ID Date Author Category Type Module Target/Number Subject Text Attachments
  844   Monday, February 16, 2015, 11:57 David WangCraneRepair  TH craneDave.Morris installed a new battery on
crane control PLC board and uploaded the
program. Travis, Dan and I tested the crane
  
  843   Thursday, February 12, 2015, 09:11 David WangCraneRepairTM4 TH crane troubleshoot and annual inspection.Gordon crane technicians continued their
troubleshooting on this Tuesday. They found
the crane up-limit protection switch which
  
  842   Wednesday, February 11, 2015, 13:13 chad fisherSouth Hot-CellMaintenance  New gas bottle storage rackThe new gas bottle storage rack has been
installed by/for the south hot cell.
 
 20150211_115656.jpg 
  841   Friday, February 06, 2015, 12:27 David WangCraneRepair  TH crane troubleshoot Gordon crane technician started TH crane
trouble shooting this morning. The problem
is found that there is no 115VAC power supply
  
  840   Friday, February 06, 2015, 08:06 David WangCraneRepair  TH crane lost movement controls since last Friday.Last Friday, During the crane per use check,
I found the main power supply to to crane
was shut off. I was told   Don and Travis
  
  839   Monday, February 02, 2015, 14:06 chad fisherSouth Hot-CellRepairTM2 TM2 Tray buildMaster target jig installed to locate attachment
bracket ITA3389 as well as conductor insulator
block b (aluminum / for soldering version)
 TM2_Tray_20150202_134752.jpgTM2_Tray_20150202_134759.jpg 
  838   Monday, February 02, 2015, 09:59 chad fisherSouth Hot-CellRepairTM2 TM2 Tray BuildMissing heli coils installed this morning.
Threads had to be chased with tap
for 1/4-20 heli coil and missing countersinks
  
  837   Thursday, January 29, 2015, 11:31 chad fisherSouth Hot-CellRepairTM2 TM2 Tray BuildOn Tuesday morning I attempted to complete
assembly of the source tray for TM2 however
discovered that 3 1/4-20 x 0.25 titanium
 TM2_Tray_20150126_112232.jpg 
  836   Wednesday, January 28, 2015, 10:42 Anders MjosConditioning StationMaintenanceTM2 TCS shut down for site wide power outage    
  835   Monday, January 26, 2015, 09:36 chad fisherSouth Hot-CellRepairTM2 TM2 Tray AlignmentTM2 tray alignment was confirmed with the
alignment tray this morning:
Front target 0.000 vertically, 0.000
 TM2_Tray_20150126_090448.jpg 
  834   Tuesday, January 20, 2015, 13:45 chad fisherSouth Hot-CellRepairTM2 TM2 Tray AlignmentTM2 Tray Alignment is complete except for
verification with alignment tray.
First attempt results were:
 TM2Alignment_Target_Front_Jan_20.jpgTM2_Alignment_Target_Rear_Jan_20.jpg 
  833   Monday, January 12, 2015, 14:29 chad fisherSouth Hot-CellRepairTM2 TM2 Tray Build StatusCountersink problem with supports has been
remedied. Scratches, dings, and pitting has
been buffed out and supports re-cleaned and
 TM2_Tray_20150112_01.jpg 
  832   Thursday, January 08, 2015, 15:24 Anders MjosConditioning StationDevelopmentTM2 Fault 2 on chiller unit Found both VFDs with OF3 fault (over
voltage during constant speed operation).
Thursday, January 08, 2015, 16:37:
 Capture.PNGVFD_Fault.jpg 
  831   Thursday, January 08, 2015, 10:34 chad fisherSouth Hot-CellStandard Operation  TM2 Tray Build Status and ProblemsFinal assembly of the source tray for TM2
was started this morning.
Sliding tray was received from keensert
 TM2_Tray_20150108_09.jpgTM2_Tray_20150108_10.jpgTM2_Tray_20150108_11.jpgTM2_Tray_20150108_12.jpg 
  830   Thursday, January 08, 2015, 08:04 David WangITEStandard OperationTM4 TM4 water lines have been disconnected in ITE and purged.TM4 waterlines have been disconnected and
purged in ITE. The TM4 vacuum system is still
in operation.
  
  829   Wednesday, January 07, 2015, 09:31 Anders MjosConditioning StationDevelopmentTM2 High Voltage ConditioningNo Source Tray installed. Loop on cooling
circuit D. All other circuits blanked off.
Voltages stated below are set point
  
  828   Tuesday, January 06, 2015, 11:21 Anders MjosConditioning StationDevelopmentTM2 He leak check of cooling circuits.No leak detected on either He-detector
(connected directly to Service Cap) or on
RGA. See attached screen shots.
 2015-01-06_He_leak_check_water_circuits.pdf 
  827   Tuesday, January 06, 2015, 11:14 David WangITEStandard OperationTM4 4 Shielding blocks have been moved out of ITE .4 shielding blocks have been moved out
of  ITE to block storage area. Fiona
did the survey and with me during the move.
  
  826   Monday, January 05, 2015, 15:01 Anders MjosConditioning StationDevelopmentTM2 RGA switched on    
  825   Monday, January 05, 2015, 12:47 Anders MjosConditioning StationDevelopmentTM2 Cooling package started by "enable staging" button.
MP3 has to be turned off-on to open WPV1
  