473
|
Thursday, September 26, 2013, 15:00 |
Bevan Moss | Conditioning Station | Standard Operation | TM3 | NiO#2 | RGA not connecting | Following the helium pressure test
Don attempted to connect to the RGA via the
network. He was unable to do so. This scan |
|
|
472
|
Thursday, September 26, 2013, 14:55 |
Bevan Moss | Conditioning Station | Standard Operation | TM3 | NiO#2 | HV conditioning | The first attempt at HV conditioning
of TM3 with the new source tray and NiO#2
target installed. Conditioning so far has |
|
|
471
|
Thursday, September 26, 2013, 14:47 |
Bevan Moss | Conditioning Station | Maintenance | TM3 | NiO#2 | Water pumps turned on | The water pumps for the conditioning
station were turned on at ~11:45. It took
longer to start the conditioning station |
|
|
470
|
Thursday, September 26, 2013, 14:42 |
Bevan Moss | South Hot-Cell | Repair | TM3 | NiO#2 | Activities September 24 - 25 |
|
|
|
469
|
Thursday, September 26, 2013, 14:37 |
Bevan Moss | Conditioning Station | Standard Operation | TM3 | NiO#2 | Leak check / Pressure Test |
|
|
|
468
|
Thursday, September 26, 2013, 14:31 |
Bevan Moss | South Hot-Cell | Repair | TM3 | NiO#2 | Activities September 24 - 25 | September 24
After the manipulator repair
Maico installed the NiO#2 onto the target |
|
|
467
|
Thursday, September 26, 2013, 09:46 |
maicodallavalle | Conditioning Station | Repair | TM3 | | Leak check / Pressure Test | TM3 has had all of the water lines pressurized
with Helium and the Helium Leak detector
was connected to the turbo pumps. There were |
|
|
466
|
Wednesday, September 25, 2013, 13:48 |
Travis Cave | Conditioning Station | Standard Operation | TM3 | NiO#2 | Electrical check | Electrical check of TM#3 in the conditioning
station under vacuum see attached PDF for
details. |
|
|
465
|
Wednesday, September 25, 2013, 11:08 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | NiO#2 | Electrical check | The module was checked electrically this
morning before the module move. See the attached
PDF for details. |
|
|
464
|
Wednesday, September 25, 2013, 10:00 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | NiO#2 | module move | TM#3 with NiO#2 has been moved from the
south hot cell to the conditioning station. |
|
|
463
|
Wednesday, September 25, 2013, 06:59 |
maicodallavalle | South Hot-Cell | Standard Operation | TM3 | | Containment box cover | The containment box cover has had all
the bolts installed and all bolts were checked
with a mirror. TM3 has been raised and is |
|
|
462
|
Tuesday, September 24, 2013, 14:46 |
Bevan Moss | South Hot-Cell | Repair | | | Right manipulator repair | |
|
|
461
|
Tuesday, September 24, 2013, 08:15 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | Electrical check | Electrical check was done on TM#3 yesterday
and again the coil lines to the 60kV common
and the coil line to each other failed, as |
|
|
460
|
Monday, September 23, 2013, 16:10 |
Bevan Moss | South Hot-Cell | Repair | TM3 | | Activities Sept 20 - 23 2013 | September 20th
Today was a trying day. When attempting
to make the water line connections for the |
|
|
459
|
Monday, September 23, 2013, 13:55 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | window circuit leak check | This morning, Bevan and I leak checked
window circuit on TM3 at SHC after containment
box was installed. It took about 20minutes |
|
|
458
|
Thursday, September 19, 2013, 15:56 |
Bevan Moss | South Hot-Cell | Repair | TM3 | | Activities for September 18th and 19th | September 18th
The wiring harness was completed
by Maico and Travis today (see pics) and |
|
|
457
|
Thursday, September 19, 2013, 11:09 |
Travis Cave | South Hot-Cell | Maintenance | TM3 | no target | Electrical check | Electrical check of TM#3 with no target
was performed and it failed. |
|
|
456
|
Thursday, September 19, 2013, 09:08 |
Travis Cave | South Hot-Cell | Standard Operation | TM3 | no target | wiring harness | The wiring harness for TM#3 was made and
a continuity and megger test was done on
it and it passed, it has since been installed |
|
|
455
|
Tuesday, September 17, 2013, 14:36 |
Bevan Moss | South Hot-Cell | Standard Operation | TM3 | | Containment Box has been removed | The containment box has been removed.
Tomorrow the wiring harness will be installed. |
|
|
454
|
Friday, September 13, 2013, 08:05 |
David Wang | South Hot-Cell | Repair | TM4 | | TM4 coil 1 leak check in SHC | Leak checked TM4 coil1 in SHC with Isaac
. The leak detector only can pump down to
1.5xE-7 atm.cc/sec. The leak detector got |
|