ID |
Date |
Author |
Category |
Type |
Subject |
82
|
Tuesday, February 16, 2016, 16:32 |
Isaac Earle | Cyclotron | Standard Operation | HE1 Probe Removed from Cyclotron |
The HE1 Probe was removed from the cyclotron this morning following the procedure in Document-126165 (currently in draft status, to be released after the probe has been reinstalled). The procedure took approximately 2 hours from when the trolley was put into the tank until when it was removed from the tank with the probe. The procedure took from 8am - noon including putting the bridge into the cyclotron, and removing the probe from the trolley into the Probes Group work area on the B2 level.
No major surprises were encountered during the procedure. Camera view screen captures were taken at each step to be added to the procedure.
Possible improvements to the procedure and equipment include:
1. A flow restrictor should be added to the inner-member stop tab air line to slow movement
2. The inboard guide views on both sides (camera views #7 and #8) would be more useful if they were more zoomed in
3. It would be useful to be able to turn off the trolley fluorescent light at the inboard end once the bridge is in the tank (it caused glare in some views)
4. The opposite side latch camera view (camera view #5) seems to not be secure enough and was bumped slightly out of position during trolley move, try to secure better
5. In Section 1 of the report it would be better for a final check of each view with the probe mockup to be done after the trolley has been lowered to the bridge
6. The probe didnt lower freely immediately after unhooking the outboard latch. After slight lowering of the frame and a few up and down movements it became free. It is suspected this is because of too much upward force on the probe from the frame due to the inboard tip being tilted too high. Steps have been added to the procedure to prevent this in the future. Another possible improvement to the equipment would be load cells on the trolley or between the trolley and frame |
81
|
Wednesday, February 10, 2016, 14:53 |
Travis Cave | Cyclotron | Standard Operation | shadow shields |
All cyclotron in tank work is completed. |
80
|
Tuesday, February 09, 2016, 14:48 |
Travis Cave | Cyclotron | Standard Operation | shadow shields |
All shadow shields have been installed. Ladders, the pothole covers and the second rad survey will be done tomorrow. |
79
|
Friday, February 05, 2016, 14:57 |
Travis Cave | Service Bridge | Maintenance | outrigger problem |
outrigger 1 had a power failure, bridge was removed power restored and outrigger parked, outrigger will be looked at once the shield are done hopefully. |
78
|
Friday, February 05, 2016, 14:55 |
Travis Cave | Shielding | Standard Operation | shadow shields |
all 200, 400, 500, 600, and some 700 series of shield are in. |
77
|
Wednesday, February 03, 2016, 08:16 |
Dan McDonald | Cyclotron | Standard Operation | Cyclotron lid up |
Lid up procedure Started at 12:00pm. Initial numbers. # 1-47,2-49,3-45,4-47,5-47,6-47,7-49,8-45,9-50,10-50,11-51,12-49. After a number of unsuccessful attempts at jogging the system and trouble shooting it was decided to suspend operations record numbers and resume on Feb 2nd. Final numbers for Feb 1st #1-1289,2-1297,3-1288,4-1295,5-1283,6-1298,7-1287,8-1289,9-1290,10-1296,11-1287,12-1296.
Feb 2nd commence lid up operations at 11:30 am .When Maico Dalla Valle and my self arrived Dan Louie and Arther Leung had attempted to trouble shoot elevating issues and lowered the lid in hopes that raising would be smoother . The counter numbers on our arrival where as follows station # 1-2856,2-2858,3-2848,4-2857,5-2855,6-2861,7-2856,8-2857,9-2852,10-2862,11-2860,12-2859. After Discussion between Grant Minor, Dan Louie and all involved it was decided to lower the lid re gap the yokes and reset counters to base numbers ensuring they correlated with master synchro. lowered lid numbers #1-55,2-59,3-55,4-57,5-57,6-54,7-50,8-54,9-59,10-59,11-58,12-59.
