  2199   Friday, March 12, 2021, 11:36 Travis CaveSouth Hot-CellMaintenance East Entrance ModuleEntrance module move

 The East Entrance Module has been moved from the East Target Station to the South Hot Cell.

  2200   Monday, March 15, 2021, 13:01 Isaac EarleCraneDevelopment  Plate & pin lift assembly load testing (ITA6550)

In mid-2020 design analysis was completed on the steel plate & pin assemblies (ITA6550) used to connect the ISAC target hall crane hook block to the module lifting yoke assembly ITA0494.  The released design note is Document-184431.  

In November 2020 fabrication was completed on two full plate & pin assemblies (photos attached below).  As per the relevant ASME standards (identified in the design note), each assembly has been identified with serial numbers (#1 and #2).  Material test reports for the steel plate and round bar material used for fabrication are attached in PDF format.  For both materials the tested tensile yield strength (from the MTR) exceeds the value used in design calculations (from Document-184431):  117ksi vs 100ksi for the plate material;  138si vs 103ksi for the round bar material.

On February 8, 2021 both plate and pin assemblies were load tested by David Wang and Frank Song.  The total load applied to each was 31,400 lbs (as per the ISAC target hall crane load cell) which exceeds the 125% of rated capacity (31,250 lbs) required for the test.  The lifts were conducted successfully and no deformations or other damage to the assemblies were observed.  Photos of the load test are also attached.

Both plate & pin assemblies are now certified for use up to their rated capacity.  As specified on drawing ITA6550 and in Document-184431, a monthly visual inspection must be performed to check for structural deformation, cracks, excessive wear, and loose or missing fasteners.  In addition, an annual inspection must be performed to check for structural deformation, cracks, excessive wear, loose or missing fasteners, and missing or illegible markings or safety labels.  A written record of the annual inspection must be documented and kept readily available.

 

Attachment 1: 1.jpg
1.jpg
Attachment 2: 3.jpg
3.jpg
Attachment 3: 4.jpg
4.jpg
Attachment 4: 5.jpg
5.jpg
Attachment 5: ASTM_A514_-_Steel_Plate_-_Material_Test_Report.pdf
ASTM_A514_-_Steel_Plate_-_Material_Test_Report.pdf
Attachment 6: AISI_4140_HTSR_-_2in_Diameter_Round_Bar_-_Material_Test_Report.pdf
AISI_4140_HTSR_-_2in_Diameter_Round_Bar_-_Material_Test_Report.pdf
Attachment 7: Load_test_1.jpg
Load_test_1.jpg
Attachment 8: Load_test_2.jpg
Load_test_2.jpg
Attachment 9: Load_test_3.jpg
Load_test_3.jpg
Attachment 10: Load_test_4.jpg
Load_test_4.jpg
Attachment 11: Load_test_5.jpg
Load_test_5.jpg
  2201   Wednesday, March 17, 2021, 09:10 Travis CaveITEStandard Operation  Entrance module move

 The east entrance module is now back at the east target station.

  2202   Wednesday, March 17, 2021, 11:43 Frank SongITERepair  Re-connect Entrance Module in ITE

 David and I re-connect Entrance module at ITE after the monitor been replaced at SHC. 

Attachment 1: job_done_by_following_#190510.pdf
job_done_by_following_#190510.pdf job_done_by_following_#190510.pdf job_done_by_following_#190510.pdf job_done_by_following_#190510.pdf job_done_by_following_#190510.pdf job_done_by_following_#190510.pdf job_done_by_following_#190510.pdf job_done_by_following_#190510.pdf
  2204   Thursday, March 25, 2021, 08:55 Anders MjosConditioning StationMaintenance  Filters inspected and cleaned on water circuit

By Curtis. See Work Permit I2021-03-24-1 for details.

  2205   Thursday, March 25, 2021, 10:38 David WangSpent Target VaultStandard Operation C#1Remove pail 237 spent target C#1 from storage vault to mini storage.

Pail 237 only has 200u sv/hr field at 0.5 meter. On contact measurement: 0.9 to 1.6 m sv/hr.and less than 80 count contamination outside the pail.   It is moved to mini storage. We will transfer this pail to cyclotron vault and store it there later.

