1905
|
Friday, April 05, 2019, 13:44 |
chad fisher | Spent Target Vault | Development | | | 2019 Pail drop tests |
- Drop test performed January 8, 2019 with 25 lb target, UN pail and lug cover. Drop failed. Lug cover half removed. Pictures and video in docushare collection 24626.
- Second test January8, 2019 UN pail, "new" dish cover, old lock lever ring, 25 lb target. Single drop from 1.2m onto latch, no sealant. No leaks 24 hours later. Pictures in docushare collection 24626
- Drop test performed April 2, 2019 repeat of previous test using until that was loaded in north hot cell test. Target punctured can. Pictures in docushare collection 24626.
- Drop test performed April 5, 2019 repeat of previous test with the addition of a aluminum sleeve (0.05" thick) inside the pail between pail and target.
New UN rated pail with 9.55 kg target, 1.2 kg 16 gauge Al sleeve (10.75 OD x 14.75" tall), 3 liters of water with red food coloring no sealant on gasket.
First drop standard drop test from 1.2m onto latch
Second drop test 1.2m onto bottom of pail
Third drop 1.2m onto side of pail
Drops 4-6 1.2m onto lid
Pail was left inverted for an hour after the first three drops with no leaks after 1 hour.
No leaks after the remaining 3 drops .Bottom very damaged suggesting need for protective disc in bottom of pail.
Pictures can be found in docushare Collection-24627
- Drop tests performed May 2, 2019 with 9.7 kg target, 1.346 kg of mixed module and target components, sleeve and disc. First drop on latch from 1.2m, no leak, second drop straight on bottom from 1.2m, no leak, third drop on side from 1.2m leak. Drop test described in more detail in document drop test witness document on docushare. Pictures and video in docushare collection 24626.
|
1153
|
Friday, January 22, 2016, 14:24 |
David Wang | South Hot-Cell | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule (sketch) |
Post a sketch of 2016 winter shut down target hall schedule. see attachment 1,2
UPDATE THE SCHEDULE ACCORDING TO CYCLOTRON SIDE JOB. SEE ATTACHMENTS 3,4 |
Attachment 1: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 2: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 3: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 4: 2016_winter_shut_down__target_hall_schedule.mpp
|
1154
|
Friday, February 12, 2016, 13:00 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule |
2016 Winter shut down target hall schedule. See attachments1,2.
update the schedule weekly. Everything is on time so far. see attachment 3,4.
Update the schedule according to beam new beam schedule and target process. see attachment 5,6 |
Attachment 1: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 2: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 3: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 4: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 5: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 6: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
1163
|
Friday, March 04, 2016, 13:58 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule |
Update Schedule according to changes.See attachment1, 2.
Re-post it after some minor correction See attachment 3,4.
Update schedule according changes. See attachments 5,6
update schedule according to changes. See attachment 7,8 |
Attachment 1: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 2: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 3: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 4: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 5: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 6: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 7: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 8: 2016_winter_shut_down__target_hall_schedule.mpp
|
1165
|
Monday, March 14, 2016, 15:22 |
David Wang | Conditioning Station | Standard Operation | TM2 | | 2016 Winter Shut Down Target Hall Schedule |
update schedule according to change. See attachment 1,2
|
Attachment 1: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 2: 2016_winter_shut_down__target_hall_schedule.mpp
|
1183
|
Wednesday, March 30, 2016, 08:40 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule |
update the schedule according to changes.See attachment1, 2. |
Attachment 1: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 2: 2016_winter_shut_down__target_hall_schedule.mpp
|
1202
|
Friday, April 08, 2016, 13:16 |
David Wang | Conditioning Station | Standard Operation | | | 2016 Winter Shut Down Target Hall Schedule |
Update schedule weekly .see attachment 1,2 |
Attachment 1: 2016_winter_shut_down__target_hall_schedule.mpp
|
Attachment 2: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
1214
|
Friday, April 22, 2016, 14:07 |
David Wang | Conditioning Station | Standard Operation | TM2 | | 2016 Winter Shut Down Target Hall Schedule |
Weekly update.This is the last update on 2016 winter shut down schedule. The new TH schedule for beam130 will be posted weekly after this. All jobs in winter shut down schedule were finished on time.
