Friday, March 06, 2020, 13:36, Keith C Ng, M9, Repair, M9 B1 moved to warm cell
|
The M9 B1 was removed from the M9 channel surveyed and moved to the remote handling warm cell for refurbishment.
The warm cell is currently locked. Remote Handling should be contacted if access is needed to B1.
A field map of B1 is attached as a pdf file. |
Friday, August 07, 2020, 16:18, Keith C Ng, M9, Maintenance, T2 M9 exit port and B1 flange cleaning
|
Today we attempted to scrape remnant indium from T2 M9 exit port and clean B1 knife flange for the new magnet. Report of todays activities attached to
the elog. |
Monday, August 10, 2020, 16:08, Keith C Ng, M9, Development, M9 Q1Q2 magnet assembly installed in pit
|
The M9 Q1Q2 magnet assembly was installed in the M9 beam line today.
Attached to elog is an inspection report of the indium ring that will be used in the M9 T2 Q1 joint. |
Tuesday, February 14, 2012, 16:29, Keith C Ng, M20, Repair, m20 q1 q2 repair
|
Warm cell reconfigured for water leak repair at coil termination. Radiation surveys done. M20 Q1 ready for removal of insulators.
Attached photo of warm cell as of Tuesday morning. |
Thursday, February 16, 2012, 08:08, Keith C Ng, M20, Repair, m20 q1 q2 repair
|
Insulators # 6,7,8 removed from Q1 headers late afternoon by C Ballard. Ready for removal and re-brazing of #7 joint some time today. |
Thursday, February 16, 2012, 16:22, Keith C Ng, M20, Repair, m20 q1 q2 repair
|
Old #7 coil fitting removed, replaced and re-brazed today by M Good. Insulators ready to go back on to magnet coils to be pressure checked.
Image P1020013.JPG shows #7 coil fitting before removal. Heat shielding in the form of small aluminum sheets were installed to protect the magnet
and electrical wiring. |
Friday, February 17, 2012, 15:35, Keith C Ng, M20, Repair, m20 q1 q2 repair
|
Reinstalled ceramic insulators #6 7 8 to Q1 magnet by C Ballard. #6 and 8 went on with no issues. The copper tubing on insulator #7 had to be bent to
match the new position of the re-brazed #7 fitting. This may have been due to the removal of the inner and outer conductors (the two copper plates that
clamp the two coils together) during yesterdays repair which shifted the position of the coil. See photos. |
Thursday, May 24, 2012, 18:59, Grant Minor, M20, Repair, M20 front-end leak vacuum check T2/Q1/Q2/Scraper 6x
|
Normal
0
false
false
false
EN-CA
X-NONE
X-NONE
|
Thursday, April 25, 2019, 11:13, Keith C Ng, M20, Repair, M20 Q2 repair notes
|
See attached scan for repair notes regarding M20 Q2 during the 2019 winter shutdown. The repair method for M20 Q2 was instigated by Doug Preddy and Beamlines
group. Cooling line was blanked off during the 2019 winter shutdown in order to keep the M20 beamline running without removing the magnet and doing a complete
repair on the leaking coil. |
|