Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-ISAC  Not logged in ELOG logo
Message ID: 2401     Entry time: Friday, January 06, 2023, 10:38
Author: David Wang 
Category: ITW 
Type: Standard Operation 
Module: TM2 
Target/Number:  
Subject: ITW/TM2 vacuum vessels leak check and TM2 internal cooling lines helium pressure test.  

ITW and TM2 primary and secondary vacuum vessel leak check is done. Leak detector is connected to ITW TP1. Base leak rate on leak detector is 0.0 x E-9 atm.cc/sec.   See attachment for the result.  No big issue. Two old leaks we found last year at location D and E disappeared in this check. We did Vacseal resin spray on them last year.  It looks like the Vacseal spray works .  From the result , I can see the o-ring between exit 1 module and T - flange is closing to the end of the life.  There are two small leaks on this o-ring now at A and B location. We plan to change this o-ring next winter shut down. We do vacseal spray on them this year. The big O-ring between tank vessel and T -flange looks still ok. Two small leaks are found on location F and G on this O-ring. Not much we can do on them. The leak on location C and B were sprayed with resin yesterday after leak check. They are leak free after spray on check. I will double check them. Leak on location A will be resin sprayed after TM2 is removed and ITW is under vacuum.   All TM2 internal water-cooling lines are helium pressurized (70 psi) for 5 minutes each. HS shows 2.5 X E-9atm.cc/sec leak rate. The rest lines are 0.0 X E-9 atm.cc/sec.

Attachment 1: ITW_vacuum_leak_check_2023.pdf  40 kB  | Show | Hide all
ELOG V2.9.2-2455