Entry  Monday, February 22, 2016, 16:09, Keith C Ng, Primary Beamlines, Development, 4V CM1 blanking 20160222_beamline4v_P1030502.JPG20160222_beamline4v_P1030511.JPG20160222_beamline4v_P1030505.JPG20160223_4VCM1_blank_off_inspection_report.pdf
 
Rolled indium into new blanking plate turned down to 5.550". Dry fit with no indium
ok. Assembled hook eyes from the previous blank off plate (removed from the slits box?). Used the same 20.5 mm spring compression (1.5 turns of the nut
Entry  Friday, March 04, 2016, 16:05, Keith C Ng, Primary Beamlines, Development, vault beamline 4 disassembly 
 
Attempted to remove RH parts between Q1, 2 and monitor vacuum box. Removed Q1 to monitor
box parts, could not remove monitor to Q2 parts, pin drive and indium ring are stuck in place. Indium joint is severed however. Collar was removed.
Entry  Wednesday, March 16, 2016, 17:19, Ron Kuramoto, Primary Beamlines, Development, 4VQ3 Removal IMG_1893.JPGIMG_1893.JPGIMG_1899.JPGIMG_1902.JPGIMG_1907.JPG
 On 8March2016, under W/P C2016-03-08-2, 4VQ3 was lifted out of BL4V with the vault orbit crane where it was first weighed then lifted onto the
RH flat deck rail dolly.  It was then moved into the RH basement where it was surveyed before lifting it up onto the Red wagon cart in the RH loading
bay.  It was then pulled to the Meson Hall loading bay by fork lift where and then over the Cycloton vault to the top of the E-Hall roof beams under
Entry  Wednesday, March 16, 2016, 17:57, Ron Kuramoto, Primary Beamlines, Development, 4VQ1&Q2 Removal 13x
 On 14March2016, 4VQ1&Q2 were removed from BL4V and lowered into the Vault basement B3 level where they were stored in the south west corner
on their respective wood pallets.  The hot ends of both magnets were place against the west wall.  4VQ2 was lifted out first and moved temporarily
downstream where it was separated from its magnet stand. Q2 was then craned into the basement where it was tipped 45o to lay on the flat side
Entry  Thursday, March 31, 2016, 15:32, Keith C Ng, Primary Beamlines, Development, 1VM3 to 1VQ4 joint. 
Re-installed indium vacuum joint for 1VQ4, routing installation. R. Kuramoto sprayed silicone grease on to the threads and bushings on pin drive. Drove
down tapererd pins and stopped 1/16" short of old marker markings.  RK. Commented on the drive screw bending under load, reversed drive 1/2 turn
to relieve the stress on the screw.
Entry  Wednesday, March 08, 2017, 16:05, Keith C Ng, Primary Beamlines, Repair, collimator joint repair t2m920170308_114226_1136.jpgt2m920170308_151426_1438.jpg
Started uncovering the area above the T2 to Q13 joint:
 
