ID |
Date |
Author |
Category |
Type |
Module |
Target/Number |
Subject |
Text |
|
2215
|
Monday, May 03, 2021, 15:14 |
Frank Song | ITE | Maintenance | | | High voltage test in ITE | Anders and I prepared ITE high voltage
test in April 30 ( Friday morning), The MAA
is locked for this. |
|
2214
|
Friday, April 30, 2021, 14:09 |
Luca Egoriti | ITE/ITW | Development | TM4 | | TM4 resistance measurements for P2N | Friday, April 30, 2021, 14:06
Anders and Luca
Resistance measurements on each electrical |
|
2213
|
Monday, April 26, 2021, 13:02 |
David Wang | South Hot-Cell | Repair | TM4 | | TM4 new steerer cable installation. | New steerer cables are installed in TM4.
Cables are properly routed in containment
box and service cap top. After job, TP2 is |
|
2212
|
Thursday, April 22, 2021, 08:41 |
David Wang | South Hot-Cell | Repair | TM4 | | TM4 steerer electical check at SHC and TH. | Using SHC electrical test cables routed
to to TH, We tested TM4 steerer
4 polarities. At 100v megga test, left, right |
|
2211
|
Wednesday, April 21, 2021, 11:18 |
David Wang | Cooling | Maintenance | | | Refilling high active wtaer system and starting HA water pumps. | High active water system is refilled. Air
are drained out of system before pump
to be started. Following sequence are used |
|
2210
|
Wednesday, April 21, 2021, 10:34 |
David Wang | South Hot-Cell | Standard Operation | TM4 | | Remtely remove TM4 from Silo to SHC. | On 2021- 04-20, Tm4 is removed from
Silo to SHC. The moving is smooth. |
|
2209
|
Wednesday, April 21, 2021, 10:32 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | Remotely remove TM3 from SHC to silo | On 2021-04-19, Frank and I remotely removed
Tm3 from SHC to silo . The moving is successful.
|
|
2208
|
Monday, April 12, 2021, 13:47 |
Anders Mjos | Assembly/Bench Test | Repair | TM4 | | Steerer wiring | Travis assembled and tested the steerer
wires March 31st (see attached) |
|
2207
|
Monday, April 12, 2021, 13:45 |
Anders Mjos | Cooling | Maintenance | | | New T installed for instrumentation loop on HALCW system | Adrian and co installed a new T to be able
to add an instrument loop for O2 and pH monitoring
on the low conductivity water systtem (photo). |
|
2206
|
Friday, March 26, 2021, 12:22 |
Adam Newsome | Crane | Development | | | Aux Hoist Pendant Upgrade | The crane pendant for the auxiliary hoist
was upgraded to a FLEX EX2 style pendant
by Canco Cranes. The installation work was |
|
2205
|
Thursday, March 25, 2021, 10:38 |
David Wang | Spent Target Vault | Standard Operation | | C#1 | Remove pail 237 spent target C#1 from storage vault to mini storage. | Pail 237 only has 200u sv/hr field at 0.5
meter. On contact measurement: 0.9 to 1.6
m sv/hr.and less than 80 count contamination |
|
2204
|
Thursday, March 25, 2021, 08:55 |
Anders Mjos | Conditioning Station | Maintenance | | | Filters inspected and cleaned on water circuit | By Curtis. See Work Permit I2021-03-24-1
for details. |
|
2203
|
Tuesday, March 23, 2021, 09:47 |
David Wang | South Hot-Cell | Standard Operation | TM3 | | TM3 has been moved from TCS to SHC. | Frank and I removed Tm3 from TCS to SHC.
The move is successful. |
|
2202
|
Wednesday, March 17, 2021, 11:43 |
Frank Song | ITE | Repair | | | Re-connect Entrance Module in ITE | David and I re-connect Entrance module
at ITE after the monitor been replaced at
SHC. |
|
2201
|
Wednesday, March 17, 2021, 09:10 |
Travis Cave | ITE | Standard Operation | | | Entrance module move | The east entrance module is now back
at the east target station. |
|
2200
|
Monday, March 15, 2021, 13:01 |
Isaac Earle | Crane | Development | | | Plate & pin lift assembly load testing (ITA6550) | In mid-2020 design analysis was completed
on the steel plate & pin assemblies (ITA6550)
used to connect the ISAC target hall crane |
11x |
2199
|
Friday, March 12, 2021, 11:36 |
Travis Cave | South Hot-Cell | Maintenance | | East Entrance Module | Entrance module move | The East Entrance Module has been
moved from the East Target Station to the
South Hot Cell. |
|
2198
|
Thursday, March 11, 2021, 11:42 |
Frank Song | ITE | Maintenance | | | ITE water flow wheels and coils replacement. | ITE water flow wheels
and coils are replaced. Wheels and coils |
|
2197
|
Friday, March 05, 2021, 09:12 |
Matthew Gareau | North Hot-Cell | Development | TM3 | | Containment box door removal and swivel arm test | First thing I entered into the NHC to install
to the target kart mounting clip, and remove
excess tools and materials from the hotcell |
|
2196
|
Thursday, March 04, 2021, 16:30 |
Isaac Earle | North Hot-Cell | Development | | | NHC gas delivery lines leak checked | The North Hot Cell gas delivery lines
(labeled 1, 2, and 3 on the hot and cold
side panels) were leak checked today. |
|