2463
|
Wednesday, July 12, 2023, 22:21 |
Carla Babcock | North Hot-Cell | Standard Operation | | TiC#5 | TiC#5 post irradiation inspection results | The TiC#5 post irradiation inspection was
done on Wed. June 14 and Mon. June 19. This
target didn't have any obvious issues but |
|
2467
|
Tuesday, July 25, 2023, 16:25 |
Carla Babcock | North Hot-Cell | Standard Operation | | SiC#45 | SiC#45 post irradiation inspection | Looked at SiC#45 in the hot cell. Looked
very clean, no deposits on the heat shield
or other components. Target also looked very |
|
2476
|
Wednesday, August 09, 2023, 13:43 |
Carla Babcock | North Hot-Cell | Standard Operation | TM2 | TiC#6 | TiC#6 PIE | PIE on TiC#6 was done in the NHC. The target
assembly looked brand new when we took it
out, no heating spots or deposits (pictures |
|
2508
|
Wednesday, November 29, 2023, 12:45 |
Carla Babcock | ITE | Standard Operation | | | gas lines pumped down | Pumped down the gas lines in ITE on Tuesday
Nov. 28 2023 and opened the CF4 bottle valves.
Missed the small section between the regulator |
|
2513
|
Tuesday, January 02, 2024, 16:01 |
Carla Babcock | Conditioning Station | Development | TM3 | | TM3 service tray HV testing and conditioning | Tuesday, January 02, 2024, 15:58 :
Started HV ramp up on TM3 service
tray about 3pm today. Had to bypass TCS:BIAS |
|
2519
|
Wednesday, January 10, 2024, 16:51 |
Carla Babcock | ITE | Standard Operation | TM4 | UCx#43 | UCx#43 failure | To deliver stable beam to RadMol,
started heating UCx#43 up again. Target was
overheated during initial conditioning in |
|
2524
|
Wednesday, January 17, 2024, 20:09 |
Carla Babcock | South Hot-Cell | Standard Operation | | Ta#66 | Ta#66 post irradiation inspection | On Jan. 9 we did the PIE on Ta#66. Opened
the heat shield and removed the EE. The inside
of the heat shield was very black with lots |
|
2536
|
Friday, January 26, 2024, 16:48 |
Carla Babcock | South Hot-Cell | Standard Operation | TM4 | UC43 | UCx#43 PIE | UCx#43 PIE was done in the SHC. As expected
based on electrical measurements, the target
container was broken on the right side and |
|
2541
|
Monday, February 12, 2024, 18:44 |
Carla Babcock | ITW | Maintenance | | | ITW annual HV testing | ITW was set up for HV testing - water is
running and at a high resistivity due to
injected N. Einzel lens is attached to ground. |
|
2545
|
Thursday, February 15, 2024, 17:40 |
Carla Babcock | ITE | Standard Operation | | | ITE annual HV testing | ITE was set up for HV tests - this time
the module plug was not in so the BIAS and
EE had to be bypassed. NOTE: ITE:BIASPLC |
|
2566
|
Tuesday, April 23, 2024, 17:34 |
Carla Babcock | South Hot-Cell | Repair | TM3 | | TM3 wire pulling | Wires were pulled in TM3 and service cap
was closed up again:
Einzel lens wire (30kV kapton), routed |
|
2581
|
Thursday, May 02, 2024, 18:48 |
Carla Babcock | ITW | Standard Operation | | | ITW cage setup | ITW gas lines pumped down to 2e-3Torr on
leak detector with leak rate in the low e-7
atm-cc/s. Gas bottles opened at 3psi and |
|
2591
|
Tuesday, May 14, 2024, 15:27 |
Carla Babcock | ITE | Development | TM3 | UCx#44 | TM3 conditioning and testing in ITE | Tuesday, May 14, 2024, 10:26 :
Ramping up bias/EE/EL on ITE - will
see if the HV cage in the pit can hold 60kV |
|
2604
|
Tuesday, June 04, 2024, 11:44 |
Carla Babcock | South Hot-Cell | Development | | empty LP FEBIAD | investigation of cathode short on empty LP FEBIAD | On May 30 Aaron, Chad and I removed the
empty LP FEBIAD target from the SHC into
the anteroom to attempt to find out the source |
|
2613
|
Friday, June 14, 2024, 16:04 |
Carla Babcock | ITW | Repair | TM4 | UC#45 | Replaced and reinstalled electronics in ITW cage | ITW has been behaving badly at higher voltages
recently, even without protons on. I conditioned
it up to 50kV with heaters off in the TCS |
|
2615
|
Monday, June 17, 2024, 17:24 |
Carla Babcock | ITE | Development | TM3 | UCx#44 | Status of gas system prototype in ITE | A new gas system for FEBIAD operation was
installed in ITE to enable us to use a calibrated
leak which is attached to the target heat |
|
2622
|
Monday, June 24, 2024, 14:37 |
Carla Babcock | South Hot-Cell | Development | TM3 | UCx#44 | Inspection of TM3 and UCx#44 after no-protons run | TM3 and UCx#44 ran in ITE but issues with
the cyclotron prevented proton beam delivery.
Nonetheless, the target was heated and provided |
|
2630
|
Thursday, July 04, 2024, 01:20 |
Carla Babcock | ITE | Development | TM3 | SiC#46 | TM3 conditioning with protons | Initial Summary:
TM3 sparking behaviour in ITE has
been very disruptive both with and without |
|
2636
|
Tuesday, July 09, 2024, 16:14 |
Carla Babcock | ITE | Repair | | | Attempts to reduce ITE:EL trips from HV sparks | ITE:EL has been tripping off due to HV
sparks. Usually this also trips ITE:Q1/2.
These are sitting in side-by-side racks. |
8x |
2654
|
Sunday, August 11, 2024, 11:25 |
Carla Babcock | South Hot-Cell | Repair | TM3 | TiC#8 | short on multipin wires to TBHT discovered | With the new TiC#8 target installed on
TM3, there was a ~7kOhm connection between
TGHT/TBHT (A/B/C/D) and HV common. The standard |
|