At this point we re gapped to .250" with counters at #1-119,2-177,3-123,4-144,5-137,6-120,7-123,8-111,9-127,10-148,11-128,12-117. After comparison with Dan L and the Master Synchro, stations #2,3,4,5,10 where jogged to better match the average on the counters and synchro these stations where put at 120 on the station counters. Once this was completed we started final lid up operations stopping at 5" to check tank seal, once it was confirmed the seal was not sticking we continued uninterrupted to final lid up position. #1-16947,2-47366,3-47351,4-47365,5-47362,6-47365,7-17495,8-47358,9-47360,10-47366,11-47362,12-47363. Counters #1 #7 appear to be failing, they will be changed out and indexed to match as needed.
|
Attachment 1: lid_up_2016.pdf
|
|
76
|
Wednesday, January 27, 2016, 10:51 |
maicodallavalle | Elevation Jack | Maintenance | 2016 Cyclotron Elevation System Maintenance |
The Cyclotron Elevating System Shut Down work done this year was done on Station #9 and Station #10.
Work done on Station #9
- note the readings on the Station counter and the gap clearance on the Yoke.
- Remove all the spares from Station #9 Elevating system (Spares are made up of two Jacks, two Highfield gear reducers,and one electric motor)
- Reinstall the complete serviced original Station into Station #9.
- Set the noted gap on the Yoke and the same readings on the Station counter.
- Station #9 Jacks were found to have some discoloration on the worm and worm gear. Next shut down they will be taken out and inspected and reinstalled.
Work done on Station #10
- Note the readings on the Station counter and the gap clearance on the Yoke.
- Remove the complete Station #10 Elevating system.
- Install the complete Spare Elevation system(Station#14) into Station #10.
- Set the noted gap on the Yoke and the same reading on the Station counter.
- The complete original Station #10 is taken to the Remote Handing Active Machine shop where each component will be inspected and serviced.(This Station will be ready to be reinstalled during next years Shut Down)
Electric Motors have been reconnected on Station #9 and #10. We have not been able to test them until all the Interlocks have been satisfied. This may happen on Monday February 1st.
|
75
|
Tuesday, January 19, 2016, 17:59 |
Grant Minor | Elevation Jack | Development | Upper Bearing Fall Protection Installation - Stations 1, 2, 6, 7, 8, 11, & 12 |
The installation of the upper bearing fall protection equipment was completed last week by Dan and Maico.
- Full safety platform assemblies (ref. TRH1217) were installed on stations 1, 6, 7, 11, 12
- Short safety platform assemblies (ref. TRH1248) were installed on stations 2 and 8 to avoid interference with the lights
- Inboard anchors and SRL (self retracting lifeline) units were installed on 1, 2, 6, 7, 8, 11, 12, to permit the setup of the inboard railings at each station
- Outboard anchors were drilled and installed at all stations, using either D-ring swivel loops or Saf-Lok wedge anchors (both DBI Sala products), to allow safe setup of the outboard railings at each station
Also note:
- One railing at Station 1 had to be shortened to avoid interference with the guardrail of the aluminum stairs at that station, see attached photo.
- The beam clamp for the horizontal lifeline at Station 1 has an extension that protrudes into the working area. This extension has been marked with pink flagging tape.
- It was noted that one more horizontal lifeline and two more beam clamps are needed to permit safe access to a station. Grant will ask the equipment provider if they can make a shorter beam clamp to use at station 1, then transfer that longer standard clamp to the station that requires it (along with another new longer clamp).
