89
|
Monday, February 22, 2016, 16:09 |
Keith C Ng | Primary Beamlines | Development | 4V CM1 blanking |
Rolled
indium into new blanking plate turned down |
|
|
90
|
Friday, March 04, 2016, 16:05 |
Keith C Ng | Primary Beamlines | Development | vault beamline 4 disassembly |
Attempted
to remove RH parts between Q1, 2 and monitor |
|
|
91
|
Wednesday, March 16, 2016, 17:19 |
Ron Kuramoto | Primary Beamlines | Development | 4VQ3 Removal | On 8March2016, under W/P C2016-03-08-2,
4VQ3 was lifted out of BL4V with the vault
orbit crane where it was first weighed then |
|
|
92
|
Wednesday, March 16, 2016, 17:57 |
Ron Kuramoto | Primary Beamlines | Development | 4VQ1&Q2 Removal | On 14March2016, 4VQ1&Q2 were
removed from BL4V and lowered into the Vault
basement B3 level where they were stored |
13x |
|
93
|
Thursday, March 31, 2016, 15:32 |
Keith C Ng | Primary Beamlines | Development | 1VM3 to 1VQ4 joint. | Re-installed indium vacuum joint for 1VQ4,
routing installation. R. Kuramoto sprayed
silicone grease on to the threads and bushings |
|
|
104
|
Wednesday, March 08, 2017, 16:05 |
Keith C Ng | Primary Beamlines | Repair | collimator joint repair | Started uncovering the area above the T2
to Q13 joint:
|
|
|
105
|
Thursday, March 16, 2017, 15:50 |
Keith C Ng | Primary Beamlines | Repair | collimator b transition to t2 | On Monday found leaking joint was the ring
directly downstream of T2. Vacuum group has
been spraying Vacseal (http://www.vacseal.net/Pages/default.aspx) |
|
|
106
|
Thursday, July 27, 2017, 09:02 |
Keith C Ng | Primary Beamlines | Development | test | test |
|
|
107
|
Tuesday, January 23, 2018, 15:44 |
Keith C Ng | Primary Beamlines | Repair | 1AQ15 insulator repair | Assisted beamlines in replacing 2 insulators
on 1A Q15 magnet. #10 and #14 insulators
were found to be leaking at the ceramic, |
|
|
108
|
Wednesday, January 31, 2018, 15:28 |
Keith C Ng | Primary Beamlines | Repair | Q15 repair | Beamlines has changed out another 2 insulators
on Q15 after discovering two additional leaks.
Insulators #2 & #4 were replaced. One |
|
|
109
|
Thursday, February 01, 2018, 15:44 |
Keith C Ng | Primary Beamlines | Repair | q15 repair | Correction that all supply side (even numbered
insulators) ceramic insulators on Q15 have
been replaced with new old stock insulators |
|
|
110
|
Monday, February 05, 2018, 15:40 |
Keith C Ng | Primary Beamlines | Repair | 1A Q15 repair. | 1.) Completed covering up 1A Q15.
2.) RH flask currently contains the
8 insulators removed from Q15. 3.6 mSv/h |
|
|
111
|
Wednesday, February 14, 2018, 10:36 |
Keith C Ng | Primary Beamlines | Repair | 1a q12 q13 | Uncovered and placed bridges for 1a q12
q13 for doug's re cabling work. See WP C2018-02-13-2:
work |
|
|
119
|
Tuesday, April 16, 2019, 11:19 |
Ron Kuramoto | Primary Beamlines | Repair | 1AQ14 B/L Flange Broken Thermocouple | On March 7,2019 the Thermocouple (TC) cable
which monitors the temperature of the 1AQ14
B/L vacuum joint was broken when the iron |
|
|
122
|
Tuesday, September 24, 2019, 14:37 |
Keith C Ng | Primary Beamlines | Standard Operation | lead pig radiation survey | Surveyed contents of storage flask located
at TNF. The lid was lifted off roughly 12"
up and a pole monitor was swept over the |
|
|
123
|
Thursday, October 24, 2019, 14:41 |
Keith C Ng | Primary Beamlines | Maintenance | annotated drawing of 1A Q15 cooling headers | Annotated drawing of TBP0425D attempting
to capture the repairs of 1A Q15 triplet
magnet ceramic insulator/coils over the years. |
|
|
126
|
Thursday, March 19, 2020, 15:42 |
Keith C Ng | Primary Beamlines | Development | Vault beamline beam position monitor | The Beam Position Monitor between 1VB1
and 1VM3 has been installed. The indium joints
are leak tight, however the V flanges are |
|
|
129
|
Friday, March 18, 2022, 12:12 |
Keith C Ng | Primary Beamlines | Repair | q15 repair | beamlines replaced leaking insulator
on q15, circuit #4. See updated pdf for replacement
part and location. |
|
|
130
|
Friday, May 06, 2022, 11:27 |
Keith C Ng | Primary Beamlines | Standard Operation | 4V CM1 RH joint install | 2022 Apr 28 to 29:
Installed a new remote handling 4"
indium joint for new beamline 4 north section. |
|
|
8
|
Thursday, October 11, 2012, 16:40 |
Keith C Ng | M9 | Repair | m9 t2 joint repair | Today:
Bridge setup complete; Noticed 12
x 3 x 3 block when placed on top of several |
|