  4   Tuesday, February 28, 2012, 11:00 John WongEmptyTest oven LP-SISDoneMeasuring temperatures, currents & voltages Tuesday, February 28, 2012, 10:36
Two thermocouples were inserted through
the left side of the copper heat shield,
 Evap_2_thermocouple.jpg 
  3   Monday, February 13, 2012, 16:24 John Wong   DoneEvaporator #2 Commissioned  Monday, February 13, 2012, 16:21
The Evaporator 2 is now commissioned.
 See attachment#1 for the commissioning
 Evap2_Commissioning_Report.PDF 
  2   Thursday, July 21, 2011, 17:33 Pierre Bricault   Maintenance Rick mentioned to me that the evaporator is
ready for the next steps of the commissioning
process.
  
  1   Monday, March 28, 2011, 12:40 John Wong    Under ConstructionEvaporator #2 is still under construction. 
For further information please contact Jens
Lassen.
  