- It was noted that we were short 2 carabiners. Grant will order extra. |
Attachment 1: Station_1_18Jan2016.JPG
|
|
Attachment 2: Station_1_short_left_rail_and_flagged_clamp_18Jan2016.JPG
|
|
Attachment 3: Station_1_stairs_and_short_rail_18Jan2016.JPG
|
|
Attachment 4: Station_2_CCW_aspect_18Jan2016.JPG
|
|
Attachment 5: Station_2_short_18Jan2016.JPG
|
|
Attachment 6: Station_2_short_platform_18Jan2016.JPG
|
|
Attachment 7: Station_3_close_18Jan2016.JPG
|
|
Attachment 8: Station_4_18Jan2016.JPG
|
|
Attachment 9: Station_5_18Jan2016.JPG
|
|
Attachment 10: Station_6_18Jan2016.JPG
|
|
Attachment 11: Station_7_close_18Jan2016.JPG
|
|
Attachment 12: Station_8_short_platform_18Jan2016.JPG
|
|
Attachment 13: Station_9_18Jan2016.JPG
|
|
Attachment 14: Station_10_18Jan2016.JPG
|
|
Attachment 15: Station_11_18Jan2016.JPG
|
|
Attachment 16: Station_12_18Jan2016.JPG
|
|
Attachment 17: Station_12_top_view_2_18Jan2016.JPG
|
|
Attachment 18: Stations_1_and_12_lifeline_18Jan2016.JPG
|
|
Attachment 19: Stations_1-12-11-10_top_view_18Jan2016.JPG
|
|
Attachment 20: Stations_3-4-5-6_general_top_18Jan2016.JPG
|
|
Attachment 21: Stations_11-10-9_general_top_18Jan2016.JPG
|
|
Attachment 22: Stations_12_and_11_top_view_18Jan2016.JPG
|
|
74
|
Tuesday, January 05, 2016, 09:58 |
Travis Cave | Cyclotron | Standard Operation | Opened the shield door |
The shield door on the B2 level has been opened. |
73
|
Tuesday, October 27, 2015, 07:50 |
maicodallavalle | Elevation Jack | Standard Operation | Service to Station # 9 Right side |
Station #9 Cleaning of discoloration-
The right side Jack screw nut and worm screw (mating parts in the right side Jack) had some discoloration from may years ago it is thought.
These two parts were cleaned with Scotch Brite.
The Jack was reassembled with grease.Station #9 has been fully serviced and is ready for 2016 Shut Down to be put back in place.
|
Attachment 1: IMG_2099.JPG
|
|
Attachment 2: IMG_2101.JPG
|
|
Attachment 3: IMG_2103.JPG
|
|
Attachment 4: IMG_2100.JPG
|
|
Attachment 5: IMG_2102.JPG
|
|
Attachment 6: IMG_2095.JPG
|
|
Attachment 7: IMG_2097.JPG
|
|
Attachment 8: IMG_2096.JPG
|
|
Attachment 9: IMG_2098.JPG
|
|
72
|
Wednesday, September 30, 2015, 11:52 |
Isaac Earle | Elevation Jack | Standard Operation | Station 9 Jack Left Side - Inspection & Service Status |
The left side jack was disassembled and cleaned. It was discovered that the left side had been rebuilt with a new jack nut (similar to the three spare jack nuts in the RH machine shop). This nut had been machined as is required to fit the bearing races on and fit the nut into the jack nut case. The jacking case and lid also were machined to accommodate the different size rings for both ends of the nut This rebuild may have been done after the jack failure that occurred in the late 70s / early 80s due to incorrect bearings and grease in the jacks.
There was less grease in the left side, and one of the worm bearings was on the dry side. All other components still seemed lubricated, but not as much as the right side. It seemed that some grease was stuck on the outsides of the jacking case and not mixing with the other grease. The jacking case was approximately 70% full of grease.
There was a normal amount of wear visible on the surfaces of all jack parts according to Maico. No unusual wear or colouration such as on the right side observed. A leak in the shaft seal opposite the drive coupling was observed - this was replaced upon reassembly.
