ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
Text |
 |
2241
|
Wednesday, August 11, 2021, 11:15 |
Adam Newsome | Spent Target Vault | Development | | | Mini-Storage: Cable track for e-chain installed | A cable track was installed between the
mini-storage vault and the silos, for the
purpose of implementing a retractable cable |
|
2242
|
Thursday, August 12, 2021, 14:13 |
Adam Newsome | ITW | Repair | | | West Entrance Module Move to ITW | The West Entrance Module has been moved
from the South Hot Cell to the West Target
Station. |
|
2247
|
Friday, September 17, 2021, 14:28 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#62 | Spent Target Move | The spent Ta#62 target along with
2A2M19 were placed in pail #256 and placed
in spot 7A of the spent target vault. See |
|
2249
|
Wednesday, September 22, 2021, 11:13 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#34 | Spent Target Move | The spent UC#34 target was moved
from the north hot cell to the spent target
vault. See attached PDF for details. |
|
2250
|
Thursday, September 23, 2021, 19:04 |
Adam Newsome | Spent Target Vault | Development | | | Mini-Storage: Remote Capability | Remote capability was added for the mini-storage
door control. The control signals originate
from the Opto 22 Module box that is used |
|
2256
|
Wednesday, October 06, 2021, 10:42 |
David Wang | ITE | Repair | | | ITE IG1S cable end connector replacement | ITE IG1S cable end connector replacement
has been finished by Roy Huang. |
|
2259
|
Wednesday, October 13, 2021, 11:54 |
Travis Cave | North Hot-Cell | Standard Operation | | SiC#41 | Spent Target Move | The spent SiC#41 target has been
placed in pail #260 and placed in spot 5B
of that spent target vault. See attached |
|
2261
|
Friday, October 29, 2021, 12:27 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#56 | Repacking of the target. | Ta#56 in pail #169 was repacked and
placed into #269 and was placed in the mini
vault at the back. It was 3.86mSv/hr upon |
 |
2266
|
Wednesday, November 10, 2021, 11:06 |
Travis Cave | Spent Target Vault | Standard Operation | | C#3 | Spent Target Move | The spent C#3 target has been moved
from the south hot cell to the spent target
vault it was placed in pail #270 and put |
|
2267
|
Monday, November 15, 2021, 12:00 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#53 | Repacking of the target. | Ta#53 was repacked and placed in
the mini vault it was changed from pail#164
to pail#262. See attached PDF for further |
 |
2268
|
Monday, November 15, 2021, 12:15 |
Adam Newsome | South Hot-Cell | Repair | | | Squeaking noise during turntable rotation - chain misalignment and improper tension | It was noted on Nov. 9 that a squeaking
noise was present when the turntable was
rotated CCW with a module present. |
|
2269
|
Wednesday, November 17, 2021, 11:42 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#57 | Repacking of the targets. | Ta#57 was repacked and placed in
the mini vault. The pail was changed from
#174 to #263. See attached PDF for more details. |
 |
2270
|
Thursday, November 18, 2021, 09:47 |
Travis Cave | Spent Target Vault | Standard Operation | | SiC#38 and UC#29 | Spent Target Move | The spent targets SiC#38 and UC#29
have been removed from the spent target vault
and placed into the mini storage. See attached |
 |
2271
|
Friday, November 19, 2021, 12:48 |
Adam Newsome | South Hot-Cell | Development | | | Vertical motion limit switch installation | A rotary limit switch was installed, attached
to the shaft adjacent to the drive motor
for the vertical drive system. This limit |
|
2272
|
Monday, November 22, 2021, 12:44 |
Adam Newsome | Crane | Repair | | | Crane PLC Fault: 0004h | An issue was observed in which the target
hall crane was not functioning: the N-E-S-W
and up/down motions did not work, however |
|
2278
|
Friday, November 26, 2021, 10:52 |
Adam Newsome | Spent Target Vault | Standard Operation | | UC#35 | Spent Target Move | The spent UC#35 target has been moved from
the south hot cell to the spent target vault.
It was placed in pail #264 and put in spot |
|
2279
|
Monday, November 29, 2021, 12:16 |
David Wang | Spent Target Vault | Standard Operation | | | Five spent targets have been loaded into F308s | We loaded UCx #29 , SiC #38 , Ta#53,
Ta#56 ,and Ta#57 from mini storage
into F308 flasks. Later, the flasks |
|
2288
|
Tuesday, January 11, 2022, 11:50 |
David Wang | ITW | Maintenance | | | ITW Exit module 1 side sqaure panel O-ing seal replacement. | Frank and I replaced ITW Exit module 1
side square service panel o-ring seal. Also,
The target module pit top flange o-ring seal |
|
2290
|
Wednesday, January 12, 2022, 14:09 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#36 | Spent Target Move | The spent UC#36 target in the north
hot cell has been removed and placed in the
spent target vault. See attached PDF for |
|
2294
|
Wednesday, January 19, 2022, 13:26 |
David Wang | Crane | Standard Operation | | | Inpection of Target module lifting frames ITA0494-1997-01 and ITA0494-1997-02. | Tom Gauss inspected two target module
lifting frames ITA0494-1997-01 and ITA0494-1997-02..
He certified the use of these two frames. |
   |