Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 115 of 138  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
Entry  Thursday, June 15, 2017, 11:29, Isaac Earle, North Hot-Cell, Development, , , NHC inlet ducting installed IMG_0217.jpgIMG_0218.jpgIMG_0219.jpgIMG_0214.jpg

The North Hot Cell inlet ducting assembly was installed today in the target hall at the north end of the NHC roof block.  A small section of the perforated aluminum sheet on the TCS cage had to be trimmed for the assembly to fit (see IMG_0214).  At each end of the assembly it was fastened to the roof structure using a 1/4"-20 tapped hole in the steel roof, and a 1/4"-20 anchor in the north wall of the target hall.  The base flange of the assembly was sealed to the roof structure and TH wall using Sikaflex 1A polyurethane sealant on all sides.

 

IMG_0217.jpg

 

IMG_0218.jpg

 

IMG_0219.jpg

 

IMG_0214.jpg

Entry  Thursday, June 22, 2017, 11:10, chad fisher, South Hot-Cell, Maintenance, , , In cell airline 

The in cell airline has preemptively been replaced. The hose was, as far as I know the original.

Entry  Friday, June 23, 2017, 12:08, David Wang, Crane, Repair, , , TH crane inspection and probem fixing by Gordon crane  

Gordon crane technician Peter came in today and checked TH crane. Maico and I were there with him. What he found is that brake gap on both side of main hoist decreased after months of using.  The solution is to lock the automatic self adjustment system so the gap will be fixed there. Each year during annual inspection, they will adjust the gap manually. After he locked both side of device, I tested the crane up and down couple of times. The brakes work fine. 

Entry  Friday, June 23, 2017, 17:28, Isaac Earle, North Hot-Cell, Development, , , NHC module flange and cameras installed IMG_0231.jpgIMG_0234.jpgIMG_0240.jpgIMG_0245.jpgIMG_0240.jpg

 The North Hot Cell module support flange (IRH1152D) was installed on June 21, 2017 using 1/8" rubber sheet as a sealing gasket.  The rubber was glued at the seams with Loctite 495 instant adhesive.  Cameras with all required wiring and connectors were installed on the mounting bars (IGN0325D) and then aligned to provide the same view as at other module installation locations in the target hall.  A cable with 5 video signals, and a camera power cable was routed from the south wall in the target hall (where video line connections are), to the panduit on the north wall.  An additional section of cable will be installed to link to the flange cameras after cable covers are installed on the floor.

 

IMG_0231.jpg

 

IMG_0234.jpg

 

IMG_0245.jpg

 

IMG_0240.jpg

Entry  Thursday, June 29, 2017, 11:55, David Wang, Conditioning Station, Repair, , , TCS HV cable and feed through installation 

John Chow and I installed new TCS HV cable and feed through with their mounting panel back to TCS Faraday cage this Tuesday. ECO-4269 has been issued for the new cable feed through and mounting panel.

Entry  Thursday, June 29, 2017, 14:42, Travis Cave, Spent Target Vault, Standard Operation, , UC#20, Spent Target Move Vault_Storage_June_29_2017.pdf

 The spent UC#20 has been moved from the south hot cell to the spent target vault. It was placed in pail #150 and spot 1B in the vault. See attached for details of the vault.

Entry  Wednesday, July 05, 2017, 15:36, Isaac Earle, North Hot-Cell, Development, , , NHC and SHC nuclear ventilation flow sensors installed IMG_0264.JPGIMG_0265.JPG

 Installation of new flow sensors and transmitters for the NHC and SHC duct lines was completed in the target hall today.  The sensors are Dwyer DS-300-8 in-line sensors for 8" pipe; The transmitters are Dwyer MS0121 magnesense differential transmitters with 4-20mA output.  The transmitters will be wired to the new PLC control system when the upgrade is done.

 

IMG_0264.JPG

 

IMG_0265.JPG

Entry  Thursday, July 06, 2017, 14:23, Isaac Earle, North Hot-Cell, Repair, , , Slave side Z motion tape snapped on NHC right side manipulator 

The NHC right side manipulator was evaluated today to check if operation was normal through all ranges of motion.  The manipulator was first moved through usual motions without the electric motion drives: the feel was fairly normal, a sound could be heard from the master side Z motion tapes rubbing on the sides of the pulleys, this problem had been identified a few weeks ago however it was significantly reduced since the master side upper and lower Z motion tapes were tensioned yesterday (using CRL repair manual)

The Y motion drive was then tested:  with the master arm close to the window we attempted to move the slave arm close to the slave side window using the Y motion drive; part way through travel the arm stopped moving and would not move any further towards the window.  At this point it was approximately 1 foot from the slave side window.  (I recall that when the manipulator was installed in the wall it was difficult to get the slave end fully horizontal, the arm would travel part way, then stop for seemingly no reason.  Eventually after multiple attempts I got it to reach the horizontal position)

The Z motion was then tested.  The slave end was moved to the fully extended position.  At this point when the Z drive was continued downwards the master side moved up.  Once it reached the upper limit the drive continued which caused the Z motion tape on the slave end to snap.  At this point testing was stopped.

 

Our plan is to assemble and test the left side manipulator after the manipulator handling cart repair is completed.  If the left side has the same problems it is likely a manufacturer defect.  If not, the problems with the right side may be due to a timing error introduced when we removed the slave end to fit the assembly and cart through the roof hatch from the ISAC-1 experimental hall.  In either case we plan to have  CRL technician come in to address the issues and tune-up both arms before use.