The jack was reassembled without grease . The following measurements were taken:
Nut in jack case - vertical play: 0.008" (vertical when installed)
Nut in jack case - tilt: 0.008"
Worm gear backlash: 0.017"
Nut on jack screw - backlash: 0.040"
Nut on jack screw - horizontal play on top of nut: 0.031"
Nut on jack screw - horizontal play on bottom of nut: 0.031"
The left side jack was fully reassembled with grease and is ready for installation.
|
Attachment 1: IMG_2059.JPG
|
|
Attachment 2: IMG_2060.JPG
|
|
Attachment 3: IMG_2062.JPG
|
|
Attachment 4: IMG_2063.JPG
|
|
Attachment 5: IMG_2064.JPG
|
|
Attachment 6: IMG_2065.JPG
|
|
Attachment 7: IMG_2066.JPG
|
|
Attachment 8: IMG_2067.JPG
|
|
Attachment 9: IMG_2068.JPG
|
|
Attachment 10: IMG_2069.JPG
|
|
Attachment 11: IMG_2071.JPG
|
|
Attachment 12: IMG_2072.JPG
|
|
Attachment 13: IMG_2073.JPG
|
|
Attachment 14: IMG_2074.JPG
|
|
Attachment 15: IMG_2075.JPG
|
|
71
|
Wednesday, September 30, 2015, 11:26 |
Isaac Earle | Elevation Jack | Standard Operation | Station 9 Jack Right Side - Unusual Wear Investigation |
The following people were consulted regarding the unusal wear noticed on jack station #9 right side
Neil Wong: Neil inspected the jack parts. Based on the wear and condition of the grease he thought that the wear wasn't recent and that the parts are ok to use. Neil supported assembling the parts w/o grease and measuring clearances and backlash worm gears & jack screw to nut
Guy Stanford: Guy came in and inspected the parts. Based on the condition of the grease and the parts he also thought that the parts are ok to use and that the backlash/clearance tests should be done. Guy could not recall when and which stations were damaged.
Ron Mullen: Ron was contacted by phone. He suggested putting in one of the new phosphor bronze jack nuts. He also supported doing the tests
Bill Chapman: Bill was contacted by phone. Bill remembered discoloration of some of the stations. He also agreed with doing the tests. He thought the worn one should be ok to use. He suggested cleaning the old one, reassembling and installing, then pulling out again after 1 year of use to inspect.
There are 3 spare phosphor bronze jack nuts on the shelf in the RH machine shop (2 left, 1 right). No documentation has been found regarding these spares. The right side spare was put onto the jack screw (no problems), but when it was put into the jack housing we realized that the nut requires machining to accommodate the bearing races. The jack case and the jack lid also need to be modified to accommodate the rings at each end of the jacking nut (this was confirmed when Station 9 Jack Left Side was disassembled - see next E-Log entry). Machining these parts would likely need to be done off site due to the size.
It was noted that on the inner thread of the jacking nut the thin edge was slightly sheared off. A piece of the thread was removed to prevent this piece from shearing into the jacking gearbox - see attached photos.
The original right side jack parts were cleaned and reassembled without grease. The following measurements were taken:
Nut in jack case - vertical play: 0.010" (vertical when installed)
Nut in jack case - tilt: 0.010"
Worm gear backlash: 0.014" (travel of key on the worm shaft before nut moves)
Nut on jack screw - backlash: 0.023" (vertical travel when lifting nut)
Nut on jack screw - horizontal play on top of nut: 0.027"
Nut on jack screw - horizontal play on bottom of nut 0.022"
One of the new spare jack nuts was installed on the jack screw. The following measurements were taken:
Nut on jack screw - backlash: 0.005"
Nut on jack screw - horizontal play on top of nut: 0.004"
Nut on jack screw - horizontal play on bottom of nut: 0.005"
Outer diameters of the old jack nut were measured:
Top bearing race: 7.473"
Bottom bearing race: 7.472"
Top jack case lid: 7.461"
Lower jack nut housing bore: 7.463"
Outer diameters of a new unused jack nut were measured:
Top bearing race: 7.479"
Bottom bearing race: 7.480"
It was decided that we should disassemble the left side and inspect before proceeding. Work will continue on the right side when Maico returns from holidays on Oct 22. The current plan is to clean off the wear, reassemble, install, run it for one year, and then remove and inspect in Shutdown 2017.