|
Attachment 1: 2016_winter_shut_down__target_hall_schedule.pdf
|
|
Attachment 2: 2016_winter_shut_down__target_hall_schedule.mpp
|
848
|
Wednesday, February 25, 2015, 10:44 |
David Wang | ITW | Maintenance | | | 2015 shut dwon ITW water sensor coils and pedal wheels replacement |
Dan and I replaced pedal wheels and coils on ITW water flow sensors. It is a shut down job we did every two years. See attachment for detail. |
Attachment 1: 2015_shut_down_ITW_water_sensors__replacements.pdf
|
|
847
|
Monday, February 23, 2015, 12:28 |
David Wang | ITE | Maintenance | | | 2015 shut down coils and pedal wheels replacement on ITE water flow sensors. |
Dan and I replaced pedal wheels and coils on ITE water flow sensors. It is a shut down job we did every two years. See attachment for detail. |
Attachment 1: 2015_shut_down_ITE_water_sensors__replacements.pdf
|
|
2427
|
Monday, March 13, 2023, 11:25 |
Carla Babcock | ITE/ITW | Development | | | 10kOhm resistors installed in ITE/ITW faraday cages |
On Sept. 14 2022, a 10kOhm 30W resistor was installed in each target station faraday cage, in line with the HV bias supply. This was an effort to reduce the current draw from the BIAS supply and protect the power supply controls cards which have been repeatedly breaking due to HV sparks (we think). In the end we still broke cards after the installation, so it doesn't seem to have helped. See below for details on the electrical side:
At 30kV, HV currents are around 100-150uA, meaning the voltage drop over the resistor is around 1.5V. When operating at higher voltages, with higher current draw, the voltage across the resistor could be over 2V and we could get into a situation where it would have an effect outside the normal adjustments needed on the mass separator. We made this decision based on the fact that the power supply's setting resolution is on the order of 1 x 10-4.
When the resistance of the water changes, this affects the current draw from the power supply and this in turn affects the voltage over this resistor. Based on some sample numbers of running times, there is not much variation in the current except from sparks and if there is some issue, like water leaking between HV and ground. During normal running, the voltage change across the resistor should be less than 0.5V during normal operation. This is on the same order as the 8 hour stability of the power supply.
|
Attachment 1: ITE_ITW_BIASresistor.docx
|
2688
|
Monday, September 23, 2024, 11:31 |
David Wang | South Hot-Cell | Development | TM3 | | 10 pins lectrical check result after insulator is installed on water cap C. |
10 pins lectrical check result after insulator is installed on water cap C.
pin 14 to 60kv bias has 20 Kohm @250V Megga check. The rest check on ohmmeter and megga @250 are either OLor over 25Mohm which are good. |
1450
|
Tuesday, March 14, 2017, 11:46 |
chad fisher | South Hot-Cell | Maintenance | | | 'Z' motion cable dry run |
Did a dry run with the latest procedure with Dan Mcdonald. Elapsed time was approximately 30 min. |
2191
|
Tuesday, February 23, 2021, 09:00 |
David Wang | Assembly/Bench Test | Maintenance | | | target staion vacuum pumps inspection. |
Edi and I inspected roughing pump ITM MP1, primary backup pump ITHMP1, and secondary backup pump ITHMP2. We checked oil level and color on all pumps. Refilled lubricant to ITMMP1. ITHMP1 and MP2 oil level is fine. ITH MP1 oil color is darker than MP2. But, both them are ok still. Shielding block has been restored after the job. |
1093
|
Tuesday, October 06, 2015, 13:00 |
David Wang | ITE | Repair | TM4 | | spark on top of TM4 in ITE |
During the weekend condition The TM4 spark at 30KV without vacuum response. It is confirmed the spark is from the top TM4 this morning.The flexible cables in a black wire sleeve which is used for febiad X pin connection drooped too close to the TM4 surface plate, and caused the sparking. The problem is fixed by Anders and David. The cables is put back where it should stay. After test, no sparking on the top. |
2227
|
Thursday, June 10, 2021, 14:54 |
David Wang | North Hot-Cell | Standard Operation | TM2 | UCX33 | UCX 33 on TM2 electical check at NHC. |
TM2 UCX33# electrical check and leak check results. See attachment. |
Attachment 1: UCX33_TM2_electrical_check.pdf
|
|
2337
|
Wednesday, June 22, 2022, 09:14 |
David Wang | South Hot-Cell | Standard Operation | TM2 | SiC#42 and SiC#43. | Three of TM2 moves related to SiC#42 to SiC #43 target switching job. |
Monday morning June 20th: TM2 with SiC # 42 was moved from ITW to NHC.
Monday afternoon: TM2 with no target was moved from NHC to SHC due to 10 pin connector guide pin loose issue. The guide pin has to be moved out in SHC due to NHC manipulator configuration limit .
Monday afternoon: TM2 with SiC # 43 was moved from SHC to ITW.
all module moves are smooth. |
2054
|
Thursday, January 30, 2020, 10:22 |
David Wang | ITW | Standard Operation | TM4 | | TM4 water lines helium pressure leak check. |
TM4 internal water lines helium pressure leak check at ITW : 70psi helium 5 minutes on each circuits. Base leak rate 0.0X E-9 atm.cc/sec. Base pressure 0.0X E-4torr. Only B line(Oven -) has a tiny 1.5Xe-9 atm.cc/sec response on LD during the check . All others all perfect good. |
2212
|
Thursday, April 22, 2021, 08:41 |
David Wang | South Hot-Cell | Repair | TM4 | | TM4 steerer electical check at SHC and TH. |
Using SHC electrical test cables routed to to TH, We tested TM4 steerer 4 polarities. At 100v megga test, left, right , up and down to ground are all OL. TM4 steerer has no short. |
1682
|
Wednesday, January 24, 2018, 13:30 |
David Wang | Conditioning Station | Standard Operation | TM1 | | TM1 has been moved to TCS this morning |
Tm1 has been moved to TCS this morning. All turbo-pumps are started successfully at TCS and TM1. |