  548   Tuesday, November 19, 2013, 10:52 Travis CaveSouth Hot-CellStandard OperationTM3NiO#2module moveTM#3 with NiO#2 moved from ITE to the south
hot cell.
  
  547   Monday, November 18, 2013, 16:44 Bevan MossConditioning StationStandard Operation  Testing of cooling package I have tested all of the compressors
for TCS. All are operational and cycled as
they should. 
  
  546   Monday, November 18, 2013, 16:42 Bevan MossConditioning StationStandard OperationTM2 HV Testing The Glory of TM2 continues 100V at
a time. Today I brought the module to 46kV
and left it there for 1 hour. During this
 the_glory_of_TM2.JPG18112013_TM2_No_source_tray_HV_Test.txt 
  545   Monday, November 18, 2013, 11:54 Bevan MossConditioning StationRepairTM2 Fault on TCS Chill This morning when I went to start
HV conditioning CP2 and CP3 both had faults
and the temperature of the water was ~27C.
  
  544   Friday, November 15, 2013, 16:48 Bevan MossConditioning StationStandard OperationTM2 HV Testing High voltage testing was started
on TM2 with no source tray today. The maximum
stable for 1 minute voltage reached was 47.5kV
 TM2_conditioning_15112013.JPG15112013_TM2_No_source_tray_HV_test.txt 
  543   Thursday, November 14, 2013, 08:08 chad fisherSouth Hot-CellRepairTM2 TM2 Blank off and jig removalFirday, November 8 all water blocks (excluding
I and K) were blanked off and vacuum leak
checked. No responses were found. (First
 TM2_20131108.jpgTM2_20131112.jpg 
  542   Wednesday, November 13, 2013, 10:01 David WangConditioning StationRepairTM2 TM2 leak check at conditioning stationI leak checked TM2 at conditioning station
this morning. All air to vacuum seals  on
the top of the module are good. All water
 TM2_leak_check_at_CS_2013-11-13.pdf 
  541   Tuesday, November 12, 2013, 14:33 Bevan MossConditioning StationRepair  Cooling manifold returned The cooling manifold for the conditioning
station high power water cooled lines has
been returned. The cooling package can once
  
  540   Tuesday, November 12, 2013, 14:31 Bevan MossConditioning StationStandard OperationTM2 Turbo pumps started The turbo pumps have been started
on TM2 and the conditioning station.
  
  539   Tuesday, November 12, 2013, 12:43 Bevan MossConditioning StationStandard OperationTM2 TM2 moved from SHC to TCS TM2 was moved by myself and David
from the SHC to the TCS. Move went well.
Curiously the fields on the module were measured
  
  538   Tuesday, November 12, 2013, 10:59 Bevan MossSouth Hot-CellStandard OperationTM2 Electrical Test Don Jackson and Myself completed
started an electrical test on TM2. All lines
passed the with OL to ground. When testing
 tm2_elec_test.pdf 
  537   Tuesday, November 12, 2013, 09:51 David WangITEStandard OperationTM3 TM3 disconnectionTM3 has been disconnected this morning
and  purged all HV water lines. I found
the power plug for all turbo pump fans wasnt
  
  536   Wednesday, November 06, 2013, 10:41 David WangSouth Hot-CellRepairTM2 Installed 2 turbopumps on TM2Bevan and I installed 2 turbo pumps on
TM2. The o- ring flanges on TM2 had been
cleaned before the installation.
  
  535   Tuesday, November 05, 2013, 10:37 chad fisherSouth Hot-CellRepairTM2 Thermocouple wire removalThe old thermocouple wire has been sucessfully
removed from the module.
Thanks Bevan, Travis and David.
  
  534   Monday, November 04, 2013, 10:46 chad fisherSouth Hot-CellRepairTM2 TM2 ExplorationTM2 is now in the hot cell with the containment
box off for inspection and eventual blank
off off the water blocks.
 TM2_20131104.jpg 
  533   Friday, November 01, 2013, 09:08 Travis CaveSouth Hot-CellStandard OperationTM2no targetmodule moveTM#2 has been moved from the north west
silo to the south hot cell. The module has
a field of about 3.1mSv/hr when it was lowered
  
  532   Thursday, October 31, 2013, 11:38 Anders MjosITEStandard OperationTM3NiO#2Padlle wheel frequency measurementswith TM4 in ITW as measured today in the
electrical room by David and Anders.
 ITE-TM3-NiO#2-HP-FEBIAD_Water_Flow_EOB.pdf 
  531   Thursday, October 31, 2013, 10:36 David WangITWStandard OperationTM4 I moved 5 shielding blocks from ITE to ITW.I moved 5 shielding blocks from ITW to
ITE. The ITW  is configured to take
proton beam.
  
  530   Friday, October 25, 2013, 14:09 Travis CaveSouth Hot-CellStandard OperationTM4Ta#41Target conductance

    

       
            
 TM#4_Ta#41_elec_test_SHC.PDF 
  529   Friday, October 25, 2013, 13:39 Anders MjosITEStandard OperationTM3NiO#2Padlle wheel frequency measurementswith TM4 in ITW as measured today in the
electrical room by David and Anders.
 
 ITE-TM3-NiO#2-HP-FEBIAD_Water_Flow_wITW-TM4.pdf 