  1122   Thursday, November 12, 2015, 10:18 Anders MjosConditioning StationMaintenanceTM3 Air to vacuum leak on service cap

    

       
            
  
  1123   Thursday, November 12, 2015, 13:25 Anders MjosConditioning StationStandard OperationTM3FEBIAD Test TargetElectrical check and leak checkTarget to Anode and target to Common showed
~ 500 kOhm values. No leaks above 3E-9 atm-cc/s
seen. See attached.  
 TM3_iwth_FEBIAD_in_TCS_Electrical_Check.pdf 
  1125   Monday, November 16, 2015, 10:09 Anders MjosConditioning StationStandard OperationTM3FEBIAD Test TargetElectrical check after HV conditioning Problem found between ANODE (F) and
chassis 90 kOhm. See attachment for details.
 2015-11-16_TM3_Electrical_Test.pdf 
  1126   Monday, November 16, 2015, 10:33 Anders MjosConditioning StationStandard Operation FEBIAD Test TargetHV conditioning by ISAC operatorsISAC operators attempted HV conditioning
over the weekend.
https://web.accel.triumf.ca/isac_elog/Elog_show_result.pl?inid=218447&style=entry
  
  1137   Wednesday, November 25, 2015, 15:37 Anders MjosConditioning StationStandard OperationTM4UC#14Conditioning Wednesday, November 25, 2015, 15:36:
RGA on

Thursday, November 26, 2015,
  
  1145   Tuesday, December 01, 2015, 11:47 Anders MjosConditioning StationMaintenanceTM4UC#14Short on Extraction Electrode After conditioning over the weekend
the EE developed a short. This was confirmed
by measuring the resistance between EE and
  
  1148   Thursday, December 10, 2015, 13:17 Anders MjosConditioning StationStandard Operation  Blank off flangeThursday, December 10, 2015, 13:17: Roughing
Thursday, December 10, 2015, 14:56:
Started TP1S
 TCS_Blank_Off.png 
  1149   Friday, December 18, 2015, 11:42 Anders MjosConditioning StationRepair  Vacuum gauges not reading correctly It was found that the conversion
from voltage to vacuum (Torr) in EPICS is
not correct for the XGS-600 controllers in
  
  1150   Monday, December 21, 2015, 13:27 Anders MjosConditioning StationRepair  Vacuum gauges not reading correctly

    

       
            
  
  1200   Friday, April 08, 2016, 08:13 Anders MjosITE/ITW CoolingMaintenance  High Active Water ResistivityThe high active water resistivity took
a long time to recover after the upgrade
to the water cooling circuit. The system
 2016-04-08_ISAC_High_Active_Water_Resistivity.png 
  1211   Thursday, April 14, 2016, 09:46 Anders MjosConditioning StationStandard OperationTM2 TM2 water leak test Thursday, April 14, 2016, 07:50:
RGA on

Friday, April 15, 2016, 08:09
 2016-04-15_RGA.png 
  1233   Monday, May 16, 2016, 10:48 Anders MjosConditioning StationMaintenance  Topped up water in TCS:TK2 Filled from 15 to 25 in   
  1235   Monday, May 16, 2016, 13:26 Anders MjosConditioning StationStandard OperationTM2Ta#48Conditioning Ta#48 Monday, May 16, 2016, 13:20: BIAS/EL/EE
30 / 15 / 1.5 kV
Monday, May 16, 2016, 13:20: Ramping
 Ta#48.docx 
  1259   Wednesday, June 08, 2016, 08:25 Anders MjosConditioning StationStandard OperationTM4UC#16Conditioning UC#16 Wednesday, June 08, 2016, 08:15:
RGA on

Thursday, June 09, 2016,
 UC#16.docxTCS-2016-06-08_UC#16.rga 
  1277   Wednesday, July 06, 2016, 15:23 Anders MjosConditioning StationStandard OperationTM2SiC#33Conditioning SiC#33 Wednesday, July 06, 2016, 15:23:
RGA on. IGs on

Friday, July 08, 2016, 17:07:
 SiC#33.docxTCS-2016-07-06-SiC#33.rga 
  1279   Friday, July 08, 2016, 16:56 Anders MjosConditioning StationRepair  VFD21 OL1 fault on ChillerPlant Services group (Tony) will contact
a service tech on Monday.
Water system will be switched off
  
  1286   Thursday, July 14, 2016, 13:25 Anders MjosConditioning StationRepair  VFD21 OL1 fault on Chiller

    

       
            
  
  1291   Monday, July 25, 2016, 08:15 Anders MjosConditioning StationRepairTM3 HV Test Monday, July 25, 2016, 08:14: Enabled
staging for chiller
Monday, July 25, 2016, 08:33: Disabled
 TM3_HV_conditioning_2016-07-25.docxTCS-2016-07-25_TM3_no_target.rgaTCS-2016-07-26_TM3_no_target.rga 
  1299   Wednesday, August 03, 2016, 08:08 Anders MjosConditioning StationStandard OperationTM4UC#17Conditioning UC#17Wednesday, August 03, 2016, 08:08: RGA
on
Wednesday, August 03, 2016, 11:25:
 UC#17.docxTCS-2016-08-03_UC#17.rgaTCS-2016-08-08_UC#17.rga 
  1311   Tuesday, August 09, 2016, 11:36 Anders MjosConditioning StationMaintenance  RGA and CG1S moved The locations (ports) for the RGA
and CG1S was swapped today by Anders and
Isaac to provide clearance for the North
 Old.JPGNew.JPG 