Wednesday, April 27, 2022, 16:05, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2022
|
The lid down operation took place on Apr. 27, 2022.
The system was not energized well ahead of time to allow to "warm up", |
Monday, March 21, 2022, 13:14, Adam Newsome, Trolley, Repair, Video Trolley Mk 1 - Radial Limit Switch Replacement
|
An issue was observed in which radial motion on the Video Trolley Mk 1 did not respond to commands. After troubleshooting, it was determined that this
was due to the "OP LIMIT" interlock - the "OP LIMIT" pushbutton on the console was illuminated in red, and needed to be continuously
held down in order to operate the radial in/out motion buttons. |
Tuesday, February 08, 2022, 11:39, Adam Newsome, Cyclotron, Development, Radiation Survey - sampling rate error
|
When attempting to perform the radiation survey, the program displayed an error at startup stating that the software was not able to keep up with the
incoming hardware samples, and suggested to increase sampling rate or buffer size. The default sampling rate of 500 ms was not used - rather, 100 ms was
used. No issues were observed with this rate. As far as I am aware, this issue had not occurred in the past, and the cause is unknown. |
Friday, February 04, 2022, 11:52, Adam Newsome, Cyclotron, Standard Operation, Lid up operation - 2022
|
The lid up operation took place on Feb. 4, 2022.
The system was not energized well ahead of time to allow to "warm up", |
Wednesday, January 19, 2022, 09:50, Travis Cave, Shielding, Standard Operation, Shield door is now open
|
The shield door is now open on the RH B2 level. |
Tuesday, August 31, 2021, 14:28, Adam Newsome, Trolleys serviced, Development, Upper Resonator Trolley - Finger Cylinders Replaced
|
The two support fingers on the upper resonator trolley were bent due to excessive loading during cylinder toggling.
Fingers were bent back into position such that they are vertical when the cylinder is retracted.
The cylinders used to actuate these fingers were replaced (one was leaking) - replacement allowed for the opportunity for upgrade. The following |
Wednesday, June 16, 2021, 09:59, Adam Newsome, Service Bridge, Development, Bridge Lift Mechanism Refurbishment (Phase 1 of 2) - Complete  
|
The following items from Phase 1 of 2 of Bridge Lift Mechanism Refurbishment (O504) are complete:
Replacement of pneumatic tubing
Replacement of hydraulic cylinders for lifting, and procurement of spare
The
newly refurbished system has been tested by Dan McDonald (June 16, 2021) and verified as functioning. |
Wednesday, May 05, 2021, 12:20, Adam Newsome, Infrastructure, Development, Cyclotron RH Control Room: Outlets Installed
|
The following outlets were installed by Electrical Services Group in order to facilitate upgrading power supplies for Cyclotron Remote Handling, as per
Work Request 5289: |
Tuesday, April 20, 2021, 15:02, Adam Newsome, Carrier, Development, Emergency Trolley Rescue Winch: Installed and Tested 
|
An emergency trolley rescue winch (TRH1527) was developed for the purposes of retrieving trolleys from the cyclotron tank whose radial drive have failed.
This winch was tested today on the carrier in mockup setting with success by Adam Newsome, Dan McDonald, and Travis Cave. The
following is a summary of the test: |
Thursday, April 01, 2021, 13:47, Adam Newsome, Cyclotron, Standard Operation, Vault Shield Door Closed
|
The vault shield door has been closed and seal inflated. The operation was performed with no issue. |
Friday, February 26, 2021, 13:00, Adam Newsome, Trolleys serviced, Maintenance, Lower Resonator Trolley - Radial Drive Failure Issue
|
On Feb. 24 while practising a training exercise, the lower resonator trolley unexpectedly experienced a radial drive failure. The trolley did not move
in either radial direction (this occurred after approx. 5 minutes in the tank, near the centre post, with FTRF jig installed). The trolley was retrieved
from the tank manually for investigation. Upon retrieval and testing on the mockup, the radial drive began to work again. |
Friday, February 26, 2021, 08:29, Adam Newsome, Trolleys serviced, Maintenance, First Turn Radial Flag (FTRF) Jig - Pneumatic Upgrade
|
Old fittings and broken pneumatic tubing on the FTRF jig have been replaced with new push-connect fittings and polyurethane tubing. The jig was previously
not in a functioning state due to damaged tubing. A pneumatic diagram was created in the process of the upgrade. The tubing will be cleaned up within the
next few days and the jig tested. |
Wednesday, February 03, 2021, 12:37, Adam Newsome, Cyclotron, Development, Ladder Handling Tool - First In-Tank Test (SAS0824)  
|
The newly developed Ladder Handling Tool (TRH1401), which is used to move the maintenance ladders from the #5 resonator area closer to the centre post,
was tested inside the cyclotron tank to perform the actual operation. This is a task that was historically performed by operators, resulting in dose received
(typically 0.1 - 0.3 mSv for two people, twice per annual shutdown). This tool completely eliminates the need for people to receive this dose - only a |
Friday, January 22, 2021, 14:30, Adam Newsome, Cyclotron, Standard Operation, Lid up operation - 2021
|
The lid up operation took place on Jan. 22, 2021.
The system was not energized well ahead of time to allow to "warm up", as is usually done.
|
Wednesday, January 13, 2021, 11:35, Adam Newsome, Shielding, Maintenance, Shadow Shields Inspection - 2021 Shutdown
|
All shadow shields which are remotely placed inside the cyclotron during shutdown were inspected by Adam Newsome and Chris Peterson on Jan. 13, 2021.
The inspection consisted of:
Verifying feet were damage-free, welds intact (note: only outer feet were checked due to the large amount of effort that would be involved |
Monday, November 09, 2020, 09:17, Adam Newsome, Infrastructure, Development, New crane pendant: B2 level crane
|
A new remote crane pendant was installed to replace the existing wired pendant on the B2 level of Remote Handling building (basement area - vault access).
Two remote pendants exist (spare). The previously used pendant will be kept, at least temporarily, as a backup if needed.
|
Thursday, November 05, 2020, 15:38, Adam Newsome, Infrastructure, Development, New crane pendant: B1 level crane
|
A new remote crane pendant was installed to replace the existing wired pendant on the B1 level of Remote Handling building (electrical lab). Two remote
pendants exist (spare). The previously used pendant will be kept, at least temporarily, as a backup if needed.
|
Thursday, July 16, 2020, 11:57, Adam Newsome, Cyclotron, Development, Cyclotron Mockup: Orbital Position Pendant Upgrade 
|
The pendant used for controlling the orbital motion of the bridge mockup was upgraded. Features of the new pendant include:
One cable to controller (formerly two cables required)
Ergonomic and robust form factor of pendant
Easily
modifiable button/contact setup, with spare button space
Extended cable to reach anywhere in the room
Pictures attached show |
Sunday, April 05, 2020, 13:24, Dan McDonald, Elevation Jack, Maintenance, Elevating system station swap 2019-2020
|
Station 11-12 where swapped for station 13-14 during 2018-2019 shutdown. Once lock out and motor disconnect was complete we commenced removal of spares
and installation of original equipment. Station 13 was swapped in for station 3 and the upper bearing was serviced. In addition to regular maintenance
we built and installed a cover for the void in between station 10-11, this void in shielding measured approx 2'x4'. RH borrowed a demo Milwaukee 1' cordless |
Saturday, April 04, 2020, 10:03, Dan McDonald, Trolley, Development, Addition of DC motor controller mounts
|
Upper and lower resonator trolleys received mounting plates and brackets to accommodate DC motor controls for updated drive motors. |
|