  990   Thursday, July 09, 2015, 14:02 David WangConditioning StationDevelopmentTM1 TM1 is pumping down at CS

TM1 and CS  vacuum system are connected. All turbo-pumps are started. The new TP1S works fine also. The pumping down looks good so far. During the TM1 and CS roughing down time, Joe .M noticed a Rn-220 level surge up in TH . Then,the Rn220  level slowly dropped back. Anders suspected this Rn-220 surging is related to the TM1 roughing down at CS. We decided we will stop the pumps , vent the CS , and roughing  again tomorrow. During the same time Joe will monitor  Rn-220 level in TH to see if the surging is repeatable. We want to learn more on this TH Rn-220 issue.

  992   Friday, July 10, 2015, 14:41 Anders MjosConditioning StationMaintenanceTM1 Replaced roughing pump

 The roughing pump was replaced with a more leak tight pump due to the discovery of Rn-220 migration while roughing on TM1 in TCS

  993   Monday, July 13, 2015, 11:31 Travis CaveConditioning StationStandard OperationTM1no targetModule moved

TM#1 has been moved back to the south west silo from the conditioning station.

  1018   Monday, July 27, 2015, 17:03 David WangConditioning StationStandard OperationTM4UCx 13UCx13 and TM4 under vacuum at CS.

I connected the CS  vacuum system  to TM4. The CS and TM4 turbo pumps are started. Everything is good so far. The HS line will be pressured with helium tomorrow for leak checking. The CS and TM4 will be vented with Argon on Wednesday morning as planned before moved to ITE.

  1019   Tuesday, July 28, 2015, 10:12 David WangConditioning StationStandard OperationTM4UCx 13Helium pressure test on TM4 HS line at CS

I did the helium pressure test on TM4 HS line at CS. Applied 70 psi helium  2 minutes. base leak rate0.0x E-9 atm.cc/sec.  No response during the test. No leak.

  1021   Tuesday, July 28, 2015, 14:31 Travis CaveConditioning StationStandard OperationTM4UC#13Electrical Check

TM#4 with UC#13 electrical check at the conditioning station under vacuum. See attached PDF.

  1024   Wednesday, July 29, 2015, 06:24 David WangConditioning StationStandard OperationTM4UCx 13Stopped the CS and TM4 pumps and vent with argon.

Dan and I stopped the CS and TM4 pumps. We are venting the CS with argon for UCX13 target.

  1036   Thursday, August 13, 2015, 14:36 Travis CaveConditioning StationStandard OperationTM2Dummy TargetModule moved

TM#2 with the dummy target has been moved to the conditioning station.

  1037   Thursday, August 13, 2015, 17:17 David WangConditioning StationRepairTM2Dummy targetTM2 at CS

TM2 has been moved to CS. All turbo-pumps have been started. The pumping down is good so far.  I connected the leak detector to service cap, and finished the leak check today.  The LD base LR:0.0Xe-9atm.cc/sec. 80psi helium were applied to coil1, coil 2. HS and window circuits, each for 2minutes. No any response has been found on LD. So all water lines are leak tight now. I also sprayed   helium to top service cap checking all air to   vacuum seals. They are all good either. But, The new installed PGN1 does not work. Other thing need to mention is The TP2 is running at 2.45A which is 1A higher comparing to TP1. It need to be monitored to see if we have to replace it or not. The high current cables and water lines will be connected tomorrow morning.

  1038   Friday, August 14, 2015, 10:00 David WangConditioning StationRepairTM2 Started CS water package for TM2

I finished the rest TM2 connections to CS, and started CS cooling package. Everything works fine so far.

  1039   Monday, August 17, 2015, 10:44 Anders MjosConditioning StationDevelopmentTM2LP-FEBIAD Test Target (empty)Conditioning TM2 Source Tray with FEBIAD test target

TGHT, TBHT, ANODE and COIL power tested (some amps/volts)

Monday, August 17, 2015, 10:43: BIAS/EL/EE to 15/7.5/1.5 kV

Monday, August 17, 2015, 10:45 : COIL 20A, ANODE 200V

Keiko fixed the auto-ramping program and access rights to it.

Monday, August 17, 2015, 13:06: Auto-ramping at 2/1 A/min. Good/bad vacuum at 6E-6 and 8E-6 T

Monday, August 17, 2015, 13:24 : ANODE current limit set incorrectly. Corrected and 200V (9 mA)

Monday, August 17, 2015, 15:28: COIL to 50 A

Monday, August 17, 2015, 15:43: Reduced ANODE to 100 V

Monday, August 17, 2015, 16:56 : Increased EL to 8.3 kV to increase FC current.

