848
|
Wednesday, February 25, 2015, 10:44 |
David Wang | ITW | Maintenance | | | 2015 shut dwon ITW water sensor coils and pedal wheels replacement | Dan and I replaced pedal wheels and coils
on ITW water flow sensors. It is a shut
down job we did every two years. See attachment |
|
849
|
Thursday, February 26, 2015, 09:22 |
David Wang | ITW | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Mar 25th | TH shut down activities schedule from Feb
23th-March 25th. The schedule will be updated
each week. See attachment 1. |
 |
850
|
Friday, February 27, 2015, 09:34 |
chad fisher | South Hot-Cell | Maintenance | | | Hot cell Entry February 25 2015 | See attached report.
Summary:
Radio problems just before entry |
|
853
|
Thursday, March 05, 2015, 07:17 |
David Wang | ITW | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | TH shut down jobs are processing as scheduled
this week. Discussed with Don, and we think
the jobs scheduled in next week should be |
6x |
854
|
Thursday, March 05, 2015, 14:30 |
chad fisher | South Hot-Cell | Development | | | Dissection Box | Box for dissecting targets almost complete.
Should be done tomorrow. |
|
855
|
Monday, March 09, 2015, 09:42 |
chad fisher | South Hot-Cell | Development | | | Hot Cell Table Swiping | 3 swipes of the south hot cell table were
taken from the target hall through the roof
hatch (2 standard, 1 alpha). |
|
861
|
Friday, March 13, 2015, 13:36 |
Travis Cave | Spent Target Vault | Standard Operation | | ThO#1 | Spent Target Move | The ThO#1 has been placed in the storage
vault placed in pail #122 in spot 2B of the
vault. It was 6.2mSv/hr upon removal from |
|
864
|
Tuesday, March 17, 2015, 10:33 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#11 | Spent Target Move | The spent UC#11 has benn moved from the
south hot cell to the spent target vault.
See attached PDF for details. |
|
865
|
Friday, March 20, 2015, 13:37 |
chad fisher | South Hot-Cell | Development | | | TM2 Optics Tray | Final assembly and alignment of TM2 optics
tray continued today. Front section is "aligned". |
![20150320_113132[2].jpg 20150320_113132[2].jpg](attachment.png) |
866
|
Monday, March 23, 2015, 07:56 |
David Wang | ITE | Standard Operation | | | TH Shut Down Activities Schedule Feb 23th- Apr 15th update | This schedule is following Dons schedule
on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule. |
   |
867
|
Monday, March 23, 2015, 14:03 |
chad fisher | South Hot-Cell | Standard Operation | | Ta#45 | Ta#45 inserted into hot cell | Ta#45 has been inserted into the hot cell.
Swipe taken of inner tool port area: 100000
counts/min. |
|
871
|
Wednesday, March 25, 2015, 10:37 |
chad fisher | South Hot-Cell | Development | | | TM2 optics tray build | TM2 optics tray build is continuing. Going
well. Hope to have assembly and alignment
finished by Friday. |
  |
885
|
Monday, April 13, 2015, 08:59 |
David Wang | ITE | Standard Operation | | | Target Hall Scheduled Activities April 07 - June 26 2015 | See attachments 1, 2 for target hall schedule
from 07 April to 26 June 2015. The first
TM1 move which is scheduled on 16 April 2015 |
   |
886
|
Wednesday, April 15, 2015, 09:01 |
Anders Mjos | Conditioning Station | Development | | | Archiver variables added by Controls |
|
|
903
|
Tuesday, April 28, 2015, 11:09 |
Anders Mjos | ITW | Maintenance | | | Resistance measured of TGHT and TBHT lines to ITW | The new TBHT and TGHT power supplies were
brough up to high current; 350 A and 420
A respectively. The TGHT power supply was |
|
909
|
Monday, May 04, 2015, 13:32 |
Anders Mjos | Conditioning Station | Maintenance | | | TK2 expansion tank topped up | Caled cyclotron ops to open P23 and confirmed
penthouse valve open.
Filled up TK2 to 21 in water leve. |
|
913
|
Monday, May 11, 2015, 10:45 |
Anders Mjos | Conditioning Station | Maintenance | | | RGA electronics box installed | The communications chip has been
replaced. The electronics box has been grounded
(see attached pdf). |
|
930
|
Wednesday, June 03, 2015, 11:22 |
David Wang | Conditioning Station | Standard Operation | | | Target Hall Scheduled Activities April 07 - July 21 2015 | I revised the Target Hall schedule to July
21 2015. It is the time new TM2 with ZrC
target started at ITW. |
   |
945
|
Friday, June 12, 2015, 13:27 |
David Wang | South Hot-Cell | Standard Operation | | | TM2 new source tray has been remotely transferred from TH into SHC successfully. | TM2 new source tray has been remotely transferred
into SHC successfully. The transfer table
has been moved back to TH within 1 hour. |
|
948
|
Monday, June 15, 2015, 14:14 |
David Wang | South Hot-Cell | Standard Operation | | | Target Hall Scheduled Activities April 07 - July 21 2015 | Weekly update Target Hall schedule 2015-06-15.
See attachment 1,2
2015-06-19, Update the schedule |
   |