ID Date Author Category Type Module Target/Number Subject Text Attachments
  2415   Monday, January 30, 2023, 11:30 Travis CaveSpent Target VaultStandard Operation UC#41Spent Target Move The spent UC#41 was moved from the
south hot cell to the spent target vault,
placed in spot 1C, in pail #231. See attached
 Target_Index_2023-01-30.pdf 
  2414   Friday, January 27, 2023, 07:25 David WangCraneStandard Operation  Inspection of TH crane below hook attachment pins and plates ITA6550-01Tom Kauss inspected target hall crane below
hook attachment pins and  plates ITA6550-01
yesterday. He certified the use of these
  
  2413   Friday, January 27, 2023, 07:18 David WangCraneStandard Operation  Inspection of target module lifing frame ITA0494-1997-01 and ITA0494-1997-02Tom Gauss inspected  two target module
lifting frames ITA0494-1997-01  and ITA0494-1997-02
yesterday. He certified the use of these
  
  2412   Friday, January 27, 2023, 07:15 David WangCraneStandard Operation  Target hall Crane annual inspection has beend done.Tom Kauss  finished TH crane annual
inspection yesterday. The crane woks fine.
Tom has this inspection record in his file.
  
  2411   Friday, January 27, 2023, 07:11 David WangCraneStandard Operation  Target hall Crane annual inspection has beend done.Tom Kauss inspected target hall crane yesterday.
The crane works fine. Tom has this inspection
record in his file. The inspection tag has
  
  2410   Wednesday, January 25, 2023, 06:52 David WangITEStandard OperationTM4UCx#41ITE primary and secondary vacuum vessel air to vacuum seals leak check. ITE primary and secondary vacuum vessel
air to vacuum seals leak check was done this
week. One leak has been found on IG1S feed
 ITE_vacuum_vessel_leak_check_2023..pdf 
  2409   Tuesday, January 24, 2023, 14:22 David WangSouth Hot-CellStandard OperationTM4UCx#41TM4 electrical check with and without target at SHCTM4 electrical check with UCX41target and
without target at SHC.  The results
are good. See attachment.
 TM4_electrical_check_with_UCX41_and_without_target_2023_Jan.pdf 
  2408   Tuesday, January 24, 2023, 08:46 David WangITEStandard OperationTM4UCx#41TM4 has been disconnected in ITE. TM 4 has been disconnected in ITE. 
See attachment for disconnection checklist.
 UCx#41_TM4_disconnection_checklist_in_ITE.pdf 
  2407   Tuesday, January 24, 2023, 07:26 David WangConditioning StationStandard Operation  TH floor moping and garbage collelctions.Plant group and us  finished TH floor
mopping and garbage collections last Wednesday.
Th moping head had 800 count after using.
  
  2406   Tuesday, January 24, 2023, 07:21 David WangITWMaintenance  ITW pit general clean up.  ITW  was cleaned with vacuum
canister in Jan 10th. HV  cage inside
and blue  nylon insulators were wiped. 
  
  2405   Tuesday, January 24, 2023, 07:17 David WangITEStandard OperationTM4UCx#41TM4 water lines helium pressure test 2023. TM4 water lines helium pressure test was
done yesterday at ITE. All water lines were
air purged one day ahead  for the test.
 TM4_water_lines_helium_presuure_test_2023.pdf 
  2404   Wednesday, January 11, 2023, 11:34 Travis CaveSpent Target VaultStandard Operation UC#40Spent Target Move UC#40 was moved from the north hot
cell to the spent target vault. It was placed
in pail #278 put in spot 1B and was 15.6
 Target_Index_2023-01-11.pdf 
  2403   Tuesday, January 10, 2023, 10:15 Frank SongSafe Module ParkingStandard OperationTM2UCx40 removedTM2 electrical check with no target attached on SW silo TM2 with no target on SW silo be
electrical checked right after module moving.
 TM2_electrical_check_without_UCx40_on_SW_silo.png 
  2402   Monday, January 09, 2023, 14:19 Frank SongITWStandard OperationTM2UCx#40TM2 with UCx40 disconnection in ITW TM2 with target UCx40 was disconnected
in ITW and moved to NHC.
 TM2_with_UCx40_disconnection_in_ITW.png 
  2401   Friday, January 06, 2023, 10:38 David WangITWStandard OperationTM2 ITW/TM2 vacuum vessels leak check and TM2 internal cooling lines helium pressure test. ITW
 and TM2 primary and secondary vacuum
 ITW_vacuum_leak_check_2023.pdf 
  2400   Friday, January 06, 2023, 09:41 Adam NewsomeSpent Target VaultStandard Operation  Pails moved to mini-storage vaultThe following three pails were moved from
the main storage vault to the mini-storage
vault:
 Target_Index_2023-01-06.pdf 
  2399   Friday, December 16, 2022, 16:39 Adam NewsomeCraneStandard Operation  Crane powered off for holidays[edit 2023-01-03] The crane was powered
back on this morning - there do  not appear
to be any faults and it seems that the crane
  
  2398   Friday, December 16, 2022, 16:35 Adam NewsomeSpent Target VaultStandard Operation  Pails measured, moved to mini-storage vaultThe following five pails were moved to
the mini-storage vault today under work permit
I2022-12-16-1:
 Target_Index_2022-12-16.pdf 
  2397   Thursday, December 01, 2022, 13:45 Carla BabcockNorth Hot-CellStandard OperationTM4C#4Post irradiation inspection C#4Post irradiation inspection of C#4 which
was running in TM4/ITE was conducted at the
NHC on Nov. 22 2022.
 20221122_152435.jpg20221122_153033.jpg20221122_152407.jpg 
  2396   Thursday, December 01, 2022, 08:20 Frank SongITEStandard OperationTM4UCx#41Module Connection TM4 with UCx#41 was connected in
ITE on Tuesday (2022-11-29) 
 TM4_with_UCx#41_connection_in_ITE.png 