targetmodule movedTM#1 moved from conditioning station to
the south hot cell, the module had a field
of 16mSv/hr.  The move was not without
  
  88   Thursday, April 19, 2012, 09:36 Travis CaveSouth Hot-CellStandard OperationTM1Nb#6Electrical checkElectrical check has been completed of
TM#1 with Nb#6 attached. Our new micro-ohm
meter was also used for the first time for
 Elec_Check_TM1_Nb6.PDF 
  90   Friday, April 20, 2012, 14:07 Travis CaveConditioning StationStandard OperationTM1Nb#6module moveTM#1 with Nb#6 is now in the conditioning
station. The fields of the module at the
south cell was 15.8mSv/hr. The move was uneventful.
  
  92   Tuesday, April 24, 2012, 10:02 Travis CaveITWStandard OperationTM1Nb#6module moveTM#1 with Nb#6 from the conditioning station
to the west target station, move was uneventful.
Mike LaRoss was there today for move in place
  
  99   Monday, May 14, 2012, 12:37 Travis CaveITEStandard OperationTM4SiC#26module moveTM#4 with SiC #26 was moved from the East
Station to the South Hot Cell. Bevan was
at the helm of the PLC. There was no issue
  
  100   Tuesday, May 15, 2012, 11:45 Travis CaveSouth Hot-CellStandard OperationTM4SiC#26Electrical checkResults of the electrical check of TM#4
with SiC#26 attached post beam.
 TM#4_SiC#26_FEBIAD_post_beam.PDF 
  102   Tuesday, May 15, 2012, 14:29 Travis CaveSouth Hot-CellStandard OperationTM4no targetmodule moveTM#4 moved from the south hot cell to the
north east storage silo. No issues with the
move.
  
  103   Wednesday, May 16, 2012, 10:35 Travis CaveSpent Target VaultStandard Operation SiC#26Spent target moveSiC #26 was moved from the south hot cell
into storage today. The target was is in
pail # 94 and was placed in slot 1B in the
 Vault_Storage_May_16_2012.pdf 
  104   Thursday, May 17, 2012, 14:08 Travis CaveSouth Hot-CellStandard OperationTM4no targetmodule moveTM#4 has been moved from the north east
silo to the south hot cell for target installation. 
No problems with the move.
  
  106   Friday, May 18, 2012, 08:29 Travis CaveSouth Hot-CellStandard OperationTM4SiC#27Electrical checkTM#4 with SiC#27 has had its electrical
check. See attached PDF for details.
 TM#4_SiC#27_pre_beam.PDF 