Entry  Thursday, March 16, 2017, 15:50, Keith C Ng, Primary Beamlines, Repair, collimator b transition to t2 20170316_collimatorb_RHB_8023.JPG20170316_collimatorb_RHB_8025.JPG
On Monday found leaking joint was the ring directly downstream of T2. Vacuum group has been spraying Vacseal (http://www.vacseal.net/Pages/default.aspx)
sealant over the last 3 days attempting to get it in between the flanges and have partial vacuum to draw in the fluid. Seven sprays have been completed
as of March 16th.
Entry  Thursday, July 27, 2017, 09:02, Keith C Ng, Primary Beamlines, Development, test 
test
Entry  Tuesday, January 23, 2018, 15:44, Keith C Ng, Primary Beamlines, Repair, 1AQ15 insulator repair vlcsnap-00001.jpgvlcsnap-00002.jpg20180123_1aq15repair_P1030875.JPG20180123_1aq15repair_P1030880.JPG
Assisted beamlines in replacing 2 insulators on 1A Q15 magnet. #10 and #14 insulators were found to be leaking at the ceramic, where the stainless steel
fitting joins the insulator. They were both replaced. During re-installation of the #10 ceramic, the VCR coil termination broke off the coil end and a
new one with updated design (see TBP0379) had to be soldered back in its place. The original SS fittings are deemed to have problems in their construction
Entry  Wednesday, January 31, 2018, 15:28, Keith C Ng, Primary Beamlines, Repair, Q15 repair 
Beamlines has changed out another 2 insulators on Q15 after discovering two additional leaks. Insulators #2 & #4 were replaced. One of them failed
on installation (broken ceramic?)  and was replaced by another stocked replacement. Magnet was pressure tested and now enegerized as part of power
testing. Doug P. expects repairs to be complete and to cover up the area by tomorrow.
Entry  Thursday, February 01, 2018, 15:44, Keith C Ng, Primary Beamlines, Repair, q15 repair 
Correction that all supply side (even numbered insulators) ceramic insulators on Q15 have been replaced with new old stock insulators as of today. Beamlines
finds no power or water issues. Expected to cover up tomorrow moving on to the Q12 and Q13 magnet area next week. 
Entry  Monday, February 05, 2018, 15:40, Keith C Ng, Primary Beamlines, Repair, 1A Q15 repair. 20180205_1aq15repair_P1030889.JPG
1.) Completed covering up 1A Q15.
2.) RH flask currently contains the 8 insulators removed from Q15. 3.6 mSv/h on contact, 40-60 uSv/h @ .5 m. Double bagged. Bag exterior was swiped
clean, inside was not checked (didn’t want to breach interior bag just to swipe components).
Entry  Wednesday, February 14, 2018, 10:36, Keith C Ng, Primary Beamlines, Repair, 1a q12 q13 P1030907.JPG
Uncovered and placed bridges for 1a q12 q13 for doug's re cabling work. See WP C2018-02-13-2: work
permit
Entry  Tuesday, April 16, 2019, 11:19, Ron Kuramoto, Primary Beamlines, Repair, 1AQ14 B/L Flange Broken Thermocouple 1AQ14_FlgTC1_7Mar2019.jpeg1AQ14_FlgTC2__7Mar2019.jpeg1AQ14_FlgTC3_7Mar2019.jpeg
On March 7,2019 the Thermocouple (TC) cable which monitors the temperature of the 1AQ14 B/L vacuum joint was broken when the iron shield block (Triumf Dwg
D-3237 aka M8 Tongue block) was restored on the east of the T2 Monolyth. See attached photos.  This TC (Omega #KTSS-116U-144) is attached to the 1AQ14
Indium ring seal (Triumf Ref Dwg TBP0372D) and should be replaced the next time this B/L joint is serviced.
The Controls Group has noted on the CCSC2,
Entry  Tuesday, September 24, 2019, 14:37, Keith C Ng, Primary Beamlines, Standard Operation, lead pig radiation survey 
Surveyed contents of storage flask located at TNF. The lid was lifted off roughly 12" up and a pole monitor was swept over the opening. The fields
of the combined items in the flask were 9.84 mSv/h at 12-24". Extrapolated, the field is approximately 3.7 mSv/h at 1/2 m. 
Entry  Thursday, October 24, 2019, 14:41, Keith C Ng, Primary Beamlines, Maintenance, annotated drawing of 1A Q15 cooling headers  tbp0425d_revB_acad-magnetinsulatortopheaderassembly_w-repairannotations.pdf
Annotated drawing of TBP0425D attempting to capture the repairs of 1A Q15 triplet magnet ceramic insulator/coils over the years.

Note that the file contains embedded comments visible only if opening the file in adobe acrobat reader.
Entry  Thursday, March 19, 2020, 15:42, Keith C Ng, Primary Beamlines, Development, Vault beamline beam position monitor 
The Beam Position Monitor between 1VB1 and 1VM3 has been installed. The indium joints are leak tight, however the V flanges are leaking slightly. The
leak is small enough to still be able to run beam.
Entry  Friday, March 18, 2022, 12:12, Keith C Ng, Primary Beamlines, Repair, q15 repair tbp0425d_revB_acad-magnetinsulatortopheaderassembly_w-2022_repairannotations.pdfInkedRH1_0044_LI.jpgRH1_0046.jpgRH1_0050.jpgRH1_0049.jpg
 beamlines replaced leaking insulator on q15, circuit #4. See updated pdf for replacement part and location.
Entry  Friday, May 06, 2022, 11:27, Keith C Ng, Primary Beamlines, Standard Operation, 4V CM1 RH joint install 2022_4v_cm1_rh_joint_install.pdf
 2022 Apr 28 to 29:
Installed a new remote handling 4" indium joint for new beamline 4 north section. Issues were encountered in clearance between the downstream
steering magnet and the compression collar of the joint. Joint installation itself went smoothly. 
Entry  Thursday, October 11, 2012, 16:40, Keith C Ng, M9, Repair, m9 t2 joint repair 20121011_RH1_01_0357.JPG20121011_RH1_02_0367.JPG20121011_RH1_02_0362.JPG20121011_RH1_02_0363.JPG
Today:
Bridge setup complete; Noticed 12 x 3 x 3 block when placed on top of several other blocks rocked when placed down.
Took initial photos of joint: west side approximately 0.05" to 0.06" gap, east side 0.20" to 0.220" gap. Joint appears to be