822
|
Monday, December 15, 2014, 13:25 |
Anders Mjos | Conditioning Station | Maintenance | TM2 | | BIASSW1 temperature and flow removed from interlock chain |
|
|
|
824
|
Tuesday, December 23, 2014, 14:10 |
Anders Mjos | Conditioning Station | Development | TM2 | | He leak check of the Service Cap using RGA | The RGA showed no response to He-spray
on the Service Cap. He stable at 3.5E-9 T
partial pressure, water at 1.3E-6 T. IG1 |
|
|
825
|
Monday, January 05, 2015, 12:47 |
Anders Mjos | Conditioning Station | Development | TM2 | | Cooling package started | by "enable staging" button.
MP3 has to be turned off-on to open WPV1 |
|
|
826
|
Monday, January 05, 2015, 15:01 |
Anders Mjos | Conditioning Station | Development | TM2 | | RGA switched on | |
|
|
828
|
Tuesday, January 06, 2015, 11:21 |
Anders Mjos | Conditioning Station | Development | TM2 | | He leak check of cooling circuits. | No leak detected on either He-detector
(connected directly to Service Cap) or on
RGA. See attached screen shots. |
|
|
829
|
Wednesday, January 07, 2015, 09:31 |
Anders Mjos | Conditioning Station | Development | TM2 | | High Voltage Conditioning | No Source Tray installed. Loop on cooling
circuit D. All other circuits blanked off.
Voltages stated below are set point |
|
|
832
|
Thursday, January 08, 2015, 15:24 |
Anders Mjos | Conditioning Station | Development | TM2 | | Fault 2 on chiller unit | Found both VFDs with OF3 fault (over
voltage during constant speed operation).
Thursday, January 08, 2015, 16:37: |
|
|
836
|
Wednesday, January 28, 2015, 10:42 |
Anders Mjos | Conditioning Station | Maintenance | TM2 | | TCS shut down for site wide power outage | |
|
|
845
|
Tuesday, February 17, 2015, 13:06 |
Anders Mjos | ITE | Development | | | Resistance measured of TGHT and TBHT lines to ITE | The copper bars was installed by David
and Anders. After the measurements were completed,
the copper bars were removed. |
|
|
846
|
Tuesday, February 17, 2015, 13:07 |
Anders Mjos | ITW | Development | | | Resistance measured of TGHT and TBHT lines to ITW | See e-log entry
for ITE for details. The copper bars have
not been removed. They can be used for testing |
|
|
860
|
Thursday, March 12, 2015, 13:33 |
Anders Mjos | South Hot-Cell | Standard Operation | TM1 | ThO#1 | Target inspection | Chad, Anders and Alex inspected the target
this morning. The target had no significant
visible damage to the container. Some material |
|
|
878
|
Monday, March 30, 2015, 09:03 |
Anders Mjos | Conditioning Station | Standard Operation | TM4 | Ta#45 | Ta#45 Conditionoing | Monday, March 30, 2015, 08:59: Reset chiller
by switching on off power (fault 2)
Monday, March 30, 2015, 09:02: Switched |
|
|
886
|
Wednesday, April 15, 2015, 09:01 |
Anders Mjos | Conditioning Station | Development | | | Archiver variables added by Controls |
|
|
|
891
|
Monday, April 20, 2015, 10:12 |
Anders Mjos | Conditioning Station | Standard Operation | TM1 | UC#12 | Conditioning UC#12 | Monday, April 20, 2015, 09:35: Started
cooling water circulation
HV cover did not fit due to interference |
|
|
897
|
Thursday, April 23, 2015, 12:56 |
Anders Mjos | Conditioning Station | Maintenance | TM1 | | IG1 Good Vacuum limit changed | Changed by Dave Morris.
New value is 1E-5 T (old value was
7.09E-5 T) |
|
|
903
|
Tuesday, April 28, 2015, 11:09 |
Anders Mjos | ITW | Maintenance | | | Resistance measured of TGHT and TBHT lines to ITW | The new TBHT and TGHT power supplies were
brough up to high current; 350 A and 420
A respectively. The TGHT power supply was |
|
|
909
|
Monday, May 04, 2015, 13:32 |
Anders Mjos | Conditioning Station | Maintenance | | | TK2 expansion tank topped up | Caled cyclotron ops to open P23 and confirmed
penthouse valve open.
Filled up TK2 to 21 in water leve. |
|
|
913
|
Monday, May 11, 2015, 10:45 |
Anders Mjos | Conditioning Station | Maintenance | | | RGA electronics box installed | The communications chip has been
replaced. The electronics box has been grounded
(see attached pdf). |
|
|
931
|
Wednesday, June 03, 2015, 13:01 |
Anders Mjos | Conditioning Station | Standard Operation | TM4 | SiC#31 | Conditioning SiC#31 | PNG1 connected to PNG in service cap
(as per David W)
Wednesday, June 03, 2015, 12:59: |
|
|
959
|
Tuesday, June 23, 2015, 16:49 |
Anders Mjos | Conditioning Station | Development | | | TCS is beeing migrated to ISAC | by controls group (Dave Morris).
Friday, June 26, 2015
TCS has been migrated to ISAC controls. |
|