1421
|
Tuesday, January 17, 2017, 13:45 |
Isaac Earle | North Hot-Cell | Development | | | NHC ducting installed | The new ducting section connecting
the existing duct termination in the TCS
space to the NHC partition wall has been |
|
|
1420
|
Monday, January 16, 2017, 09:32 |
David Wang | ITW | Standard Operation | TM2 | | Helium pressure test on TM2 water llines at ITW | TM2 helium pressure test result at ITW.
70 psi helium 3 minutes on each circuit.
LD base LR0.0XE-9atm.cc/sec BP 0.0XE-4torr. |
|
|
1419
|
Thursday, January 12, 2017, 14:24 |
David Wang | ITW | Standard Operation | TM2 | | ITW primary and secondary vacuum vessel winter shut down leak check. | TM2 is located in ITW for this leak check.
Leak detector is installed between ITW BV2s
as before. LD base leak rate 0.0XE-9atm.cc/sec, |
|
|
1418
|
Wednesday, January 04, 2017, 14:27 |
David Wang | Conditioning Station | Standard Operation | | | started TCS vacuum pump | TCS TP1S has been started.
2017-01-23 afternoon: Stopped TP1S.
We will use TCS to take TM2 tomorrow afternoon. |
|
|
1417
|
Friday, December 09, 2016, 18:05 |
Aurelia Laxdal | Conditioning Station | Repair | TM3 | | TM3 vacuum system have been connected at TCS. |
|
|
|
1416
|
Friday, December 09, 2016, 14:58 |
Isaac Earle | North Hot-Cell | Development | | | NHC service area floor and top of roof block painted | The concrete floor in the North Hot
Cell service area and the top of the NHC
roof block in the target hall have been painted |
|
|
1415
|
Monday, December 05, 2016, 10:10 |
David Wang | ITW | Standard Operation | TM2 | | Five shielding blocks have been transferred from ITE to ITW. | The ITW is configured to take proton beam. |
|
|
1414
|
Monday, December 05, 2016, 10:04 |
Aurelia Laxdal | Conditioning Station | Repair | TM3 | | TM3 vacuum system have been connected at TCS. |
|
|
|
1413
|
Saturday, December 03, 2016, 10:01 |
David Wang | ITW | Repair | TM2 | | venting ITW and TM2 with argon. | A short between TM2 EE and bias is produced
yesterday during tube heater ramp up.
Alex asked for an argon venting on ITW to |
|
|
1412
|
Wednesday, November 30, 2016, 16:31 |
David Wang | Conditioning Station | Repair | TM3 | | TM3 vacuum system have been connected at TCS. | All water circuits are by passed on the
top of TM3. Water pumps and vacuum turbo-
pumps are started. Everything is ready for |
|
|
1411
|
Tuesday, November 29, 2016, 14:50 |
Travis Cave | ITW | Standard Operation | TM2 | UC#18 | module moved | TM#2 with UC#18 has been moved to ITW from
the conditioning station. |
|
|
1410
|
Tuesday, November 29, 2016, 12:57 |
David Wang | ITW | Standard Operation | TM2 | | TM2 is connected in ITW | All turbo pumps are started. Water system
and water signals have been checked. Pumping
down on ITW and TM2 is good so far. |
|
|
1409
|
Tuesday, November 29, 2016, 07:50 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 is disconnected at TCS. | Argon venting is done. |
|
|
1408
|
Tuesday, November 29, 2016, 06:27 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TCS water pumps are stopped | Argon venting on TCS and TM2 is processing |
|
|
1407
|
Friday, November 25, 2016, 09:04 |
Travis Cave | Spent Target Vault | Standard Operation | | SiC#35 | Spent Target move | On November 24th 2016 the spent SiC#35
was moved from the south hot cell to the
spent target vault. see attached pdf for |
|
|
1406
|
Thursday, November 24, 2016, 10:30 |
David Wang | Conditioning Station | Standard Operation | TM2 | | HV cover is installed on TM2 at TCS | Interlock key are returned back to
B2 level.TM2 is ready for HV conditioning
and heating up at TCS. |
|
|
1405
|
Thursday, November 24, 2016, 09:33 |
Anders Mjos | Conditioning Station | Standard Operation | TM2 | UC#18 | Conditioning UC#18 | Thursday, November 24, 2016, 09:33: Water
package on
Thursday, November 24, 2016, 09:43: |
|
|
1404
|
Wednesday, November 23, 2016, 16:21 |
David Wang | Conditioning Station | Standard Operation | TM2 | | TM2 and TCS vacuum system has been connected. | All vacuum pumps have been started. Air
ballast 50seconds on roughing pump. Everything
is good so far. |
|
|
1403
|
Wednesday, November 23, 2016, 16:10 |
David Wang | South Hot-Cell | Standard Operation | TM2 | | SHC, TM2 leak check on HS line. | Chad and I leak checked TM2 HS line with
new UCx target installed. Helium spray
2 seconds on each joint and 10seconds flushing |
|
|
1402
|
Wednesday, November 23, 2016, 14:25 |
Travis Cave | South Hot-Cell | Standard Operation | TM2 | UC#18 | Electrical Check | Results of TM#2 with UC#18 electrical at
the south hot cell. See attached PDF for
details. |
|