Friday, February 16, 2024, 10:57, Adam Newsome, Spent Target Vault, Standard Operation, , , F-308 flask loading - three flasks loaded
|
Today (2024-02-16), three flasks were loaded in preparation for shipment with the following targets: UCx#39, UCx#41 and C#3.
Note: prior to shipping, the pails within these flasks will need to have a crimped lifting loop added to them.
The mini-storage vault is now EMPTY. |
Friday, March 15, 2024, 10:04, Adam Newsome, South Hot-Cell, Standard Operation, TM3, , TM3 Move - SHC to NE Silo
|
TM3 was moved from SHC to NE silo. Cable tray was recently installed. |
Tuesday, June 18, 2024, 15:04, Adam Newsome, Spent Target Vault, Maintenance, , , Annual Inspection of Main and Mini Storage Vaults
|
The annual inspection of the main storage vault will be skipped this year since extensive inspection and testing was performed during the re-alignment
job in May (see this e-log for details: e-log 2584). This included successful testing of the emergency
close mechanism. |
Tuesday, June 18, 2024, 15:16, Adam Newsome, Crane, Maintenance, , , Pail Handling Tool - Annual Inspection
|
The pail handling tool which is used to move 5 gallon pails around the target hall was inspected by A. Newsome. The main tool was checked, but not
the spare as it is currently in a disassembled and unusable state. The tool appears to be in good, working condition. The following items were checked.
Inspect structural integrity of long tube - check for bending, warpage, dents, cracks, rust/corrosion
Inspect structural |
Friday, July 05, 2024, 14:13, Adam Newsome, Waste Package/Ship, Standard Operation, , , F-308 flask loading - five flasks loaded
|
Today (2024-07-05), five flasks were loaded in preparation for shipment with the following targets: SiC#43 (Pail 272), SiC#44 (Pail 275), Ta#63 (Pail
266), UC#40 (Pail 278), UC#38 (Pail 274).
The crimped lifting loop has been applied to each pail. The locks have not yet been applied to the flasks at the time of writing this log, but |
Wednesday, July 10, 2024, 09:55, Adam Newsome, Safe Module Parking, Maintenance, , , Annual electrical and mechanical inspection of Safe Module Parking
|
An annual electrical and mechanical inspection was performed on the SMP today by Adam Newsome, Travis Cave, Riley Sykes, Maico Dalla Valle, and Jason
Zhang as per Work Permit I2024-07-10-1. The following items were checked:
Check condition of wiring for physical/radiation/UV damage
OK, no signs of significant damage
|
Wednesday, July 17, 2024, 15:06, Adam Newsome, Facilities, Standard Operation, , , Safety Walkaround Complete - SHC/NHC Area
|
A safety walkaround for July 2024 was completed for the B2 level by A. Newsome. No deficiencies to report.
Results can be found in the master
spreadsheet |
Thursday, September 05, 2024, 12:50, Adam Newsome, Crane, Maintenance, , , Overhead crane: up/down hoist delayed start issue
|
D. Wang reports that recently the overhead crane has been exhibiting a delayed start (approx. 1 min) when operating in local mode. This issue applies
to the main hoist's up/down functionality only and does not seem to apply to other motion axes. T. Kauss briefly investigated but did not find any obvious
cause. |
Wednesday, September 11, 2024, 13:38, Adam Newsome, North Hot-Cell, Repair, , , Spare Manipulator - Y-axis motion not functioning
|
Update 2024-09-12: C. Fisher confirms this is actually normal behaviour. The Y-axis motion is inhibited when X and Z
are in a certain configuration, which was true when the manipulator was mounted on the wall in storage position. Non-issue. A note about this has been
made in the operator manual. |
Thursday, September 12, 2024, 14:12, Adam Newsome, Waste Package/Ship, Development, , SiC#44, Failed waste emplacement at CNL: Flask #22, Pail 275 (SiC#44)
|
On 2024-09-12, CNL reported difficulty with lowering Pail 275 from F-308 flask #22 into their tile hole. The four other pails associated with this shipment
were successfully emplaced. It is suspected that the issue was related to a kink in the lowering cable, causing a jam during lowering. This was observed
approximately 1 year ago. |
Thursday, October 10, 2024, 12:20, Adam Newsome, Facilities, Standard Operation, , , Safety Walkaround complete - ISAC Hot Cells, Target Hall
|
A safety walkaround was completed for the ISAC Hot Cells and Target Hall Areas.
The resulting spreadsheet can be found on DocuShare as Document-242733.
Main deficiencies identified: |
Monday, November 25, 2024, 09:56, Adam Newsome, South Hot-Cell, Standard Operation, TM3, , TM3 move - silo to SHC
|
TM3 was moved from silo to SHC with no target. Move successful. |
Tuesday, November 26, 2024, 13:54, Adam Newsome, Conditioning Station, Standard Operation, TM3, , TM3 move - SHC to TCS
|
TM3 was moved from SHC to TCS with UCx#47. The move was smooth. |
Tuesday, December 03, 2024, 10:51, Adam Newsome, South Hot-Cell, Standard Operation, TM2, , TM2 move - ITE to SHC
|
TM2 was moved from ITE to SHC with Ta#68 target. During the move, a railing was lightly bumped by the corner of the module - no obvious damage or issues
have been observed. Otherwise, the move was smooth. |
Tuesday, December 03, 2024, 12:28, Adam Newsome, South Hot-Cell, Standard Operation, TM2, , TM3 move - TCS to ITE
|
TM3 was moved with UCx#47 from TCS to ITE. The move was smooth. |
Wednesday, December 04, 2024, 10:40, Adam Newsome, South Hot-Cell, Standard Operation, TM2, , TM2 move - SHC to silo
|
TM2 was remotely moved from the South Hot Cell to SW Silo. Reading at SHC = 89.8 mSv/h. The move was smooth. |
Thursday, December 05, 2024, 12:00, Adam Newsome, Spent Target Vault, Standard Operation, , Ta#68, Spent target move - Ta#68 in Pail 300
|
Ta#68 spent target was moved in Pail 300 to storage vault location 5A. The dose rate measured at the South Hot Cell was 429 mSv/h at 1m. The target index
spreadsheet has been updated and the current vault configuration is attached to this e-log. At this time, the storage vault is getting quite full - it
is planned to remove five pails in January 2025. |
Wednesday, December 18, 2024, 12:18, Adam Newsome, Spent Target Vault, Standard Operation, , , Five Pails Transferred from Main Vault to Mini Vault
|
Five pails were transferred from main vault to mini vault. Note that there was already one pail in the mini vault, so at present there are six pails
staged for packaging into F-308s.
Nb#10, Pail 295, Tray 4A |
Wednesday, December 18, 2024, 14:17, Adam Newsome, Pail Handling Tool, Maintenance, , , Pail Handling Tool - Inspection
|
An informal inspection of the main Pail Handling Tool was performed today as the final one for the year. Note that the main formal annual inspection
was performed June 18, 2024 for this year.
The attachment to this e-log serves as a record of all inspections for this tool throughout 2024. |
Friday, January 03, 2025, 09:59, Adam Newsome, Facilities, Standard Operation, , , Safety Walkaround complete - ISAC Hot Cells, Target Hall
|
A safety walkaround was completed for the ISAC Hot Cells and Target Hall Areas.
The resulting spreadsheet can be found on DocuShare as Document-242733.
Main deficiencies identified: |
|