Friday, May 18, 2012, 08:37, David Wang, South Hot-Cell, Standard Operation, TM4, sic 27, leak check on heat shield circuit
|
Friday, May 18, 2012, 08:29, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#27, Electrical check
|
Friday, May 18, 2012, 08:17, chad fisher, South Hot-Cell, Standard Operation, TM4, SiC#27, SiC#27 Installed
|
Thursday, May 17, 2012, 14:08, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, module move
|
Wednesday, May 16, 2012, 10:35, Travis Cave, Spent Target Vault, Standard Operation, , SiC#26, Spent target move
|
Tuesday, May 15, 2012, 14:29, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, module move
|
Tuesday, May 15, 2012, 12:14, chad fisher, South Hot-Cell, Standard Operation, TM4, SiC#26, SiC#26 removal TM4 degredation 19x
|
Tuesday, May 15, 2012, 11:45, Travis Cave, South Hot-Cell, Standard Operation, TM4, SiC#26, Electrical check
|
Monday, May 14, 2012, 12:37, Travis Cave, ITE, Standard Operation, TM4, SiC#26, module move
|
Tuesday, May 08, 2012, 10:28, David Wang, ITE, Standard Operation, TM4, , Disconnected TM4 in ITE.
|
Wednesday, May 02, 2012, 11:27, David Wang, ITW, Standard Operation, TM1, , ITW is ready for taking proton beam.
|
Thursday, April 26, 2012, 13:01, David Wang, ITE, Repair, TM4, , Replaced TM4 EE water flow wheel in ITE.
|
Thursday, April 26, 2012, 09:23, David Wang, ITE, Repair, TM4, , changed flow wheel on ITE TM4 contaiment box water circuit
|
Tuesday, April 24, 2012, 10:38, David Wang, Conditioning Station, Standard Operation, TM1, LP SIS Nb6, TM1 heat shield circuit leak check with Nb5
|
Tuesday, April 24, 2012, 10:36, Bevan Moss, Conditioning Station, Standard Operation, TM1, Nb#6, HV test April 23
|
Tuesday, April 24, 2012, 10:02, Travis Cave, ITW, Standard Operation, TM1, Nb#6, module move
|
Friday, April 20, 2012, 14:07, Travis Cave, Conditioning Station, Standard Operation, TM1, Nb#6, module move
|
Thursday, April 19, 2012, 09:48, David Wang, South Hot-Cell, Standard Operation, TM1, LP SIS Nb 6, leak check heat shield circuit
|
Thursday, April 19, 2012, 09:36, Travis Cave, South Hot-Cell, Standard Operation, TM1, Nb#6, Electrical check
|
Tuesday, April 17, 2012, 11:30, Travis Cave, South Hot-Cell, Standard Operation, TM1, no target, module moved
|
|