Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC, Page 111 of 135  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
Entry  Tuesday, October 22, 2013, 14:23, Anders Mjos, ITE, Standard Operation, TM3, NiO#2, Padlle wheel frequency measurements ITE-TM3-NiO#2-HP-FEBIAD_Water_Flow.pdf
Entry  Tuesday, October 22, 2013, 11:18, Travis Cave, ITW, Standard Operation, TM1, UC#7, module move 
Entry  Monday, October 21, 2013, 12:29, Bevan Moss, Conditioning Station, Repair, TM4, , BIAS Canbus 
Entry  Monday, October 21, 2013, 10:52, Bevan Moss, Conditioning Station, Standard Operation, TM4, , Cooling On and Electrical Connections Made 
Entry  Friday, October 18, 2013, 15:55, Bevan Moss, Conditioning Station, Standard Operation, TM4, , Turbo Pumps are on 
Entry  Friday, October 18, 2013, 14:56, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, Electrical check TM#4_no_target_post_coilelectest.PDF
Entry  Friday, October 18, 2013, 14:37, Bevan Moss, Conditioning Station, Standard Operation, TM4, , Roughing Started 
Entry  Friday, October 18, 2013, 14:33, Bevan Moss, South Hot-Cell, Standard Operation, TM4, , Module move 
Entry  Friday, October 18, 2013, 13:43, chad fisher, South Hot-Cell, Repair, TM4, , C2 Circuit Removal IMG_1224[1].JPGIMG_1227[1].JPGIMG_1230[1].JPG
Entry  Friday, October 18, 2013, 10:17, Bevan Moss, ITW, Repair, , , Paddle Wheel 
Entry  Thursday, October 17, 2013, 17:16, Grant Minor, ITE, Repair, , , Pre-Separator-area (ITE Harp 9) Blocks Replaced 8x
Entry  Thursday, October 17, 2013, 10:24, chad fisher, South Hot-Cell, Repair, TM4, , Coil Line Removal TM4_C2_circuit.pdf
Entry  Wednesday, October 16, 2013, 18:53, Grant Minor, ITE, Repair, , , ITE Harp 9 Removed & Blanked-Off - blocks NOT YET replaced 11x
Entry  Wednesday, October 16, 2013, 10:12, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, module move 
Entry  Tuesday, October 15, 2013, 16:44, Grant Minor, Crane, Repair, , , Target Hall Crane - operational with temporary thermal sensor bypass ISAC_THall_Crane_elec_E5_1slash1_15Oct2013.pdf
Entry  Tuesday, October 15, 2013, 15:34, Bevan Moss, ITE, Standard Operation, TM3, , Blocks moved from ITW to ITE 
Entry  Tuesday, October 08, 2013, 18:12, Grant Minor, Crane, Repair, TM4, , Target Hall Crane Stuck in East-West Direction - Update THall_Crane_Bridge_Wheel_at_South_Rail_Splice_8Oct2013.JPGNORELCO_inv13045_joMS-064_31March2013.pdf
    Reply  Wednesday, October 09, 2013, 19:33, Grant Minor, Crane, Repair, TM4, , Target Hall Crane not operational - likely controls / PLC hardware failure (not stuck wheel) 
Entry  Tuesday, October 08, 2013, 14:58, Anders Mjos, South Hot-Cell, Standard Operation, , SiC#29, Target to Heat Shield electrical short 
Entry  Tuesday, October 08, 2013, 14:55, Travis Cave, South Hot-Cell, Standard Operation, TM4, no target, module move 
Entry  Tuesday, October 08, 2013, 13:11, Travis Cave, Spent Target Vault, Standard Operation, , SiC#29, Spent target move Vault_Storage_October_8_2013.pdf
ELOG V2.9.2-2455