1538
|
Tuesday, May 16, 2017, 14:19 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | UC#20 | module moved | TM#4 with UC#20 has been moved from the
south hot cell to the conditioning station. |
|
1540
|
Wednesday, May 17, 2017, 08:35 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TCS turbo pumps was started yesterday | Anders started TCS turbo-pumps yesterday.
The TCS and TM4 pumping down is good so far.
I started TCS water pumps this morning for |
|
1541
|
Thursday, May 18, 2017, 10:08 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 TP1 at TCS | TM4 TP1 was found making some noise during
operation this morning. The current draw
was check then. It was 1.8 A which is higher |
|
1543
|
Thursday, May 18, 2017, 11:36 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | UC#20 | Electrical Check | Electrical check of TM#4 with UC#20 at
the conditioning station under vacuum. See
attached for details. |
|
1544
|
Friday, May 19, 2017, 12:25 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TCS and TM4 water flow measurement. |
|
|
1545
|
Friday, May 19, 2017, 13:49 |
David Wang | Conditioning Station | Repair | TM4 | | TM4 TP1 at TCS | TM4 TP1 is replaced. TCS and TM4 was argon
vented before the job.The job took about
30minutes. I started the all turbo |
|
1551
|
Wednesday, June 07, 2017, 13:33 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 SiC#36 leakc check and electrical check. | The results are good. See attachment. |
|
1552
|
Wednesday, June 07, 2017, 13:34 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | I started all turbo pumps. |
|
1553
|
Thursday, June 08, 2017, 07:37 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Helium pressure test on TM2 water llines at TCS. |
The helium pressure test on HS line is done |
|
1554
|
Thursday, June 08, 2017, 08:35 |
David Wang | Conditioning Station | Development | TM2 | | TM2 gas line reconfiguration on the module top. | Reconfigured TM2 gas line on the module
top. It matches with the febiad gas line
we are using on service tray now. Facing |
|
1561
|
Monday, June 19, 2017, 07:29 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Update TH MS project schedule. | Update TH MS project schedule. See attachment
1,2. |
 |
1567
|
Tuesday, June 27, 2017, 09:14 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | Ta#52 | Module move | TM#4 with Ta#52 has been moved from
south hot cell to the conditioning station. |
|
1569
|
Tuesday, June 27, 2017, 14:34 |
David Wang | Conditioning Station | Standard Operation | TM4 | | TM4 vacuum has been connected at TCS | Turbo -pumps are started . The vacuum looks
good so far. |
|
1570
|
Wednesday, June 28, 2017, 09:14 |
Travis Cave | Conditioning Station | Standard Operation | TM4 | Ta#52 | Electrical Check | Results of electrical check of TM#4 with
Ta#52 at the south hot cell and the conditioning
station under vacuum. |
|
1571
|
Wednesday, June 28, 2017, 10:00 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#52 | TM2 has been connected at TCS | I started TCS water system. |
|
1572
|
Wednesday, June 28, 2017, 16:43 |
Anders Mjos | Conditioning Station | Standard Operation | TM4 | Ta#52 | Conditioning Ta#52 | NEW HV cable for BIAS installed earlier
this week.
Wednesday, June 28, 2017, 16:42: |
|
1574
|
Thursday, June 29, 2017, 11:55 |
David Wang | Conditioning Station | Repair | | | TCS HV cable and feed through installation | John Chow and I installed new TCS HV cable
and feed through with their mounting panel
back to TCS Faraday cage this Tuesday. ECO-4269 |
|
1576
|
Wednesday, July 05, 2017, 11:18 |
Anders Mjos | Conditioning Station | Maintenance | TM4 | Ta#52 | Changed electrical configuration to cathode bias | John Chow configured TCS to cathode
bias mode (IRH1538). The anode P/S is in
positive mode. |
|
1580
|
Monday, July 10, 2017, 10:19 |
David Wang | Conditioning Station | Standard Operation | TM4 | | Turned off TCS water system | Prepare for TM4 move tomorrow morning. |
|
1582
|
Wednesday, July 12, 2017, 11:05 |
Anders Mjos | Conditioning Station | Maintenance | | | Testing of new high voltage cable | The target hall has been locked-out as
per Document-70039.
Forced IG1, IG1S and IG2 to switch |
|