2533
|
Friday, January 26, 2024, 08:30 |
David Wang | South Hot-Cell | Standard Operation | TM4 | | window line VCR leak check after containment box removal/installation. | Chad and I did window line VCRs leak check
after containment box removal/installation.
The first pair of VCRs have leak. |
|
|
2532
|
Thursday, January 25, 2024, 07:31 |
David Wang | Crane | Standard Operation | | | Inspection oftareg hall crane below hook attachment pins and plates ITA6550-01 | Tom Kauss inspected target hall crane below
hook attachment pins and plates ITA6550-01
yesterday. He certified the use of these |
|
|
2531
|
Thursday, January 25, 2024, 07:27 |
David Wang | Crane | Standard Operation | | | Inspection of target module lifting frames ITA0494-1997-01 and ITA0494-1997-02 | Tom Gauss inspected two target module
lifting frames ITA0494-1997-01 and ITA0494-1997-02
yesterday. He certified the use of these |
|
|
2530
|
Thursday, January 25, 2024, 07:24 |
David Wang | Crane | Standard Operation | | | targe hall annual crane inspection | Tom Kauss finished TH crane annual inspection
yesterday. The crane woks fine. Tom has
this inspection record in his file. The crane |
|
|
2529
|
Wednesday, January 24, 2024, 08:34 |
chad fisher | South Hot-Cell | Repair | TM4 | UCx#43 | Plating and coating from UCx#43 failure | TM4 has seen significant coating of the
main standoff insulators and various other
components stemming from failure in UCx#43 |
|
|
2528
|
Monday, January 22, 2024, 14:12 |
Frank Song | ITE | Standard Operation | TM4 | UCx#43 | module disconnection | TM4 with spent target UCx#43 was
disconnected in ITE and is ready moved to
SHC. see attachment pls. |
|
|
2527
|
Monday, January 22, 2024, 10:16 |
David Wang | ITE | Standard Operation | TM4 | UCx# | Tm4 waterlines helium pressure test and TM service cap helium leak check. | Tm4 waterlines helium pressure test and
TM service cap helium leak check was done
last Friday. All water lines were pressurized |
|
|
2526
|
Monday, January 22, 2024, 09:56 |
David Wang | ITW | Standard Operation | | | Entrance module has been connected in ITW pit. | Entrance module has been connected in ITW
pit per document 190510 " entrance module
disconnection and removal procedure". |
|
|
2525
|
Monday, January 22, 2024, 09:50 |
David Wang | ITW | Standard Operation | | | ITW entrance module has been moved from SHC to ITW. | ITW entrance module has been moved from
SHC to ITW. A slightly bump on module shielding
block bottom side corner to tank vessel side |
|
|
2524
|
Wednesday, January 17, 2024, 20:09 |
Carla Babcock | South Hot-Cell | Standard Operation | | Ta#66 | Ta#66 post irradiation inspection | On Jan. 9 we did the PIE on Ta#66. Opened
the heat shield and removed the EE. The inside
of the heat shield was very black with lots |
|
|
2523
|
Friday, January 12, 2024, 11:25 |
David Wang | South Hot-Cell | Standard Operation | TM2 | Ta#66 | Ta#66 post operation electrical check at SHC | Ta#66 post operation electrical check was
done at SHC this Monday. See attachment.
|
|
|
2522
|
Friday, January 12, 2024, 10:53 |
David Wang | South Hot-Cell | Standard Operation | | | ITW entrance module has been moved from ITW to SHC. | ITW entrance module has been moved from
ITW to SHC. The move is smooth. I cleaned
entrance module tank flange and o r-ing slot. |
|
|
2521
|
Thursday, January 11, 2024, 13:57 |
David Wang | ITW | Standard Operation | | | ITW entrance module has been disconnect. | ITW entrance module has been disconnected
per document190510. It will be moved to SHC
for diagnostic group tomorrow. |
|
|
2520
|
Thursday, January 11, 2024, 13:54 |
David Wang | Conditioning Station | Development | TM3 | | TM3 servic cap air to vacumm seals leak check. | After Tm3 service tray and service cap
installation, TM3 service cap air to vacuum
seals leak check has been done at TCS. TCS:IG1 |
|
|
2519
|
Wednesday, January 10, 2024, 16:51 |
Carla Babcock | ITE | Standard Operation | TM4 | UCx#43 | UCx#43 failure | To deliver stable beam to RadMol,
started heating UCx#43 up again. Target was
overheated during initial conditioning in |
|
|
2518
|
Wednesday, January 10, 2024, 11:24 |
Travis Cave | Spent Target Vault | Standard Operation | | Ta#66 | Spent Target Move | The spent Ta#66 was moved from the
south hot cell to the spent target vault,
it was placed in pail#285 and placed in spot |
|
|
2517
|
Tuesday, January 09, 2024, 16:10 |
Adam Newsome | South Hot-Cell | Standard Operation | TM2 | | TM2 Move - SHC to Silo | TM2 was moved with no target attached from
the South Hot Cell to a silo. |
|
|
2516
|
Monday, January 08, 2024, 14:47 |
Adam Newsome | South Hot-Cell | Standard Operation | TM2 | | TM2 Move - ITW to SHC | TM2 was moved from ITW to the South Hot
Cell with Ta#66 target. |
|
|
2515
|
Wednesday, January 03, 2024, 14:03 |
David Wang | ITW | Standard Operation | TM2 | Ta#66 | ITW primary and secondary vacuum vessel leak check and TM2 water lines helium pressure test. | ITW primary and secondary vacuum vessel
leak check and TM2 water lines helium pressure
test are done today. No major concern. see |
|
|
2514
|
Wednesday, January 03, 2024, 13:55 |
David Wang | ITW | Standard Operation | TM2 | Ta#66 | Disconnect TM2 in ITW. | TM2 has been disconnected in ITW. All water
lines are nitrogen purged. Filled 60 psi
argon to all Tm2 water lines for module storage |
|