23
|
Friday, June 12, 2015, 10:16 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump Vac Seal Vent & Test | - Vacuum has been pumping steadily on the
EHDT section since June 8, reaching 3.2E-8
Torr at 8am today (June 12) |
|
|
18
|
Thursday, May 28, 2015, 16:08 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump Vac Seal RH Test & Installation | The following work was performed on
May 27 & 28, 2015:
- The beam dump 10kW Remote Handling |
|
|
21
|
Monday, June 08, 2015, 15:23 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump Seal Re-Install | On Monday June 8 the following work
was performed by Isaac Earle and Keith Ng:
- EHDT beamline vented |
|
|
10
|
Friday, December 19, 2014, 14:05 |
Isaac Earle | 100KW Beam Dump | Development | Beam Dump & Lead Shielding Design Documentation | As there likely won't be an opportunity
to properly document the design of the beam
dump insert and cooled lead shielding in |
|
|
33
|
Tuesday, May 02, 2017, 16:52 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender stand hardened parts tested | Hardness testing was performed on
1 sample each of parts TBP1822 and TBP1823
(part of the 35-deg magnet stand assembly |
|
|
36
|
Monday, June 05, 2017, 16:16 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender stand assembly complete | Assembly
of two complete bender stands was completed |
14x |
|
35
|
Thursday, June 01, 2017, 15:25 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender adjustment blocks modified to fit magnet | Adjustment blocks were installed on the
second dipole bender today (labeled "No.
03" "C15-III-57/15"). The |
  |
|
37
|
Wednesday, June 28, 2017, 17:37 |
Isaac Earle | BL4N | Development | BL4N 35-deg bender "No. 1" installed on magnet stand | BL4N 35-deg bender magnet "No.
1" has been installed onto the magnet
stand with "stand leg" configuration |
  |
|
17
|
Friday, May 15, 2015, 11:06 |
Isaac Earle | 100KW Beam Dump | Development | BD and Upper Pb Shield Water Hoses Replaced | The beam dump and upper lead shield
flexible hose assemblies have been replaced
with smaller diameter versions to allow for |
|
|
22
|
Wednesday, June 10, 2015, 14:57 |
Isaac Earle | 100KW Beam Dump | Development | BD Water System Leak Test | A leak test was performed on the beam dump
water system on June 9 in the afternoon.
- Pipe segments tested: The entire |
|
|
7
|
Wednesday, December 03, 2014, 10:45 |
Isaac Earle | 100KW Beam Dump | Development | BD Signals Traced from Service Stand to Junction Box | On Dec 2 the cables from the BD service
stand area to the junction box were traced
to establish which sensors correspond to |
|
|
32
|
Tuesday, April 18, 2017, 19:28 |
Jason Kapalka | T-Hall Crane | Development | ATH overhead crane fault investigation | On April 18, 2017, an investigation was initiated
to determine the cause of the ARIEL Target
Hall overhead crane faults that occurred |
8x |
|
30
|
Friday, March 31, 2017, 19:39 |
Jason Kapalka | T-Hall Crane | Development | ARIEL Target Hall overhead crane faults (Test Mode) | On March 29, 2017, a 9 tonne steel shield
block was transferred from the ARIEL Target
Pit and placed into a
|
   |
|
31
|
Wednesday, April 12, 2017, 10:52 |
Jason Kapalka | T-Hall Crane | Repair | ARIEL Target Hall crane oil leaks & inspection plan | On March 29, 2017, a 9 tonne load was transferred
in the ARIEL Target Hall with the overhead
crane (TRIUMF crane #44). On April 3, 2017, |
    |
|
34
|
Tuesday, May 16, 2017, 17:30 |
Jason Kapalka | T-Hall Crane | Development | ARIEL Target Hall Overhead Crane Measurements | On May 5, 2017 the Beamlines and Remote Handling
groups recorded distances in the ARIEL Target
Hall from the Target Pit floor and B1 Target |
 |
|
59
|
Thursday, March 16, 2023, 14:41 |
Adam Newsome | T-Hall Crane | Development | ARIEL Target Hall Crane - Spare Pendant Procured, Tested | A spare pendant for the overhead crane
was procured from COH. The pendant's functionality
is the same as the original one's. The pendant |
|
|
61
|
Tuesday, April 25, 2023, 12:28 |
Adam Newsome | T-Hall Crane | Standard Operation | ARIEL Target Hall Crane - Drives Fault | Today while operating the crane with load,
the crane stopped moving. Upon investigating,
all safety signals appeared to be OK. Fault |
|
|
85
|
Monday, March 10, 2025, 11:35 |
Jason Zhang | Hot Cell 1 | Development | ARIEL Hot Cell PLC Update - 1000kg Crane Travel Zone | Wednesday, March 05, 2025, 13:00
Implemented and tested travel zone
restrictions for the 1000kg crane to prevent |
|
|
76
|
Thursday, December 12, 2024, 15:57 |
Aaron Tam | Hot Cell 1 | Development | APTW Pistons Gas lines exchange testing | December 12, 2024 - Chad Fisher,
Albert Kong, Aaron Tam
Tests: |
13x |
|
82
|
Wednesday, January 15, 2025, 13:52 |
Albert Kong | Hot Cell 1 | Development | APTW Front End VCR Gasket Selection | Today RH (CF and AK) agreed upon using
the following style of gaskets for the ARIEL
front ends: |
|