2194
|
Thursday, March 04, 2021, 11:20 |
David Wang | ITW | Maintenance | | | ITW water flow wheels and coils replacement. |
ITW water flow wheels and coils are replaced. Wheels and coils on Oven, Tube, HS, EE, MSP, Febiad coil, containment box window, dump,dump plug, 2A window, and tank return circuits are replaced with new parts. |
2195
|
Thursday, March 04, 2021, 13:54 |
David Wang | Conditioning Station | Standard Operation | TM3 | | TM3 has been moved to NHC from silo |
TM3 has been moved from silo to NHC. The move is successful. NHC ram stand and NHC protection railings are checked and installed. Everything works fine.
2021-03-05. TM3 has been moved from NHC to silo. The move is successful. |
2203
|
Tuesday, March 23, 2021, 09:47 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | TM3 has been moved from TCS to SHC. |
Frank and I removed Tm3 from TCS to SHC. The move is successful. |
2205
|
Thursday, March 25, 2021, 10:38 |
David Wang | Spent Target Vault | Standard Operation | | C#1 | Remove pail 237 spent target C#1 from storage vault to mini storage. |
Pail 237 only has 200u sv/hr field at 0.5 meter. On contact measurement: 0.9 to 1.6 m sv/hr.and less than 80 count contamination outside the pail. It is moved to mini storage. We will transfer this pail to cyclotron vault and store it there later. |
2209
|
Wednesday, April 21, 2021, 10:32 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | Remotely remove TM3 from SHC to silo |
On 2021-04-19, Frank and I remotely removed Tm3 from SHC to silo . The moving is successful. |
2210
|
Wednesday, April 21, 2021, 10:34 |
David Wang | South Hot-Cell | Standard Operation | TM4 | | Remtely remove TM4 from Silo to SHC. |
On 2021- 04-20, Tm4 is removed from Silo to SHC. The moving is smooth. |
2211
|
Wednesday, April 21, 2021, 11:18 |
David Wang | Cooling | Maintenance | | | Refilling high active wtaer system and starting HA water pumps. |
High active water system is refilled. Air are drained out of system before pump to be started. Following sequence are used to bring the whole system back to operation:
1. close ITE , open ITW. Switch on the pump. Only 2A beam line related 5 water circuits are in loop in ITW. Switch off pump when system pressure is stable above 100 psi.
2. Close ITW, open ITE. Switch on the pump. Only 2A beam line related 5 water circuits are in loop in ITE. Switch off pump when system pressure is stable above 100psi.
3. Open ITW, Open ITE. Switch on pump. both ITW and ITE beam line related water circuits are in loop. Switch off pump when system pressure is stable above 100psi.
4. Close ITE open ITW. Bring ITW target module water circuits back to loop by connecting bypass fittings on to circuits. Only bring one circuit back to system at first. Switch on pump. Wait for system pressure stabilized. Then Close ITW. bring next circuit back to system. Open ITW . wait for pressure stabilized. repeat the process until all water circuit and connected with bypass fittings in ITW.
5. Check possible leak on valves, fittings, and flow sensors in ITW pit.
6. Go to electrical room, check all ITW water signal status.
7. Close ITW, Open ITE. Repeat same procedure as step 4 on ITE target module water circuits.
8. Check possible leak on valves, fittings and flow sensors in ITE pit.
9. Go to electrical room, check all ITE water signal status.
10. Open ITW. At this stage, full ITE station and half of ITW station water circuits are in operation. Check possible leak on pumps, valves, fittings, gauges on water station at TH west end.
