  RH-ISAC, Page 29 of 138  Not logged in ELOG logo
ID Date Author Category Type Module Target/Number Subject Text Attachments
  2188   Tuesday, February 16, 2021, 14:00 Adam NewsomeCraneDevelopment  Crane pendant upgradeThe crane pendant for the main hoist was
upgraded to a FLEX EX2 style pendant by Canco
Cranes. The installation work was performed
 PXL_20210216_183711834.jpg 
  2187   Friday, February 12, 2021, 07:07 David WangITEMaintenance  ITW and ITE clean up.Vacuum cleaned ITW and ITE station. 
  
  2186   Wednesday, February 10, 2021, 13:30 David WangSafe Module ParkingStandard Operation  TM2 and TM4 electrical check without targets. TM2 at SMP under vacuum. TM4 at silo. 
Frank and I did the tests. Everything is
fine on TM4 check.  On TM2,  all
 TM2_and_TM4_electrical_check_without_target.pdf 
  2185   Wednesday, February 10, 2021, 11:34 David WangAssembly/Bench TestStandard Operation  Old resin can and 2A window RH clamp field measurement at silo. Old resin can:  0.5 meter 360 degree
rotation above silo area, 350u sv/hr.  
On contact  3.0 to 3.5 msv/hr. 
  
  2184   Wednesday, February 03, 2021, 09:14 David WangConditioning StationStandard OperationTM4 TM4 from TCS to SW silo.TM4 is moved from TCS to SW silo. The moving
is smooth.
 
  
  2183   Wednesday, January 27, 2021, 14:30 David WangCoolingDevelopment  High active water system purgingHigh active water are purged to holding
tank at B2  level. There should be around
48 gallons are purged out of system. No purging
  
  2182   Monday, January 25, 2021, 12:33 David WangITWStandard Operation  ITW bias HV testRamp up ITW bias to 57KV. no spark. 200uA
leaking current at 57KV. The test is done
without target module in station.  
  
  2181   Monday, January 25, 2021, 10:57 David WangSouth Hot-CellRepairTM4 TM4 steers short investigation.Cables were disconnected for steers in
containment box. The Megga measurement (500V)
result from the top of the module: 
  
  2180   Friday, January 22, 2021, 12:34 David WangITEStandard Operation  ITE HV test.ITE annual HV test is done. No module in
station. The bias power supply has been ramped
up to 49KV on control page. We still have
  
  2179   Tuesday, January 19, 2021, 11:32 Travis CaveSafe Module ParkingStandard OperationTM2Nb#9Module move TM#2 with Nb#9 was moved from ITW
to SHC and then with no target it was moved
from the SHC to the SMP.
  
  2178   Monday, January 18, 2021, 12:29 David WangITWStandard OperationTM2Nb#9ITW vacuum and TM2 water lines leak check .ITW primary and secondary vacuum vessel
leak check are done. There is a 5XE-8 atm.cc/sec
leak on Exit service cap NW side square panel. 
  
  2177   Friday, January 08, 2021, 09:40 Travis CaveSouth Hot-CellStandard OperationTM4Ta#61Module move TM#4 with Ta#61 has been moved from
the east target station to the south hot
cell.
  
  2176   Wednesday, January 06, 2021, 10:39 David WangITEStandard OperationTM4 ITE and TM4 annual leak check.Frank and I finished ITE and TM4 primary
and secondary  vacuum vessel  leak
check. LD bease leak rate 0.0x-9atm.cc/sec. No leak has been found.Also, All TM4 water lines  have been pressurized with 70psi helium fro 3 minutes on each circuit. All water lines i
  
  2175   Monday, January 04, 2021, 12:13 Adam NewsomeConditioning StationDevelopmentTM3 TM3 MoveTM3 was remotely moved from the
South Hot Cell to the conditioning station.
No containment box.
  
  2174   Thursday, December 24, 2020, 09:00 Matthew GareauNorth Hot-CellDevelopment   NHC USB connection    
  2173   Monday, December 21, 2020, 11:22 Adam NewsomeCraneStandard Operation  Crane Shutdown for Power OutageThe Target Hall Crane has been shut down
in preparation for the power outage tomorrow
(Dec 22). Power will be restored on Dec 23.
  
  2172   Thursday, December 10, 2020, 15:07 Adam NewsomeSouth Hot-CellDevelopmentTM3 TM3 MoveTM3 was remotely moved from the conditioning
station to the South Hot Cell. No containment
box.
  
  2171   Monday, December 07, 2020, 12:20 Adam NewsomeConditioning StationDevelopmentTM3 TM3 MoveTM3 has been moved from
the South Hot Cell to the
Conditioning Station. No containment box.
  
  2170   Wednesday, November 25, 2020, 09:05 Adam NewsomeSouth Hot-CellStandard OperationTM3 Module MoveTM3 has been moved from
the Silo to the South Hot Cell.
  
  2169   Tuesday, November 24, 2020, 12:56 David WangITWStandard OperationTM2Nb#9TM2 has been connected in ITWTM2 has been connected to ITW. Turbo pumps
are stared. ITW pumping down is fine so far.
 TM2_Nb#9_module_connection_checklist.pdf 