  1367   Friday, September 30, 2016, 14:34 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 131(Sep-Dec, 2016)

Weekly update TH schedule for beam schedule 131. See attachments 1,2

Attachment 1: Target_Hall_shedule_131_Sep_to_Dec.mpp
Attachment 2: Target_Hall_shedule_131_Sep_to_Dec.pdf
Target_Hall_shedule_131_Sep_to_Dec.pdf
  1371   Wednesday, October 12, 2016, 10:01 David WangConditioning StationStandard Operation  TCS pumps are stopped

Argon venting is started

  1384   Wednesday, October 26, 2016, 12:33 David WangConditioning StationStandard OperationTM2 Target Hall schedule for beam schedule 131(Sep-Dec, 2016)

Update TH schedule after job delay on TM2 Febiad target. Everything should be back to schedule on last two targets. See attachments.

Attachment 1: Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
Attachment 2: Target_Hall_shedule_131_Sep_to_Dec.mpp
Attachment 3: Target_Hall_shedule_131_Sep_to_Dec.pdf
Target_Hall_shedule_131_Sep_to_Dec.pdf
  1388   Wednesday, November 02, 2016, 09:12 Travis CaveConditioning StationStandard OperationTM4Ta#50module moved

TM#4 with Ta#50 has been moved from the south hot cell to the conditioning station.

  1389   Wednesday, November 02, 2016, 13:41 David WangConditioning StationStandard OperationTM4 TM4 has been connected at TCS.

All turbo-pumps are started. The pumping down is good so far.

  1390   Thursday, November 03, 2016, 08:57 David WangConditioning StationStandard OperationTM4 Helium pressure test on TM4 HS line at TCS

70 psi helium ,2minutes to  TM4 HS line. LD base leak rate 0.0xE-9 atm.cc/sec. No leak.

  1391   Thursday, November 03, 2016, 09:01 David WangConditioning StationStandard OperationTM4 TCS water system has been started for TM4.

The system works fine. All water signals to TM4 at TCS are normal. HV cover is installed on to TM4 at TCS.

  1393   Tuesday, November 08, 2016, 07:47 David WangConditioning StationStandard OperationTM4 TCS water and vacuum pumps are switched off

TCS is vented. TM4 is disconnected and TCS.

  1397   Tuesday, November 15, 2016, 07:53 David WangConditioning StationStandard OperationTM4 Target Hall schedule for beam schedule 131(Sep-Dec, 2016)

Update TH schedules . See attachments

Attachment 1: Target_Hall_shedule_131_Sep_to_Dec.pdf
Target_Hall_shedule_131_Sep_to_Dec.pdf
Attachment 2: Target_Hall_shedule_131_Sep_to_Dec.mpp
Attachment 3: Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
Target_Hall_shedule_131__Sep_to_Dec_2016.pdf
  1400   Tuesday, November 22, 2016, 14:26 David WangConditioning StationStandard Operation  TCS vacuum pumps are switched off

TCS will be vented tomorrow morning for TM2 moving.

  1401   Wednesday, November 23, 2016, 14:21 Travis CaveConditioning StationStandard OperationTM2UC#18module moved

TM#2 with UC#18 has been moved from the south hot cell to the conditioning station.

  1404   Wednesday, November 23, 2016, 16:21 David WangConditioning StationStandard OperationTM2 TM2 and TCS vacuum system has been connected.

All vacuum pumps have been started. Air ballast 50seconds on roughing pump. Everything is good  so far.

  1405   Thursday, November 24, 2016, 09:33 Anders MjosConditioning StationStandard OperationTM2UC#18Conditioning UC#18

Thursday, November 24, 2016, 09:33: Water package on

Thursday, November 24, 2016, 09:43: TCS:WPV1 shows only 12% open. A visual inspection confirms the valve is fully opened. Controls will be contacted to troubleshoot

 

  1406   Thursday, November 24, 2016, 10:30 David WangConditioning StationStandard OperationTM2 HV cover is installed on TM2 at TCS

Interlock key  are returned back to B2 level.TM2 is ready for HV conditioning and heating up at TCS.

