ID |
Date |
Author |
Category |
Type |
Subject |
Text |
|
36
|
Monday, June 05, 2017, 16:16 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender stand assembly complete | Assembly
of two complete bender stands was completed |
14x |
35
|
Thursday, June 01, 2017, 15:25 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender adjustment blocks modified to fit magnet | Adjustment blocks were installed on the
second dipole bender today (labeled "No.
03" "C15-III-57/15"). The |
|
37
|
Wednesday, June 28, 2017, 17:37 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender "No. 1" installed on magnet stand | BL4N 35-deg bender magnet "No.
1" has been installed onto the magnet
stand with "stand leg" configuration |
|
17
|
Friday, May 15, 2015, 11:06 |
Isaac Earle | 100KW Beam Dump | Development | BD and Upper Pb Shield Water Hoses Replaced | The beam dump and upper lead shield
flexible hose assemblies have been replaced
with smaller diameter versions to allow for |
|
22
|
Wednesday, June 10, 2015, 14:57 |
Isaac Earle | 100KW Beam Dump | Development | BD Water System Leak Test | A leak test was performed on the beam dump
water system on June 9 in the afternoon.
- Pipe segments tested: The entire |
|
7
|
Wednesday, December 03, 2014, 10:45 |
Isaac Earle | 100KW Beam Dump | Development | BD Signals Traced from Service Stand to Junction Box | On Dec 2 the cables from the BD service
stand area to the junction box were traced
to establish which sensors correspond to |
|
32
|
Tuesday, April 18, 2017, 19:28 |
Jason Kapalka | T-Hall Crane | Development | ATH overhead crane fault investigation | On April 18, 2017, an investigation was initiated
to determine the cause of the ARIEL Target
Hall overhead crane faults that occurred |
8x |
30
|
Friday, March 31, 2017, 19:39 |
Jason Kapalka | T-Hall Crane | Development | ARIEL Target Hall overhead crane faults (Test Mode) | On March 29, 2017, a 9 tonne steel shield
block was transferred from the ARIEL Target
Pit and placed into a
|
|
31
|
Wednesday, April 12, 2017, 10:52 |
Jason Kapalka | T-Hall Crane | Repair | ARIEL Target Hall crane oil leaks & inspection plan | On March 29, 2017, a 9 tonne load was transferred
in the ARIEL Target Hall with the overhead
crane (TRIUMF crane #44). On April 3, 2017, |
|
34
|
Tuesday, May 16, 2017, 17:30 |
Jason Kapalka | T-Hall Crane | Development | ARIEL Target Hall Overhead Crane Measurements | On May 5, 2017 the Beamlines and Remote Handling
groups recorded distances in the ARIEL Target
Hall from the Target Pit floor and B1 Target |
|
59
|
Thursday, March 16, 2023, 14:41 |
Adam Newsome | T-Hall Crane | Development | ARIEL Target Hall Crane - Spare Pendant Procured, Tested | A spare pendant for the overhead crane
was procured from COH. The pendant's functionality
is the same as the original one's. The pendant |
|
61
|
Tuesday, April 25, 2023, 12:28 |
Adam Newsome | T-Hall Crane | Standard Operation | ARIEL Target Hall Crane - Drives Fault | Today while operating the crane with load,
the crane stopped moving. Upon investigating,
all safety signals appeared to be OK. Fault |
|
75
|
Wednesday, December 11, 2024, 11:45 |
Albert Kong | Hot Cell 1 | Development | APTW Front End Service Tray and Associated Component Testing | Dec 10, 2024
Testing completed: |
16x |
71
|
Tuesday, November 19, 2024, 15:38 |
Albert Kong | Hot Cell 1 | Standard Operation | APTW Front End Moved into Hot Cell | The APTW front end was moved into the hot
cell, on the lift table, following procedures
outlined in Document-244862. |
23x |
72
|
Wednesday, November 27, 2024, 18:38 |
Albert Kong | Hot Cell 1 | Standard Operation | APTW Front End Electrical Cable Replacement Testing | November 27, 2024
Testing completed:
Removal and re-insertion |
19x |
42
|
Tuesday, November 19, 2019, 10:31 |
Adam Newsome | T-Hall Crane | Repair | 900VFD Encoder Board Replacement | An issue arose in which the ARIEL crane hoist
could not be moved. It was determined that
the East and West drums were out of synchronization |
|
74
|
Friday, November 29, 2024, 15:23 |
Adam Newsome | Hot Cell 1 | Maintenance | 1000 kg crane: y axis position display not functioning | After a recent power cycle, the y-axis
referencing was lost for the 1000 kg crane.
The position readout was also incorrect, |
|