  2206   Friday, March 26, 2021, 12:22 Adam NewsomeCraneDevelopment  Aux Hoist Pendant Upgrade

The crane pendant for the auxiliary hoist was upgraded to a FLEX EX2 style pendant by Canco Cranes. The installation work was performed by Canco, supervised by Tom Kauss and David Wang. Installation work was performed in one day (I2021-03-26-1).

Items installed include: new pendant (2 motion, 2 speed)

The existing antenna and receiver box located in the Target Hall were used.

The new system was tested by David Wang. Everything is reported to be in working condition.

  2207   Monday, April 12, 2021, 13:45 Anders MjosCoolingMaintenance  New T installed for instrumentation loop on HALCW system

Adrian and co installed a new T to be able to add an instrument loop for O2 and pH monitoring on the low conductivity water systtem (photo). See WP I2021-04-09-4

Attachment 1: MicrosoftTeams-image_(9).png
MicrosoftTeams-image_(9).png
  2211   Wednesday, April 21, 2021, 11:18 David WangCoolingMaintenance  Refilling high active wtaer system and starting HA water pumps.

High active water system is refilled. Air are drained out of  system before pump to be started. Following sequence are used to bring the whole system back to operation:

1. close ITE , open ITW. Switch on the pump. Only 2A beam line related 5 water circuits are in loop in ITW.  Switch off pump when system pressure is stable above 100 psi.

2. Close ITW, open ITE. Switch on the pump. Only 2A beam line related 5 water circuits are in loop in ITE. Switch off pump when system pressure is stable above 100psi.

3. Open ITW, Open ITE. Switch on pump. both ITW and ITE beam line related water circuits are in loop.  Switch  off pump when system pressure is stable above 100psi.

4. Close ITE open ITW.  Bring ITW  target module water circuits back to loop by connecting bypass fittings on to circuits. Only bring one circuit back to system at first. Switch on pump. Wait for system pressure stabilized. Then Close ITW. bring next circuit back  to system.  Open ITW .  wait for pressure stabilized.  repeat the process until all water circuit and connected with bypass fittings in ITW.

5. Check possible leak on valves, fittings, and flow sensors in ITW pit.

6. Go to electrical room, check all ITW water signal status.

7. Close ITW, Open ITE. Repeat same procedure as step 4 on ITE target module water circuits.

8. Check possible leak on valves, fittings and flow sensors in ITE pit.

9. Go to electrical room, check all ITE water signal status.

10. Open ITW.  At this stage, full ITE station and half of ITW station water circuits are in operation.  Check possible leak on pumps, valves, fittings, gauges on water station at TH west end.

11. Keep system in operation. Watch on - tank level , system pressure, and conductivity on resin circuit and whole system.

  2215   Monday, May 03, 2021, 15:14 Frank SongITEMaintenance  High voltage test in ITE

 Anders and I prepared ITE high voltage test in April 30 ( Friday morning), The MAA is locked for this.

  2216   Friday, May 14, 2021, 11:29 David WangSpent Target VaultStandard Operation  Repack of 4 spent targets.

Repack of 4 spent targets in TH and SHC.  SiC#37 to new pail249#. SiC#36 to new pail 250#. Nb#8 to new pail 247#, SiC#33 to new pail 248#.  They are all in mini storage. Also, UCx 31 are transferred to mini storage.  There are 5 spent targets in mini storage now.  

2021-05-20: 5 spent targets have been loaded into F308's. We transferred two more spent targets into mini storage this morning for next week loading.

  2217   Tuesday, May 25, 2021, 15:59 Matthew GareauNorth Hot-CellDevelopment  Removed boot from left hot manipulator

 Myself and Isaac removed the boot from the left hot manipulator.

- opened the hatch in the TH to get access to the top of the boot

- released the latch on the boot and loosened the boot from above

- closed TH hatch

- with the right manipulator we were able to detach the rest of boot

This test proved that we can remove a boot from the manipulator without having to enter into the hotcell.

Due to the physical restraints that the boot causes for the operator, we have decided to not reattach the boot with its current design.

A new design will be investigated to allow the boot to be fixed without twisting, which is the source of the problems.