Photos of the Station 9 Jack Right Side parts are attached. |
Attachment 1: IMG_2046.JPG
|
|
Attachment 2: IMG_2047.JPG
|
|
Attachment 3: IMG_2048.JPG
|
|
Attachment 4: IMG_2049.JPG
|
|
Attachment 5: IMG_2051.JPG
|
|
Attachment 6: IMG_2050.JPG
|
|
Attachment 7: IMG_2052.JPG
|
|
70
|
Thursday, September 17, 2015, 18:38 |
Grant Minor | Elevation Jack | Maintenance | Station 9 Jack Worm Gear Inspection - unusual wear markings 16Sept2015 |
Unusual wear markings were observed on the Station 9 jack (not sure if L or R jack?) during a visual inspection.
The grease looked to be in good condition and no sign of chips or contamination was found in the grease, so it is possible that the wear markings are older.
More investigation is required before using this worm gear assembly again.
Grant Minor, P.Eng.
|
Attachment 1: Station_9_Worm_Gear_Spur_Spline_Wear_16Sept2015.JPG
|
|
Attachment 2: Station_9_Worm_Gear_Spur_Spline_wear_2_16Sept2015.JPG
|
|
Attachment 3: Station_9_worm_gear_wear_markings_2_16Sept2015.JPG
|
|
Attachment 4: Station_9_worm_gear_wear_markings_3_16Sept2015.JPG
|
|
Attachment 5: Station_9_worm_gear_wear_markings_16Sept2015.JPG
|
|
Attachment 6: New_Worm_Gear_Spur_Spline_for_comparison_16Sept2015.JPG
|
|
Attachment 7: Station_9_jack_bearing_races_16Sept2015.JPG
|
|
Attachment 8: Station_9_jack_bearing_races_2_16Sept2015.JPG
|
|
69
|
Tuesday, July 28, 2015, 11:47 |
Dan McDonald | Trolley | Maintenance | Camera trolley service |
Serviced the Camera trolley this morning as per Mike Gallops service outline. |
68
|
Thursday, April 16, 2015, 15:26 |
Grant Minor | Elevation Jack | Maintenance | Cyclotron Elevating System Maintenance Rotation Record - Updated 16 Apr 2015 |
|
Attachment 1: Cyclotron_Elevating_System_Maintenance_Rotation_Record_16Apr2015.pdf
|
|
67
|
Thursday, April 02, 2015, 12:09 |
Dan McDonald | Cyclotron | Standard Operation | Lid Down operations April, 2, 2015 |
Lid down Start at 11:17, lid went down without any issues or stop's. Lid finish at 11:45
Start count Finish count
1- 47386 47
2- 47378 49
3- 47374 45
4- 47382 46
5- 47394 47
6- 47385 48
7- 47398 49
8- 47375 45
9- 47395 50
10- 47395 49
11- 47395 51
12- 47393 49 |
66
|
Friday, March 27, 2015, 11:25 |
Travis Cave | Cyclotron | Standard Operation | Copper Blockers |
Copper Blockers have been removed from the cyclotron and one ladder has been installed. |
65
|
Friday, March 27, 2015, 07:31 |
Dan McDonald | Cyclotron | Repair | Lid up operations |
Lid up recap for March 26th 2015.
Start time 14:50 Master- 33 Finish 15:25 Master -47413 Zero jogs to system.
- 1- 36 47386
- 2-38 47378
- 3-33 47374
- 4-36 47382
- 5-36 47394
- 6-36 47385
- 7-37 47398
- 8-33 47373
- 9-38 47395
- 10-38 47395
- 11-38 47395
- 12-36 47393
|
64
|
Thursday, March 26, 2015, 15:48 |
Grant Minor | Elevation Jack | Standard Operation | Cyclotron Lid-Up 26 March 2015 |
Lid was raised today (2nd time during 2015 shutdown) for additional inflector work.
Dan and Maico report that the lid went up smoothly and no jogs were required. The operation took about 30 minutes.
- Grant |
63
|
Thursday, March 19, 2015, 13:14 |
maicodallavalle | Shielding | Standard Operation | Remote Handling B2 level Shielding door |
The Remote Handling B2 level Shielding door has been closed. |