3
|
Monday, February 13, 2012, 16:24 |
John Wong | | | | Done | Evaporator #2 Commissioned | Monday, February 13, 2012, 16:21
The Evaporator 2 is now commissioned. See attachment#1 for the commissioning report or refer to Document #43321. |
2
|
Thursday, July 21, 2011, 17:33 |
Pierre Bricault | | | | Maintenance | | Rick mentioned to me that the evaporator is ready for the next steps of the commissioning process.
In the chamber only the target leg heaters have current by-pass clamps on them.
The ionizer tube heaters do not have them because these lines do not have the same configuration as the others. The current by-pass clamps will
not fit these lines.
We may not need this for the commissioning, Rick will design and manufacture something for this when I get back from holiday.
The water is on in all circuits except for the power supply cooling circuit.
Pierre |
1
|
Monday, March 28, 2011, 12:40 |
John Wong | | | | | Under Construction | Evaporator #2 is still under construction. For further information please contact Jens Lassen. |
|