 

Attachment 1: IMG_20210525_134723.jpg
IMG_20210525_134723.jpg
Attachment 2: IMG_20210525_134727.jpg
IMG_20210525_134727.jpg
Attachment 3: MicrosoftTeams-image.png
MicrosoftTeams-image.png
Attachment 4: MicrosoftTeams-image_(4)1.png
MicrosoftTeams-image_(4)1.png
Attachment 5: IMG_20210525_141602.jpg
IMG_20210525_141602.jpg
Attachment 6: IMG_20210525_141851.jpg
IMG_20210525_141851.jpg
Attachment 7: IMG_20210525_142144.jpg
IMG_20210525_142144.jpg
  2218   Tuesday, May 25, 2021, 16:20 Anders MjosConditioning StationMaintenance  Chiller maintenance

A contractor on site today for chiller maintenance. CP2 and CP3 circuit is leaking and shall not be used. CP1 can still be used. The contractor will contact Plant Group with a quote for repair and upgrades.

  2219   Tuesday, May 25, 2021, 16:20 Anders MjosConditioning StationMaintenance  TK2 refilled

Tank refilled from 12 in to 25 in using the new valve.

  2230   Wednesday, June 30, 2021, 14:11 Matthew GareauNorth Hot-CellStandard Operation  North Hot Cell Commemorative Opening

 Yesterday a bottle of Cava (sparkling wine) was place, opened, and poured in the NHC, to commemorate its new operational status.

The NHC is now a functional hot cell and is ready for many years of target exchanges to come.

  2231   Wednesday, July 07, 2021, 11:59 Adam NewsomeSafe Module ParkingMaintenance  Annual Electrical and Mechanical Inspection

An annual electrical and mechanical inspection was performed on the SMP today by Adam Newsome, Dan McDonald, and Jason Zhang as per Work Permit I2021-07-07-3. The following items were checked:

  • Check condition of wiring for physical/radiation/UV damage
    • OK, no signs of significant damage
  • Check for cable tray debris or damage
    • There were multiple shards of plastic in the cable tray - they were removed and disposed of
  • Check inside control panel: components and wiring, labeling
    • Labeling intact, components in good condition
    • One COM wire for the relay array was loose - it was tightened
  • Verify camera views
    • This was not inspected but has recently been checked, and is checked prior to remote operation
  • Check connectors for damage
    • All connectors OK
  • Check pendant for damage and verify labeling intact
    • Pendant OK
  • Lid open/close test
    • Lid was opened and close multiple times - smooth operation, no concern
    • Lid close logic was checked - OK
  • Vessel rotation and limit switch check
    • Both CW and CCW limits were checked, functioning
    • No concern on rotation - chain drive, rotary limit switch, and cable reel all functioning normally
  • Lubricate chains
    • Done
  • Inspect tensioners
    • Done - OK
  • Tighten fasteners
    • Done - OK
    • Note: some concern over socket head screws in slotted parts - they should have washers. Not a critical issue but worth checking into.
  • Visual inspection
    • All OK

Overall the inspection was successful.

Attachment 1: Capture.PNG
Capture.PNG
Attachment 2: PXL_20210707_162143876.jpg
PXL_20210707_162143876.jpg
Attachment 3: PXL_20210707_162918257.jpg
PXL_20210707_162918257.jpg
  2234   Thursday, July 15, 2021, 09:02 Adam NewsomeSpent Target VaultStandard Operation  Emergency Close Mechanism Test

The emergency close mechanism for the Storage Vault door was tested by Adam Newsome and Travis Cave. The door was opened to its fully open limit, then closed with the emergency system.

The test was successful.

  2237   Friday, July 30, 2021, 16:31 Carla BabcockITERepair  ITE re-wire

See the attached for the way ITE has been re-wired for the Ta62 run. Note also that the copper block in the schematic on TBHT negative may not actually be connected. Wiring verification on Aug. 4.

Attachment 1: ISK4425D-rev9._APshortmitigationsvg_july27update.png
ISK4425D-rev9._APshortmitigationsvg_july27update.png
  2239   Friday, August 06, 2021, 11:52 Travis CaveNorth Hot-CellStandard Operation UC#33Spent Target Move
UC#33 has been packed and moved from the north hot cell to the spent target vault. See attached PDF for 
deatails
Attachment 1: Target_Index_2021-08-06.pdf
Target_Index_2021-08-06.pdf Target_Index_2021-08-06.pdf Target_Index_2021-08-06.pdf
  2240   Tuesday, August 10, 2021, 10:16 Adam NewsomeSouth Hot-CellRepair  West Entrance Module Move to South Hot Cell

The West Entrance Module has been moved to the South Hot Cell for repair.