  1408   Tuesday, November 29, 2016, 06:27 David WangConditioning StationStandard OperationTM2 TCS water pumps are stopped

Argon venting on TCS and TM2 is processing

  1409   Tuesday, November 29, 2016, 07:50 David WangConditioning StationStandard OperationTM2 TM2 is disconnected at TCS.

Argon venting is done.

  1412   Wednesday, November 30, 2016, 16:31 David WangConditioning StationRepairTM3 TM3 vacuum system have been connected at TCS.

All water circuits are by passed on the top of TM3. Water pumps and vacuum turbo- pumps are started. Everything is ready for TM3 camera sparking check.

  1414   Monday, December 05, 2016, 10:04 Aurelia LaxdalConditioning StationRepairTM3 TM3 vacuum system have been connected at TCS.

David Wang wrote:

All water circuits are by passed on the top of TM3. Water pumps and vacuum turbo- pumps are started. Everything is ready for TM3 camera sparking check.

 Wednesday November 30st: <br>

- 3 cameras (1 UV and 2 regular cameras)  were installed in the Service cap and the module was pumped down.  1 UV and 1 regular were placed on the East side of the module, aiming to water lines entering the Service Tray; 1 regular camera was placed on the South side of the module, aiming at the bottom of the blue insulators.

- started pumping down. <br>

Thursday, December 1st: <br>

- 1st HV test done. TM3 started sparking above 20kV. The cameras responses were consistent with the sparks. However, the screens were flickering and it was not clear if the responses were due to electromagnetic interferences; or due to cameras' gain change caused by high intensity light due to sparking.<br>

- added helium using the regulating valve. same results were found; <br>

Friday, December 2nd: <br>

- vented the module. <br>

- shielded the cameras' cables with aluminum tape. <br>

- removed 2 blue insulator (EE and HS) and shortened them by 1". They were found too long: HS blue insulator touching the horizontal HV water line; and the EE blue insulator at 2-3mm far from the HV water line; re-installed both shortened blue insulators.<br>

- changes the location of the cameras: 1 regular camera taped to the UV camera were placed South, aiming at the bottom of the blue insulators; 1 regular camera was kept on the East side of the module, also aiming at the bottom of the blue insulators. <br>

- started pumping down. <br>

Saturday, December 3rd: <br>

- 2nd HV test was done, with cameras' installed as mentioned above. results were consistent with the first test results. <br>

- added helium. results were the same. <br>

- vented and changed the location of the cameras: 1 regular camera taped to the UV camera were placed at the top of the Service Tray (South-West corner) aiming down the Service Tray; 1 regular camera was kept (its setup was not touched at all) on the East side of the module, aiming at the bottom of the blue insulators. <br>

- attempted to pump down, but the module was leaking. reopened the flanges, cleaned them, attempted again to pump down, but it showed a bigger leak. <br>

Sunday, December 4th: <br>

- the third attempt to pump down was successful (without reopening the module!). <br>

Monday, December 5th: <br>

- did the 3rd HV test with the cameras installed as described on December 3rd. same results as before were seen. <br>

- again helium was added and same results were noticed. <br>

- stopped pumps and prepared for venting to relocate the cameras lower in the Service Tray.

 

 

 

  1417   Friday, December 09, 2016, 18:05 Aurelia LaxdalConditioning StationRepairTM3 TM3 vacuum system have been connected at TCS.

Aurelia Laxdal wrote:

David Wang wrote:

All water circuits are by passed on the top of TM3. Water pumps and vacuum turbo- pumps are started. Everything is ready for TM3 camera sparking check.

 Wednesday November 30st: <br>

- 3 cameras (1 UV and 2 regular cameras)  were installed in the Service cap and the module was pumped down.  1 UV and 1 regular were placed on the East side of the module, aiming to water lines entering the Service Tray; 1 regular camera was placed on the South side of the module, aiming at the bottom of the blue insulators.