Entry  Monday, July 10, 2017, 09:09, Dan McDonald, North Hot-Cell, Repair, , , manipulator cart repair IMG_2955.JPG

A  hydraulic leak was found on the manipulator  install and repair cart, upon further investigation the cause was a faulty cylinder. Once the cylinder was removed and disassembled the inner bore was found to be scored beyond repair. Another point of interest was that the rod was painted to the point that when retracted it compromised the rod seal causing the cylinder to leak. attached are photos outlining the issues. new cylinders are being sourced and will be installed upon arrival. We have found that there is interaction between the tops of the cylinders and the bed of the cart when fully retracted and compressed, this might require some modifications to ensure proper operation in the future.

 

 

Entry  Wednesday, July 12, 2017, 11:05, Anders Mjos, Conditioning Station, Maintenance, , , Testing of new high voltage cable 2017-07-12_HV_Cable_Test.xlsx

The target hall has been locked-out as per Document-70039.

Forced IG1, IG1S and IG2 to switch on BIAS power supply

Wednesday, July 12, 2017, 11:53: 70 kV at 0.16 mA

2 sparks observed shortly after 70 kV was reached

Wednesday, July 12, 2017, 12:59: No sparks for the last hour.

BIAS power supply off. Forces removed.

Entry  Tuesday, July 18, 2017, 15:04, Travis Cave, Crane, Maintenance, , , Failure of the ISAC TH Crane Rotate. 

 Earlier in the day it was noted that the rotate function of the crane had creased operation. After David has finished the block moves. Don and I checked the Crane's control unit in the ISAC crane control room and found the breaker tripped for the rotation. The breaker was reset and the crane's rotation is now operational. If this occurs in the future only Travis Cave, Don Jackson or a TRIUMF Electrician are allowed in that control box as it is a 480Volt system. Don or I because we know what we are looking for and the Electrician because they are allowed to touch with and deal 480 V systems. 

Entry  Wednesday, August 02, 2017, 15:41, Keith C Ng, Assembly/Bench Test, Development, , , spare source tray build 20170802_sourcetray_RHB_8264.JPG20170802_sourcetray_RHB_8266.JPG

After re zeroing alignment telescope to master jig and adjusted parts into place:

 

Orientation: X = Left -, Right+; Y = Up +, Down -

 

Front wire target

X = 0.000, Y = 0.000

 

Rear wire target

X = 0.000, Y = +.008" (high)

 

All fasteners torqued to specification, steerer housing and assembly not installed yet. Weight of steerer assembly might cause rear to sag into place. Otherwise may attempt to split difference between the front and rear elements (alignment is on an angle in the horizontal vertical plane.)

Entry  Thursday, August 03, 2017, 15:02, Travis Cave, Spent Target Vault, Standard Operation, , SiC#36, Spent Target Move Vault_Storage_August_3_2017.pdf

 The spent SiC#36 has been moved from the south hot cell to the spent target vault.

Entry  Wednesday, August 09, 2017, 16:39, Isaac Earle, North Hot-Cell, Development, , , NHC drain line into sump identified 

 The NHC drain line was tested by pouring approximately 10 gallons of water through the drain grate at the base of the NHC partition wall.  Water was seen a few minutes later pouring into the sump labeled "ACTIVE SUMP" from the light coloured pipe on the west side of the inside of the sump.  Rob Walker had previously said that the hot cells drain into the sump next to this one which is labeled "SANITARY SUMP", which appears to be incorrect.

Entry  Tuesday, August 15, 2017, 12:10, Isaac Earle, North Hot-Cell, Development, , , ISAC Active Sump low water level measured 

The ISAC active sump in the Active Service Room (#002 on B2 level) was pumped out yesterday using the standard procedure (Section 5.5.2 of the ISAC Operators' Manual, V1.0).  The procedure makes use of the auto stop feature of the pump-out system which stops when a low level float switch is triggered.  The water level was measured after pumping stopped, and was found to be approximately 21" above the base of the sump.  A new section of pipe will be added to the 4" drain line in the sump to move the drain opening below the low level water line so that air in the sump is not pulled into the drain network (which could end up in the NHC or TCS space).

Entry  Thursday, August 17, 2017, 14:38, Isaac Earle, North Hot-Cell, Development, , , 4/6 NHC roof blocks installed 7x

 Roof blocks IRH1641, IRH1642, IRH1643, and IRH1644 have been fully assembled, labeled, and installed as per drawing IRH1652.  Fabrication of TCS shield block (IRH1646) and NHC module port block (IRH1645) is still in progress.

 IMG_0381.jpg

 

IMG_0369.jpg

 

IMG_0368.jpg

 

IMG_0364.jpg

 

IMG_0362.jpg

 

IMG_0340.jpg

Entry  Friday, August 25, 2017, 16:33, Anders Mjos, Conditioning Station, Repair, , , Testing HV after cooling line repair 2017-08-25_HV_Water_Line_Test.xlsx

 The BIAS voltage was brought up to 70 kV today and held there for 1h. No sparking observed.

Entry  Wednesday, August 30, 2017, 11:37, Travis Cave, Spent Target Vault, Standard Operation, , Ta#52, Spent Target move Vault_Storage_August_30_2017.pdf

The spent Ta#52 target has been moved from the south hot cell to the spent target vault. See attached PDF for details.

Entry  Tuesday, September 19, 2017, 10:40, chad fisher, South Hot-Cell, Maintenance, , , South East Manipulator Maintenence 

Entered hot cell to preform replacement of slave tong cable. Existing cable shows no signs of wear so it has been re-installed. A spare tong cable has been loaded into a spare tong while in the hot cell in preparation for next time this cable needs to be replaced.

Entry  Thursday, September 28, 2017, 11:59, Travis Cave, Spent Target Vault, Standard Operation, , Ta#53, Spent Target move Vault_Storage_September_28_2017.pdf

The spent Ta#53 has been moved to the spent target vault. See attached file for details.

ELOG V2.9.2-2455