  1121   Tuesday, November 10, 2015, 16:53 Anders MjosConditioning StationDevelopmentTM3FEBIAD test targetTesting TM3

Tuesday, November 10, 2015, 16:53: Roughing

Tuesday, November 10, 2015, 18:24: TP1S started

Tuesday, November 10, 2015, 18:30: TP1 and TP2 started

Tuesday, November 10, 2015, 18:41: All 3 turbos at speed.


Thursday, November 12, 2015, 08:30: Purged backing pump using purging function. Vacuum in backing line recovered to previous value. 


Module connected for HV testing. No target heating possible. All F/Ts tied together to HV common. EZL connected.

Friday, November 13, 2015, 11:20: Started water package

Friday, November 13, 2015, 11:52: 1kV on BIAS and 1 kV on EL

Friday, November 13, 2015, 12:54: BIAS/EL 10 / 5 kV

Friday, November 13, 2015, 12:59: BIAS/EL 15 / 7.5 kV

Friday, November 13, 2015, 13:04: BIAS/EL 20 / 10 kV

Friday, November 13, 2015, 13:08 : BIAS/EL 22 / 11 kV. Some sparks.

Friday, November 13, 2015, 13:17: Sparking at 22.5 kV. Had to return to 20 kV to recover. Back at 22.5

Friday, November 13, 2015, 13:21 : BIAS/EL 24 / 12 kV. 

 Friday, November 13, 2015, 13:27: Heavy spakring around 24.5 kV. Had to return to 20 kV to recover.

Friday, November 13, 2015, 13:31: Attempted to increase voltage again. Sparking started around 23 kV. Had to lower to 20 kV.

Friday, November 13, 2015, 13:36: 9 sparks for the last 5 min.

Friday, November 13, 2015, 13:45: Spark rate reduced, but multiple sparks encountered again at 20.5 kV. Reduced back to 20 kV

Friday, November 13, 2015, 13:50: Increased sparking at 20 kV. Had to lower to 18 kV

Friday, November 13, 2015, 14:07: Back at 20 kV

Friday, November 13, 2015, 14:13: BIAS and EL off


Monday, November 16, 2015, 08:18: Fault on chiller. Reset chiller unit on the roof.

Attachment 1: 2015-11-13_TCS_TM3_FEBIAD_Test_Target.docx
  1122   Thursday, November 12, 2015, 10:18 Anders MjosConditioning StationMaintenanceTM3 Air to vacuum leak on service cap

Anders Mjos wrote:

Conducted a more thorough leak check this morning with Edi. He found a leak on the base of the  blue F/T insulator for the multi-pin connector (see attachment). I discovered that all the bolts could rotate freely in the threads as they were too small. The bolts were replaced. The leak rate was reduced but still significant. The o-ring will likely need to be replaced.

Tuesday, November 10, 2015, 17:00: Could not find new o-ring. Cleaned groove and o-ring and applied o-ring grease. Re-attached F/T.

Tuesday

Steerer wire had disconnected again. See DocuShare for photos.


Thursday, November 12, 2015

Leak checked the fixed F/T and the panel for steeerers. No leaks found.

  1123   Thursday, November 12, 2015, 13:25 Anders MjosConditioning StationStandard OperationTM3FEBIAD Test TargetElectrical check and leak check

Target to Anode and target to Common showed ~ 500 kOhm values. No leaks above 3E-9 atm-cc/s seen. See attached.  

Attachment 1: TM3_iwth_FEBIAD_in_TCS_Electrical_Check.pdf
TM3_iwth_FEBIAD_in_TCS_Electrical_Check.pdf
  1124   Monday, November 16, 2015, 08:04 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

Update TH schedule according to changes. See attachment 1,2 .

update TH schedule weekly. See attachments 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1125   Monday, November 16, 2015, 10:09 Anders MjosConditioning StationStandard OperationTM3FEBIAD Test TargetElectrical check after HV conditioning

 Problem found between ANODE (F) and chassis 90 kOhm. See attachment for details.

Attachment 1: 2015-11-16_TM3_Electrical_Test.pdf
2015-11-16_TM3_Electrical_Test.pdf
  1126   Monday, November 16, 2015, 10:33 Anders MjosConditioning StationStandard Operation FEBIAD Test TargetHV conditioning by ISAC operators

ISAC operators attempted HV conditioning over the weekend.

https://web.accel.triumf.ca/isac_elog/Elog_show_result.pl?inid=218447&style=entry

 

  1127   Monday, November 16, 2015, 10:37 David WangConditioning StationRepairTM3 TM3 has been disconnected at TCS.

I stopped the TM3 and TCS vacuum pumps and water system. The TM3 is disconnected and vented. It will be moved to silo this afternoon.

  1128   Monday, November 16, 2015, 13:59 Travis CaveConditioning StationMaintenanceTM3no targetModule moved

TM#3 has been moved back to the NW silo.

  1134   Wednesday, November 25, 2015, 11:55 Travis CaveConditioning StationStandard OperationTM4UC#14Module moved and electrical check.

TM#4 with UC#14 was moved from the south hot cell to the conditioning station.  Here are the results of the electrical check of the module with the UC#14 target while at the hot cell.