- started pumping down. <br>

Thursday, December 1st: <br>

- 1st HV test done. TM3 started sparking above 20kV. The cameras responses were consistent with the sparks. However, the screens were flickering and it was not clear if the responses were due to electromagnetic interferences; or due to cameras' gain change caused by high intensity light due to sparking.<br>

- added helium using the regulating valve. same results were found; <br>

Friday, December 2nd: <br>

- vented the module. <br>

- shielded the cameras' cables with aluminum tape. <br>

- removed 2 blue insulator (EE and HS) and shortened them by 1". They were found too long: HS blue insulator touching the horizontal HV water line; and the EE blue insulator at 2-3mm far from the HV water line; re-installed both shortened blue insulators.<br>

- changes the location of the cameras: 1 regular camera taped to the UV camera were placed South, aiming at the bottom of the blue insulators; 1 regular camera was kept on the East side of the module, also aiming at the bottom of the blue insulators. <br>

- started pumping down. <br>

Saturday, December 3rd: <br>

- 2nd HV test was done, with cameras' installed as mentioned above. results were consistent with the first test results. <br>

- added helium. results were the same. <br>

- vented and changed the location of the cameras: 1 regular camera taped to the UV camera were placed at the top of the Service Tray (South-West corner) aiming down the Service Tray; 1 regular camera was kept (its setup was not touched at all) on the East side of the module, aiming at the bottom of the blue insulators. <br>

- attempted to pump down, but the module was leaking. reopened the flanges, cleaned them, attempted again to pump down, but it showed a bigger leak. <br>

Sunday, December 4th: <br>

- the third attempt to pump down was successful (without reopening the module!). <br>

Monday, December 5th: <br>

- did the 3rd HV test with the cameras installed as described on December 3rd. same results as before were seen. <br>

- again helium was added and same results were noticed. <br>

- stopped pumps and prepared for venting to relocate the cameras lower in the Service Tray.

 

 

 

 Monday, December 5th (Con't): <br>

- vented and changed the location of the cameras;<br>

- the UV camera was placed (tapped on an aluminum spacer and on the grounded water lines) at the middle of the Service Tray (right below the first Mykroy insulator-plate) aiming down the Service Tray (at the second Mykroy insulator-plate and water lines) ; <br>

- 1 regular camera was placed right below the UV camera, also using a spacer (taped with the camera on grounded water lines) and also aiming down the Service Tray (at the second Mykroy insulator-plate and water lines);  The spacer for this camera had 300counts on it after it was removed from TM3, after the test;<br>

- NOTE: when installing the 1st regular camera: dropped a small allen key in the Service Tray. It landed on last insulator with the epoxi and water lines, between the first HV line and the wall of the grounded Service Tray.  This insulator is down below in the Service tray. Used a magnet stick to recuperate the allen key. <br>

- the 2nd regular camera was placed at the top of the Service Tray (tapped on the grounded water lines) looking down at the first Mykroy insulator-plate and water lines. NOTE: this camera had a filter applied to its lens. <br>

- pumped down <br>

Tuesday, December 6th:<br>

- did the 4th HV test with the cameras installed as described on December 5rd Tuesday morning very early . Same results as before were seen, except that the top camera (2nd regular camera) with the filter applied to its lens was flickering less than the other 2 cameras, and for small sparks this camera was not reacting at all. <br>

- vented shortly after the 4th test and relocated the cameras for the 5th HV test (last test); <br>

- placed only 2 regular cameras in the Service Tray;<br>

- 1 regular camera was placed right below the 2nd Mykroy insulator-plate, aiming down the Service Tray at the last insulator with the epoxi and water lines (this insulator is down below in the Service tray); <br>

- the 1st regular camera was placed a level up in the Service Tray, right below the 1st Mykroy insulator-plate, aiming down the Service Tray at the 2nd Mykroy insulator-plate; <br>

- NOTE: no spacers were used<br>

- pumped down and did the 5th HV test with the cameras installed as described above in the evening; <br>

- again same results as before were seen: the camera with the filter applied to its lens was flickering less than the other camera, and for small sparks this camera was not reacting at all. <br>

- NOTE: for this last test heard sparks outside (at atmosphere) when the HV was pushed at 26kV; <br>

Wednesday, December 7th:<br>

- vented and removed the cameras from TM3. No contamination was found on the cameras and wires. <br>

- TM3 was moved to the silo.<br>

  1418   Wednesday, January 04, 2017, 14:27 David WangConditioning StationStandard Operation  started TCS vacuum pump

TCS TP1S has been started.

2017-01-23 afternoon: Stopped TP1S. We will use TCS to take TM2 tomorrow afternoon.