ID Date Author Category Type Moduledown Target/Number Subject Text Attachments
  1136   Wednesday, November 25, 2015, 14:16 chad fisherSouth Hot-CellRepair  Cell DeconCell (table) was systematically cleaned
with a swiffer and resulting piles of contaminated
waste placed in pail with spent Ta target.
 20151125_100512.jpg20151125_101620.jpg 
  1141   Thursday, November 26, 2015, 08:52 Travis CaveSpent Target VaultStandard Operation Ta#46Spent Target moveTa#46 was placed in the ISAC spent target
vault yesterday. See attached PDF for details.
 Vault_Storage_November_26_2015.pdf 
  1142   Monday, November 30, 2015, 11:46 David WangConditioning StationStandard Operation  Target Hall schedule from Sep 08th 2015 to Dec 25th 2015Weekly update TH schedule according to
changes. see attachment 1,2 .
Update TH schedule before the weekend.
 Target_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mppTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.pdfTarget_Hall_Scheduled_Activities__Sep_09_to_Dec_30.mpp 
  1147   Wednesday, December 02, 2015, 10:41 chad fisherSouth Hot-CellRepair  Drum Clean-up #2Another drum of waste was removed from
the south hot cell this morning. This drum
contained one 5 gal steel pail (damaged),
  
  1148   Thursday, December 10, 2015, 13:17 Anders MjosConditioning StationStandard Operation  Blank off flangeThursday, December 10, 2015, 13:17: Roughing
Thursday, December 10, 2015, 14:56:
Started TP1S
 TCS_Blank_Off.png 
  1149   Friday, December 18, 2015, 11:42 Anders MjosConditioning StationRepair  Vacuum gauges not reading correctly It was found that the conversion
from voltage to vacuum (Torr) in EPICS is
not correct for the XGS-600 controllers in
  
  1150   Monday, December 21, 2015, 13:27 Anders MjosConditioning StationRepair  Vacuum gauges not reading correctly

    

       
            
  
  1151   Friday, January 08, 2016, 09:29 chad fisherSouth Hot-CellRepair  Window DeconEntered the hot cell to perform final decon
on the window. Initial swipes this morning
were 11000 c.p.m. on 44-2. After decon approximately
  
  1152   Wednesday, January 13, 2016, 09:57 Travis CaveSpent Target VaultStandard Operation Ta#35, Ta#39, SiC#27, UC#12, ThO#1Spent targets moved to mini storage.Five spent targets have been moved from
the Spent Target Vault to Mini Storage in
preparation for transfer to F-308s in February.
  
  1153   Friday, January 22, 2016, 14:24 David WangSouth Hot-CellStandard Operation  2016 Winter Shut Down Target Hall Schedule (sketch)Post a sketch of 2016 winter shut down
target hall schedule. see attachment 1,2
 UPDATE THE SCHEDULE ACCORDING
 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp 
  1154   Friday, February 12, 2016, 13:00 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall Schedule 2016 Winter shut down target hall schedule.
See attachments1,2.
 update the schedule weekly.
 6x 
  1155   Friday, February 19, 2016, 06:58 maicodallavalleSpent Target VaultMaintenance  F-308's serviced/loaded/ bolts torquedFive F-308's were loaded with spent ISAC
targets. All five F-308's were serviced two
weeks ago. All bolts were torqued and security 
  
  1156   Thursday, February 25, 2016, 06:48 David WangITEStandard Operation  4 Shielding blocks have been transferred from ITE to block storage area.Dan and I transferred 4 shielding blocks
from ITE to block storage area. The ITE pit
is opened now.
  
  1157   Thursday, February 25, 2016, 06:52 David WangConditioning StationStandard Operation  stop CS vacuum pumps.I stopped the conditioning station vacuum
pumps. The CS is still under vacuum without
venting.
  
  1163   Friday, March 04, 2016, 13:58 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall ScheduleUpdate Schedule according to changes.See
attachment1, 2.
 Re-post it after some minor
 8x 
  1164   Monday, March 14, 2016, 11:24 David WangITE/ITW CoolingMaintenance  HALCW resin tank filter cartridges are changed todayTwo of resin tank filter cartridges(supply
and return) are changed today. Old cartridges
and bagged and tagged. The contact field
 002.JPG003.JPG006.JPG 
  1172   Friday, March 18, 2016, 11:43 chad fisherSouth Hot-CellStandard Operation  SiC#32 dissectionSiC#32 has been open for inspection.  20160318_105519_1.jpg20160318_105311.jpg20160318_105248.jpg20160318_105428.jpg 
  1177   Tuesday, March 22, 2016, 10:27 Travis CaveSpent Target VaultStandard Operation SiC#32Spent Target moveSiC#32 has been moved from the south hot
cell to the spent target storage. See attached
PDF for details.
 Vault_Storage_March_22_2016.pdf 
  1183   Wednesday, March 30, 2016, 08:40 David WangConditioning StationStandard Operation  2016 Winter Shut Down Target Hall Scheduleupdate the schedule according to changes.See
attachment1, 2.
 2016_winter_shut_down__target_hall_schedule.pdf2016_winter_shut_down__target_hall_schedule.mpp 
  1200   Friday, April 08, 2016, 08:13 Anders MjosITE/ITW CoolingMaintenance  High Active Water ResistivityThe high active water resistivity took
a long time to recover after the upgrade
to the water cooling circuit. The system
 2016-04-08_ISAC_High_Active_Water_Resistivity.png 