Attachment 1: TM4_UC14_elecchk_SHC.PDF
TM4_UC14_elecchk_SHC.PDF
  1137   Wednesday, November 25, 2015, 15:37 Anders MjosConditioning StationStandard OperationTM4UC#14Conditioning

 Wednesday, November 25, 2015, 15:36: RGA on


Thursday, November 26, 2015, 09:55: PS energized. EE connected to power supply.

Thursday, November 26, 2015, 11:41: Applied some current and voltage to all power supplies. All looks good.

Some sparking around 5 kV. Turned out to be a bad cable connection. Fixed with David W.

Thursday, November 26, 2015, 15:04: BIAS/EL/EE 20 / 15 1.5 kV

Thursday, November 26, 2015, 15:43: Handed TCS over to ISAC operations


 Target heated over the weekend. EE went into current limiting (down to ~100 V) a while after the target was at temperature.


Monday, November 30, 2015

Target conditioned by ISAC operators to 30 kV without any problems.

EE current limit increased to about 26 mA in an attempt to recover. Cooling down target to investigate.

  1138   Thursday, November 26, 2015, 06:25 David WangConditioning StationStandard OperationTM4UC#14TM4 vacuum has been connected in TCS.

TM4 vacuum has been connected in TCS. All vacuum pumps were started yesterday. The pumping down of TM4 and TCS are good so far.

  1139   Thursday, November 26, 2015, 07:34 David WangConditioning StationStandard OperationTM4UC#14Helium pressure test on TM4 HS line at CS

I did helium pressure test on TM4 HS line at TCS this morning.  70psi helium 3 minutes, 0.0xE-9 atm.cc/sec base leak rate. No response. No leak.

  1140   Thursday, November 26, 2015, 07:37 David WangConditioning StationStandard OperationTM4UC#14TM4 has been connected at CS

TM4 has been connected at TCS. The water system is started. The TCS HV cover for TM4 is installed also. Basically, The TM4 is ready for conditioning.

  1142   Monday, November 30, 2015, 11:46 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015

Weekly update TH schedule according to changes. see attachment 1,2 .

Update TH schedule before the weekend. see attachment 3,4

Attachment 1: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 2: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
Attachment 3: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdf
Attachment 4: Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp
  1143   Tuesday, December 01, 2015, 06:41 David WangConditioning StationStandard OperationTM4UC#14Turned off TCS all vacuum pumps and water pumps.

I turned off TCS vacuum and water pumps. The TSC and TM4 are still under vacuum condition.

  1145   Tuesday, December 01, 2015, 11:47 Anders MjosConditioning StationMaintenanceTM4UC#14Short on Extraction Electrode

 After conditioning over the weekend the EE developed a short. This was confirmed by measuring the resistance between EE and Heat Shield on the module yesterday.

  1148   Thursday, December 10, 2015, 13:17 Anders MjosConditioning StationStandard Operation  Blank off flange

Thursday, December 10, 2015, 13:17: Roughing

Thursday, December 10, 2015, 14:56: Started TP1S

Thursday, December 10, 2015, 15:59: Bypass applied on IG2

Thursday, December 10, 2015, 15:59: IG2 / IG1S 5.5E-5 T

Thursday, December 10, 2015, 16:01: RGA ON


Friday, December 11, 2015, 09:24 : IG2 / IG1S 7.5E-6 / 5.4E-6 T

Friday, December 11, 2015, 16:54: IG2 off for the weekend. Vacuum at 6.5 and 4.4E-6 Torr


Monday, December 14, 2015, 08:57: IG2 switched on.


Friday, December 18, 2015, 11:40: IG2 off for the weekend. Vacuum at 2.0E-6 and 8.9E-7 Torr 


Tuesday, December 22, 2015, 15:11: RGA off


Monday, January 11, 2016, 10:13: RGA on

Monday, January 11, 2016, 12:50: RGA off

Attachment 1: TCS_Blank_Off.png
TCS_Blank_Off.png
  1149   Friday, December 18, 2015, 11:42 Anders MjosConditioning StationRepair  Vacuum gauges not reading correctly

 It was found that the conversion from voltage to vacuum (Torr) in EPICS is not correct for the XGS-600 controllers in use at the TCS. EPICS did not correspond to local values displayed on the controller. An e-fault has been submitted.

  1150   Monday, December 21, 2015, 13:27 Anders MjosConditioning StationRepair  Vacuum gauges not reading correctly

Anders Mjos wrote:

 It was found that the conversion from voltage to vacuum (Torr) in EPICS is not correct for the XGS-600 controllers in use at the TCS. EPICS did not correspond to local values displayed on the controller. An e-fault has been submitted.

 EPICS conversion updated and corrected by Mike Rowe.

  1154   Friday, February 12, 2016, 13:00 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall Schedule

2016 Winter shut down target hall schedule. See attachments1,2.

 update the schedule weekly. Everything is on time so far. see attachment 3,4.

Update the schedule according to beam new beam schedule and target process. see attachment 5,6

Attachment 1: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 2: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 3: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 4: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf
Attachment 5: 2016_winter_shut_down__target_hall_schedule.mpp
Attachment 6: 2016_winter_shut_down__target_hall_schedule.pdf
2016_winter_shut_down__target_hall_schedule.pdf