393
|
Wednesday, July 03, 2013, 08:43 |
chad fisher | South Hot-Cell | Standard Operation | | | Ta#39 Transfered to spent target storage vault | |
|
|
392
|
Tuesday, July 02, 2013, 10:58 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | UC#6 | module move | TM#1 with UC#6 has been moved from the
conditioning station to the west target station,
move went well. |
|
|
391
|
Tuesday, July 02, 2013, 09:37 |
chad fisher | South Hot-Cell | Development | TM3 | | TM3 Rev.2 Source Tray Disposal | Tm3 Rev.2 source tary has been transfered
to the vault tunnel storage. |
|
|
390
|
Thursday, June 27, 2013, 14:27 |
chad fisher | South Hot-Cell | Development | | | Polishing Cleaning tool - Water blocks | The polishing/cleaning tool prototype is
now finished and appers to work great.
Thanks to Dan and Maico for the great |
|
|
389
|
Thursday, June 27, 2013, 14:23 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Ta#39 | Ta#39 Autopsy performed | An autopsy of Ta#39 was performed yesterday
and today. Ta#39 will be sent to the spent
target storage vault on Tuesday. |
|
|
388
|
Thursday, June 27, 2013, 14:21 |
chad fisher | South Hot-Cell | Standard Operation | TM1 | Ucx#6 | Ucx#6 installed Ta#39? rewmoved | Ucx#6 was installed on TM1 on Wednesday.
Ta#39 was removed. |
|
|
387
|
Wednesday, June 26, 2013, 11:03 |
David Wang | South Hot-Cell | Standard Operation | TM1 | | Leak check on TM1 UCx target heat shield | Chad and I leak checked the TM1 UCx target
heat shield at SHC. No leak has been found
so far. |
|
|
386
|
Tuesday, June 25, 2013, 14:56 |
Bevan Moss | Conditioning Station | Standard Operation | TM1 | UCx#6 | Roughing Pumps Started | The roughing pumps have been started
on the conditioning station. As it is late
in the day for David he will make the turbo |
|
|
385
|
Tuesday, June 25, 2013, 14:24 |
Travis Cave | Conditioning Station | Standard Operation | TM1 | UC#6 | module move | Module moves of TM#1 with Ta#39 from ITW
to SHC then TM#1 with UCx#6 from SHC to the
conditioning station moves went well. |
|
|
384
|
Tuesday, June 25, 2013, 13:20 |
Travis Cave | South Hot-Cell | Standard Operation | TM1 | UC#6 | Electrical check | Results from the electrical check of TM#1
with the UC#6 target. See attached PDF. |
|
|
383
|
Friday, June 21, 2013, 09:26 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock-up Leak Check Results | The Mock-up has been leak tested after
the remote connection of the water blocks
and is leak tight! |
|
|
382
|
Thursday, June 20, 2013, 13:47 |
Travis Cave | Spent Target Vault | Standard Operation | | | Spent Target Assay | Ten targets have been assayed or had field
measurements(they were too hot to ship but
were assayed the last time an assay was done) |
|
|
381
|
Wednesday, June 19, 2013, 08:15 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock up water block connections | All water block connections on the mock-up
have bben achieved. It is now ready for leak
checking. |
|
|
380
|
Tuesday, June 18, 2013, 14:00 |
chad fisher | South Hot-Cell | Development | TM3 | | Mock-up testing / water block connections | The testing of the mock-up and tooling
has commenced.
Source tray mock-up has been driven |
|
|
379
|
Thursday, June 13, 2013, 09:21 |
chad fisher | South Hot-Cell | Development | | | Warm Cell Mock-up | the warm cell mock-up has been inserted
into the warm cell and final preparation
for the remote test are being made. |
|
|
378
|
Thursday, June 13, 2013, 09:18 |
chad fisher | South Hot-Cell | Repair | TM3 | | Source Tray/Extraction Column Removal | TM3 Rev 2 source tray/extraction column
insertion into its storage was completed
yesterday and it was then removed from the |
|
|
377
|
Wednesday, June 12, 2013, 10:39 |
Travis Cave | South Hot-Cell | Standard Operation | | | spent source tray removal | The spent source tray for TM#3 has been
removed from the south hot cell and well
be placed in the the hot cell ante room. |
|
|
376
|
Tuesday, June 11, 2013, 10:05 |
David Wang | ITW | Standard Operation | TM1 | | Disconnected TM1 in ITW. | Dan and I disconnected TM1 in ITW. |
|
|
375
|
Tuesday, June 04, 2013, 15:34 |
Bevan Moss | Conditioning Station | Repair | | | Relay replaced | ESC was called out again to inspect the
chiller as it was showing the same problem
as before. This time when started one fan |
|
|
374
|
Tuesday, June 04, 2013, 12:36 |
David Wang | ITE | Standard Operation | TM4 | | 5 shielding blocks are transferred from ITW to ITE | Dan an I transferred 5 shielding
blocks from ITW to ITE. The ITE is configured
to take proton beam. |
|