Monday, August 17, 2015, 17:04 : FC0 current at 1.5E-8 A

Beam ionized and accelerated on the new TM2 source tray

Monday, August 17, 2015, 17:12 : TGHT / TBHT at 500 / 250 A. Will leave over night to outgas. ISAC ops are monitoring the source.


Tuesday, August 18, 2015, 08:07: Everything stable overnight. Continue ramping heaters.

Tuesday, August 18, 2015, 08:48: TBHT voltage limited by EPICS (hardcoded) at 273 A.

TGHT/TBHT at 600 / 273 A 

Tuesday, August 18, 2015, 09:52: Adjusted COIL current down to 0 and back up. Response seen on FC0.

Tuesday, August 18, 2015, 22:29 : Starting cool down.


 Wednesday, August 19, 2015, 08:26: Source and HV off. EE configured to conditioning mode. RGA off.

Wednesday, August 19, 2015, 08:42: BIAS/EL at 15 / 7.5 kV. PNG1 at 3.5E-6 T, IG1 at 3.9E-7 T

Wednesday, August 19, 2015, 08:53: BIAS/EL 20 / 10 kV. 2 sparks.

Wednesday, August 19, 2015, 09:54: BIAS/EL 30 / 15 kV. Some sparking around 28 kV required BIAS voltage to be reduced momentarily. 

Wednesday, August 19, 2015, 10:04: Sparking at 30 kV. Reduced BIAS to 13 kV to get spar rate to less than 10/min

Wednesday, August 19, 2015, 10:19 : BIAS current limiting. Switch off BIAS and EL

Wednesday, August 19, 2015, 12:04: Water off for purging and leak test.

Wednesday, August 19, 2015, 12:52: Vacuum response observed while David was working on purging the water lines. This turned out to be when the valve to the leak detector was opened.

  1040   Wednesday, August 19, 2015, 14:52 David WangConditioning StationRepairTM2 TM2 at CS

During the TM2 HV test at CS, It failed. In order to confirm there is no any water leak inside the module after the heaters and beam extraction test, I disconnected all the water lines on the TM2, and purged the water lines with pressure air. Leak detector was reconnected back to the TM2 service cap, and all water lines are pressurized with 80psi helium again each for 2 minutes.No any leak had been found during the test. All the water lines are still perfectly sealed. Also, I checked all the vacuum to air seals on the top of the module.They are good either.  Anders used the RGA  tracking the helium during the test. No leak.

  1041   Thursday, August 20, 2015, 09:38 David WangConditioning StationRepairTM2 TM2 was disconnected at CS

TM2 was disconnected at CS. Travis and I did  electrical check before the venting. After,The module was vented and moved to SHC. The moving is smooth.

  1043   Thursday, August 20, 2015, 11:00 Travis CaveConditioning StationStandard OperationTM2Dummy TargetElectrical Check

TM#2 electrical check at the conditioning station. All pumps were off but the module was not vented.

  1044   Thursday, August 20, 2015, 13:48 David WangConditioning StationStandard OperationTM2 Target Hall Scheduled Activities April 07 - Sep 08 2015

 Weekly update target hall schedule.See attachment 1,2

Spring and summer run is close to the end. This will be the last update on this old schedule. See attachment3,4.    A new schedule for TH activities after mini shut down will be posted next time.

  1048   Wednesday, August 26, 2015, 09:54 Anders MjosConditioning StationMaintenance  Topped up water in TCS:TK2

 Filled to 24.9 in

  1050   Wednesday, August 26, 2015, 11:12 Travis CaveConditioning StationStandard OperationTM2ZrC #7Module moved

TM#2 with ZrC#7 has been moved to the conditioning station from the south hot cell.

  1051   Wednesday, August 26, 2015, 14:28 David WangConditioning StationStandard OperationTM2ZrCLeak check on TM2 HS and windowwater line with new ZrC target at SHC

Chad and I leak checked TM2 HS and window circuit VCR joints with ZrC target and containment box installed at SHC. No leak has been found. They will   be helium pressurized  at CS later.

  1052   Wednesday, August 26, 2015, 14:30 David WangConditioning StationStandard OperationTM2ZrCTM2 and Cs vacuum sysyem has been connected at CS.

Turbo-pumps are started . The pumping down is good so far.

  1053   Wednesday, August 26, 2015, 14:52 David WangConditioning StationStandard OperationTM2ZrCHelium pressure test on TM2 HS and window lines at CS

LD base LR 0.0xE-9 atm.cc/sec , 80 psi helium 2 minutes on HS and window circuits. No leak. Also, the reinstalled(after rewiring job) TP2 and PNG1(steers) side panel have been leak checked. No leak.