11. Keep system in operation. Watch on - tank level , system pressure, and conductivity on resin circuit and whole system. |
2212
|
Thursday, April 22, 2021, 08:41 |
David Wang | South Hot-Cell | Repair | TM4 | | TM4 steerer electical check at SHC and TH. |
Using SHC electrical test cables routed to to TH, We tested TM4 steerer 4 polarities. At 100v megga test, left, right , up and down to ground are all OL. TM4 steerer has no short. |
2213
|
Monday, April 26, 2021, 13:02 |
David Wang | South Hot-Cell | Repair | TM4 | | TM4 new steerer cable installation. |
New steerer cables are installed in TM4. Cables are properly routed in containment box and service cap top. After job, TP2 is installed back onto module top. |
2216
|
Friday, May 14, 2021, 11:29 |
David Wang | Spent Target Vault | Standard Operation | | | Repack of 4 spent targets. |
Repack of 4 spent targets in TH and SHC. SiC#37 to new pail249#. SiC#36 to new pail 250#. Nb#8 to new pail 247#, SiC#33 to new pail 248#. They are all in mini storage. Also, UCx 31 are transferred to mini storage. There are 5 spent targets in mini storage now.
2021-05-20: 5 spent targets have been loaded into F308's. We transferred two more spent targets into mini storage this morning for next week loading. |
2220
|
Monday, May 31, 2021, 11:28 |
David Wang | ITE | Standard Operation | TM4 | | Remotely remove TM4 from silo to shc |
Remotely remove tm4 from silo to shc. The moving is smooth. |
2221
|
Thursday, June 03, 2021, 08:19 |
David Wang | ITE | Repair | TM4 | UCX33 | Replaced ITE TP4 |
Replaced ITE TP4 due to failure start. The new pump works fine. |
2222
|
Thursday, June 03, 2021, 08:20 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | Remotely remove TM2 from silo to shc |
Remotely removed Tm2 from silo to SHC. The moving is smooth. |
2223
|
Thursday, June 03, 2021, 08:33 |
David Wang | South Hot-Cell | Standard Operation | TM4 | UCX32# P2N | P2N UCX 32 on TM4 electical check and leak check at SHC. |
Both electrical check and leak check (HS and Window lines)results are good. See attachments
Correction: It should be UCx#32 P2N instead of UCx33# in check list attached . UCx#33 is on TM2 in ITW |
Attachment 1: P2N_UCX33#_target_electrical_chek_at_SHC_2021_0601.pdf
|
|
2225
|
Wednesday, June 09, 2021, 10:15 |
David Wang | ITE/ITW | Standard Operation | TM4 | UCX33. | ITE water signal interlock check. |
Annual ITE water signal interlock check is done. HS, TAR, TUBE, MSP, EE, COIL 1, containment box window, HVC1, HVC2, 2A window, 2A shielding plug, 2A dump, 2A collimator, and 2A tank water signal interlock are checked. Everything is working properly.
2021-06-22. Annual ITW water signal interlock check is done, HS, TAR, MSP, EE, COIL1 , containment box window, HVC1 , HVC2, 2A window, 2A shielding plug, 2A dump, 2A collimator, and 2A tank water signal interlock are checked. Everything works fine. |
2226
|
Wednesday, June 09, 2021, 10:48 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | TM2 containment box leak check. |
Chad installed containment box back to TM2 yesterday. We leak checked VCR joints on window line. No leak. |
2227
|
Thursday, June 10, 2021, 14:54 |
David Wang | North Hot-Cell | Standard Operation | TM2 | UCX33 | UCX 33 on TM2 electical check at NHC. |
TM2 UCX33# electrical check and leak check results. See attachment. |
Attachment 1: UCX33_TM2_electrical_check.pdf
|
|
2228
|
Friday, June 11, 2021, 10:36 |
David Wang | Conditioning Station | Standard Operation | TM2 | UCX33# | TM2 leak check at TCS |
Leak checked TM2 service cap at TCS. helium pressure checked containment box window and HS cooling lines. No leak on service cap and waterlines. |
2229
|
Tuesday, June 22, 2021, 15:35 |
David Wang | ITW | Standard Operation | TM2 | UCX33# | TM2 has been connected it ITW. |
TM2 has been connected it ITW. All turbo pumps are started. |
2232
|
Thursday, July 08, 2021, 11:36 |
David Wang | Conditioning Station | Standard Operation | TM4 | Ta#62 | Remotely remove TM4(Ta#62) from SHC to TCS. |
Remotely remove TM4 (ta# 62) from SHC to TCS. The moving is smooth. |