Friday, January 30, 2015, 15:02, Travis Cave, Cyclotron, Standard Operation, Day four of in tank work
|
All shields, ladders and pothole covers are in. One rad survey left to do. |
Thursday, January 29, 2015, 14:53, Travis Cave, Cyclotron, Standard Operation, Day three of in tank work
|
Over 50% of the shields are in some 700's left and the monitor box covers. |
Wednesday, January 28, 2015, 14:33, Travis Cave, Cyclotron, Standard Operation, Day two of in tank work
|
All copper blocker removed from the cyclotron and first radiation survey done. Shields start tomorrow. |
Tuesday, January 27, 2015, 14:40, Travis Cave, Cyclotron, Standard Operation, Day one of in tank work
|
Day one of RH in tank work for the cyclotron (shields and blockers stuff like that) many pictures were taken. |
Tuesday, January 27, 2015, 11:39, Grant Minor, Elevation Jack, Standard Operation, Lid-Up Report 26 Jan 2015
|
Normal
0
false
false
false
|
Monday, January 26, 2015, 07:57, maicodallavalle, Elevation Jack, Maintenance, Fall arrest Platform Railing
|
All of the Fall arrest Platform Railing has been Collapsed for Cyclotron Lid up. |
Friday, January 23, 2015, 10:27, maicodallavalle, Elevation Jack, Maintenance, 2015 Jack Maintenance - Stations #4 and Station #9
|
The Cyclotron Elevating System Shut Down work done this year was done on Station #4 and Station #9.
Work done on Station #4 |
Tuesday, January 13, 2015, 16:46, Grant Minor, Elevation Jack, Development, Upper Bearing Fall Protect Guardrails TRH1217 Installed on Stns 8,10, 3, 4 & 5 9x
|
5 x TRH1217 Upper Bearing Service Platform assemblies were installed between January 6th and January 13th at Stations 8, 10, 3, 4, and 5 (see attached
photos).
The assembly went very smoothly. Dan McDonald and Maico Dalla Valle worked together to install the platforms and wore harnesses and lanyards |
Friday, July 04, 2014, 07:21, Dan McDonald, Elevation Jack, Standard Operation, Cyclotron lid down July-2- 2014
|
Cyclotron lid down was successfully completed on July 2 2014. Lid went partially down before jack nine had to be jogged to catch up to system. After
thirty min of continual system trips Maico Dalla Valle and I Jogged all stations to 42745. Still encountering continual system trips Gord Roy and Dan Louie
removed and reset all relays in system, lid proceeded to lower with out problem. Final jack position recording done at 19:45. |
Wednesday, July 02, 2014, 16:46, Grant Minor, Elevation Jack, Standard Operation, Cyclotron Lid-Up Report for 27 June 2014
|
The cyclotron lid was raised on June 27th, 2014. Start time was 1:05pm end time was 2:17pm (good!) Dan McDonald collected and recorded numbers
from the mechanical counters for the lid up sequence, I am entering the data into the e-Log on his behalf.
Below are the mechanical counter values from the start and finish of the lid-up job: |
Monday, April 28, 2014, 10:20, Dan McDonald, Service Bridge, Maintenance, Bridge orbit reduction box
|
Noticed oil leaking out of reduction box, scan and swipe, disconnect e motor and all related cables from bridge, remove motor and reduction box assembly
with over head crane, disassemble reduction box, grease broken down and separated likely cause of leak. Inspect bearings and internals for wear -all good
re assemble with new grease and gaskets (we added two grease nipples to the bearing housing to aid lubrication), test e motor on its own- good. |
Tuesday, April 08, 2014, 10:45, Travis Cave, Shielding, Standard Operation, Large shield door on the RH B2 level
|
The large shield door on the RH B2 level of the remote handling building has been shut. |
Monday, March 03, 2014, 15:07, Grant Minor, Elevation Jack, Standard Operation, Cyclotron Lid-Down Report Monday 3-March-2014
|
The Cyclotron Lid Down was successfully completed today on Work Permit C2014-03-03-6.
The system only tripped twice on the way down. Both trips were at Station 9, at the following Master Syncro readings: 43194, 39198.
Oil was observed on the Jack #1 platform, but it was determined that it was coming from the crane when it's parked in the beam-on position, and |
Monday, March 03, 2014, 13:09, Travis Cave, Cyclotron, Standard Operation, shields
|
all shields, porthole covers and ladder out and copper blockers in. Some conmination was found on the pads of the ladders (about a 1000 count or so)
and was removed. |
Wednesday, February 26, 2014, 14:55, Travis Cave, Shielding, Standard Operation, shields
|
More shields have been removed from the cyclotron only 16 remain. I was also noted that the lift trolley is making an odd noise and will be looked at
after the shutdown. |
Tuesday, February 25, 2014, 15:00, Travis Cave, Shielding, Standard Operation, shields
|
Started on the removal of shields. |
Friday, February 21, 2014, 11:05, Bevan Moss, Cyclotron, Standard Operation, Old Monitor Box Removed, New installed 7x
|
One of the beam spill monitor boxes was removed and placed into a lead coffin. The fields around the coffin prior to the monitor being placed in
were 145 uSv/hr just above the box and 33.5 uSv/hr inside of it. A swipe was taken inside the box at this time and a count of zero was found. The tray
for the monitor box was then placed into the coffin and the monitor removed from the cyclotrons. The field above the coffin with the monitor box was 1.0 |
Friday, February 21, 2014, 15:58, Bevan Moss, Cyclotron, Standard Operation, Old Monitor Box Removed, New installed
|
During the electrical test the was no contact. To help investigate further the Montitor box was removed from the Cyclotron. It was found to have
zero counts. The issue is believed to have to do with the fit of the box but confirmation of the writing harness continuity needs to be completed. This
will continue on Monday. |
Friday, February 07, 2014, 10:50, Travis Cave, Cyclotron, Standard Operation, 2C install
|
2C has been installed into the cyclotron. |
Friday, January 31, 2014, 10:07, Travis Cave, Cyclotron, Standard Operation, 2C removal
|
2C has been successfully removed from the cyclotron and is now currently sitting in the B2 level of the RH building. A tank access was needed to feel
the stuck QDL. |
Thursday, January 30, 2014, 13:47, Travis Cave, Cyclotron, Standard Operation, shields
|
All shields, pothole covers, and ladders have been installed into the cyclotron. |
|