137
|
Friday, February 04, 2022, 11:52 |
Adam Newsome | Cyclotron | Standard Operation | Lid up operation - 2022 | The lid up operation
took place on Feb. 4, 2022. |
|
138
|
Tuesday, February 08, 2022, 11:39 |
Adam Newsome | Cyclotron | Development | Radiation Survey - sampling rate error | When attempting to perform the radiation
survey, the program displayed an error at
startup stating that the software was not |
|
139
|
Monday, March 21, 2022, 13:14 |
Adam Newsome | Trolley | Repair | Video Trolley Mk 1 - Radial Limit Switch Replacement | An issue was observed in which radial motion
on the Video Trolley Mk 1 did not respond
to commands. After troubleshooting, it was |
|
140
|
Wednesday, April 27, 2022, 16:05 |
Adam Newsome | Cyclotron | Standard Operation | Lid down operation - 2022 | The lid down operation
took place on Apr. 27, 2022. |
|
141
|
Wednesday, May 04, 2022, 12:07 |
Adam Newsome | Trolley | Development | Tool Trolley: Brass air fittings replacement complete | All of the old brass air fittings on the
Tool Trolley have now been swapped over to
push-connect style fittings. As these are |
|
145
|
Wednesday, June 29, 2022, 12:12 |
Adam Newsome | Probe | Development | LE1/LE2 Probe Frame - Updates | The LE1/LE2 Probe Frame was mounted on
the Upper Resonator Trolley in the mockup
with the intention of confirming functionality |
|
146
|
Thursday, October 06, 2022, 17:15 |
Adam Newsome | Elevation Jack | Maintenance | Preventative Maintenance: MCC-E elevating system motor contactors | Under work permit C2022-10-04-1,
the motor contactors for jack motors 1 through
12 were replaced. The contactors showed signs |
|
147
|
Friday, January 27, 2023, 12:12 |
Adam Newsome | Infrastructure | Development | Vault crane - inspection, remote pendant installation | The vault crane annual inspection was completed
by Tom Kauss.
|
|
148
|
Monday, January 30, 2023, 12:20 |
Adam Newsome | Cyclotron | Standard Operation | Lid up operation - 2023 | The lid up operation
took place on Jan. 30, 2023. |
|
152
|
Friday, March 31, 2023, 13:22 |
Adam Newsome | Cyclotron | Standard Operation | Lid down operation - 2023 | The lid down operation
took place on Mar. 31, 2023. |
|
153
|
Wednesday, April 26, 2023, 11:19 |
Adam Newsome | Cyclotron | Standard Operation | Vault Shield Door Closed | The vault shield door has been closed and
seal inflated. The operation was performed
with no issue. |
|
154
|
Friday, July 28, 2023, 12:05 |
Adam Newsome | Cyclotron | Development | Maintenance ladders: end caps added | The original end feet and end caps were
removed from the maintenance ladders and
replaced by new end caps (TRH1637). |
|
155
|
Thursday, August 03, 2023, 10:43 |
Adam Newsome | Trolley | Development | Previous generation video trolley decommissioned | The "old" video trolley featuring
scissor mechanism and DSLR camera has officially
been decommissioned. Going forward, Video |
|
157
|
Thursday, September 14, 2023, 13:51 |
Adam Newsome | Trolley | Maintenance | Lift Trolley: upgrades to camera tilt mechanism | The two camera tilt mechanisms on the lift
trolley have been upgraded. Upgrades include:
For the individual camera: |
|
158
|
Friday, September 15, 2023, 10:15 |
Adam Newsome | Trolley | Maintenance | Lift Trolley: mirror actuation mechanism repair/upgrade | The mirror actuation mechanism was observed
to be "sticky" during 2023 winter
shutdown - it occasionally did not function |
|
162
|
Tuesday, January 23, 2024, 14:03 |
Adam Newsome | Elevation Jack | Maintenance | Inspection of elevating system motor contacts | Motor contactors for the cyclotron elevating
system jacks were inspected on 2025-01-23
by Joel Semilla under work permit C2024-01-19-1. |
|
163
|
Wednesday, January 31, 2024, 11:39 |
Adam Newsome | Elevation Jack | Maintenance | Jack station 11: synchro replaced | Because of observed noise on the synchro
at jack station 11 during recent shutdown
lid up/down operations, the synchro at this |
|
165
|
Wednesday, February 07, 2024, 12:04 |
Adam Newsome | Elevation Jack | Repair | Elevating system - brake master relay fuse issue | It was observed when attempting lid up
operation on 2024-02-06 that the brakes for
each of the jacks were not operating correctly. |
|
166
|
Thursday, February 08, 2024, 08:50 |
Adam Newsome | Elevation Jack | Maintenance | Elevating system - station 10 motor contactor issue | It was observed during lid up operation
on 2024-02-08, approximately halfway through
raising the lid, that the motor contactor |
|
167
|
Friday, February 09, 2024, 15:43 |
Adam Newsome | Elevation Jack | Standard Operation | Lid up operation - 2024 | The cyclotron lid was raised starting ~10:30am
on 2024-02-06 and finishing at ~3:30pm on
2024-02-08, under work permit C2024-02-06-4. |
|