  868   Tuesday, March 24, 2015, 08:46 Travis CaveConditioning StationStandard OperationTM4No targetModule moveTM#4  with no target has been moved
from conditioning station to the south hot
cell.
  
  867   Monday, March 23, 2015, 14:03 chad fisherSouth Hot-CellStandard Operation Ta#45Ta#45 inserted into hot cellTa#45 has been inserted into the hot cell.
Swipe taken of inner tool port area: 100000
counts/min.
  
  866   Monday, March 23, 2015, 07:56 David WangITEStandard Operation  TH Shut Down Activities Schedule Feb 23th- Apr 15th updateThis schedule is following Dons schedule
on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule.
 Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp 
  865   Friday, March 20, 2015, 13:37 chad fisherSouth Hot-CellDevelopment  TM2 Optics TrayFinal assembly and alignment of TM2 optics
tray continued today. Front section is "aligned".
 20150320_113132[2].jpg20150320_113018_1[1].jpg 
  864   Tuesday, March 17, 2015, 10:33 Travis CaveSpent Target VaultStandard Operation UC#11Spent Target MoveThe spent UC#11 has benn moved from the
south hot cell to the spent target vault.
See attached PDF for details.
 Vault_Storage_March_17_2015.pdf 
  863   Monday, March 16, 2015, 14:16 Travis CaveConditioning StationStandard OperationTM4No targetModule moveTM#4 from south hot cell to the conditioning
station no target is attached to the module.
  
  862   Monday, March 16, 2015, 09:41 Travis CaveITEStandard OperationTM4UC#11Module moveTM#4 with UC#11 moved from the east target
station to the south hot cell.
  
  861   Friday, March 13, 2015, 13:36 Travis CaveSpent Target VaultStandard Operation ThO#1Spent Target MoveThe ThO#1 has been placed in the storage
vault placed in pail #122 in spot 2B of the
vault. It was 6.2mSv/hr upon removal from
 Storage_Vault_March_13_2015.pdf 
  860   Thursday, March 12, 2015, 13:33 Anders MjosSouth Hot-CellStandard OperationTM1ThO#1Target inspectionChad, Anders and Alex inspected the target
this morning. The target had no significant
visible damage to the container. Some material
  
  859   Thursday, March 12, 2015, 13:04 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITE to ITW.5 shielding blocks have been transferred
from ITE to ITW for next week TM4 move.
  
  858   Thursday, March 12, 2015, 09:48 Travis CaveSouth Hot-CellStandard OperationTM2No target Module moveTM#2 with no target and no source tray
has been moved from the conditioning station
to the north east silo.
  
  857   Tuesday, March 10, 2015, 09:01 Travis CaveSouth Hot-CellStandard OperationTM1ThO#1Module moveTM#1 has been moved from the west station
to the south hot cell had the ThO#1 target
removed and then the modules was moved from
 TM1_THO_elec_chk_postbeamSHC.PDF 
  856   Monday, March 09, 2015, 14:01 chad fisherSouth Hot-CellStandard OperationTM1ThO#1ThO#1 removedThO#1 has been removed from TM1 and placed
into the plastic dissection box.
Containment box cover has been reinstalled
  
  855   Monday, March 09, 2015, 09:42 chad fisherSouth Hot-CellDevelopment  Hot Cell Table Swiping3 swipes of the south hot cell table were
taken from the target hall through the roof
hatch (2 standard, 1 alpha).
  
  854   Thursday, March 05, 2015, 14:30 chad fisherSouth Hot-CellDevelopment  Dissection BoxBox for dissecting targets almost complete.
Should be done tomorrow.
 20150305_142144.jpg 
  853   Thursday, March 05, 2015, 07:17 David WangITWStandard Operation  TH Shut Down Activities Schedule Feb 23th- Apr 15th updateTH shut down jobs are processing as scheduled
this week. Discussed with Don, and we think
the jobs scheduled in next week should be
 6x 
  852   Thursday, March 05, 2015, 06:44 David WangITEMaintenanceTM4 5 Shielding blocks have been moved to ITE.5 Shielding blocks have been moved to ITE
for next week TM1 move and RPG Radon test.
  
  851   Monday, March 02, 2015, 10:52 David WangITEMaintenanceTM4UCxITE primary and secondary vacuum vessels leak check.Dan and I leak checked ITE primary and
secondary vacuum vessels with TM4  in
ITE. The leak detector was hooked to ITE
  
  850   Friday, February 27, 2015, 09:34 chad fisherSouth Hot-CellMaintenance  Hot cell Entry February 25 2015See attached report.
Summary:
Radio problems just before entry
 ISAC_South_Hot_Cell_Entry.pdf 
  849   Thursday, February 26, 2015, 09:22 David WangITWStandard Operation  TH Shut Down Activities Schedule Feb 23th- Mar 25thTH shut down activities schedule from Feb
23th-March 25th. The schedule will be updated
each week. See attachment 1.
 Target_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdf 