Entry  Thursday, February 09, 2017, 11:49, Laura Lambert, , , , Maintenance, New heatshield with flexible water lines 

 Thursday, February 09, 2017, 11:47

A new heatshield with flexible water lines has been put into evap2 last Friday Feb3rd


 

Entry  Monday, May 08, 2017, 10:05, Laura Lambert, , , , Maintenance, Turbo pump control box replaced 

 Monday, May 08, 2017, 10:05

Turbo pump control box died last week.

Replaced with a new one.


 

Entry  Thursday, May 11, 2017, 11:30, Laura Lambert, , , , Maintenance, New Ion Gauge for IGP2 

 Thursday, May 11, 2017, 11:25

IGP2 has been having problems where sometimes it turns off and requires simply unplugging and plugging back in.

Ion gauge has been replaced.

At first the vacuum box appeared red on epics and when attempting to reset everything nothing would work and the backing pump would try and turn on then timeout.

Apparently this new ion gauge draws slightly more than the old one and this blew a fuse in the PLC.

Old fuse was 2A, so a new 3A fuse has been replaced - seems to be working fine now. 


 

Entry  Tuesday, July 18, 2017, 15:30, Laura Lambert, , , , Maintenance, Paddle wheel replacement for all evap2 water supplies 

 Tuesday, July 18, 2017, 15:26

Problems occured with TGHT water supply paddle wheel stopped and therefore tripped off evap2 last week.

All paddle wheels were replaced today for evap2 [other than the chiller].

A build up of dirt was found on all wheels replaced.

Evap2 good to go.

Will test flow meters before heating up to higher setpoints to confirm everything is working.


 

Entry  Wednesday, July 19, 2017, 13:55, Marla Cervantes, , 40282-5, TARGET BOAT, Done, Sintering La(OH)3/C discs 170724-LaC2-CarbothermalReduction-EPICS-PLOTS.PNGIMG-20170725-WA0018.jpg

 Wednesday, July 19, 2017, 13:44

Discs previously casted by Marla and Pauline and weighed. 

Discs are placed inside a small graphite container.

Graphite container with discs loaded with 30 discs was loaded into Ta-boat previously coated with TaC.

Ta-boat is wrapped with 3 Ta heat shields.

Loaded in evaporator 2.

Chamber currently pumping down.


Thursday, July 20, 2017, 16:07

 HS water valves were opened in the morning, no leaks were detected.

Perform water test to confirm paddle wheels are working well.

Current was tapped manually to 40 A.

Read out on meter confirmed paddle wheels are registering 

Tap back down to 20 A, tripped off system on purpose by closing HS water valves.

TGHT tripped off as expected.

Water flow test was good, initiating ramp up of samples.

Taped manually to 40 A.

After the stabilization of the vacuum auto ramping was set up to 0.2 A/min.

Up to a final set up point of 250 A.

Final desired temperature ~1800 C.


 Friday, July 21, 2017, 10:20

Final set up from July 20 was reached.

Current reading: 244.6 A.

Voltage reading: 3.82 V.

Temperature reached: 1105 C.

Final set up was change to 1500 A.

The temperature reached at 6 pm was 1936 C so the current  was decreased  to 488 A.

The final temperature after 30 min was 1800 C.

The set up stayed the same for the weekend.


 Monday, July 24, 2017, 13:06

Temperature reading in the morning was 1856 C.

TGHT: 487.87 A, 9.07 V

TGHT power supply: 

IGP1: 3.75e-7 Torr

IGP2: 3.51e-7 Torr

Started to ramp down at 1 A/min rate.

Initiating auto cooling at 1.0A/min for TGHT.170724-LaC2-CarbothermalReduction-EPICS-PLOTS.PNG


 Tuesday, July 25, 2017, 09:27

LaC2/C discs were taken off of evap2.

LaC2/C discs were brought in to glove box.

IMG-20170725-WA0018.jpg

 

Entry  Tuesday, August 01, 2017, 15:34, Laura Lambert, , , , Problems, IGP1 mis-communicating with EPICS - PLC problem? evap2_trip_7.31.2017.JPG

Monday, July 31, 2017, 15:24

Turned on BV and TP this afternoon.

Started ramping down, ~1min after turned on both tripped off.

Vacuum box turned red.

IGP1 appears yellow but still registering a vacuum.

TP interlocks: requires IEVAP2:IGP1 < 500mTorr but IGP1 = 6mTorr when tripped off.

Should have been satisfied and therefore not tripped but IGP1 not communicating?

Nothing wrong with ion gauge in person, vacuum good on direct read out.

When attempting 'Global Reset', nothing would reset - vacuum box remained red etc.

See screenshot attached of errors.


 Tuesday, August 01, 2017, 15:31

Had kept BP, PV and RV overnight.

This morning vacuum fine, everything had reset except "IEVAP2:TP on" under device notes for IEVAP2:TP remained red.

Turned on BV and TP, once turbo pump registered on, red wording went away.

Currently pumping down - everything looks fine now.

Still unsure of reason for these errors...


 Friday, August 04, 2017, 10:55

Happened again last night at ~5:45 while evaps at ~420A - see elog i.d. 383 for photos and details.


 

Entry  Wednesday, August 02, 2017, 16:12, Marla Cervantes, , 40282-5, , Done, Sintering La(OH)3/C pellets 

 Monday, July 31, 2017,  

Pellets previously pressed by Marla and Pauline. 

Pellets are placed inside a small graphite container.

Graphite container loaded with 5 pellets was loaded into Ta-boat previously coated with TaC.

Ta-boat is wrapped with 3 Ta heat shields.

Loaded in evaporator 2.


 Tuesday, August 01, 2017,

Chamber pumping down.


 Wednesday, August 02, 2017, 16:03

HS water valves were opened, no leaks were detected.

Current was tapped manually to 40 A.

After the stabilization of the vacuum auto ramping was set up to 0.5 A/min.

Up to a final set up point of 300 A.

Final desired temperature ~1700 C.


 

    Reply  Friday, August 04, 2017, 10:52, Laura Lambert, , 40282-5, TARGET BOAT, Problems, Sintering La(OH)3/C pellets evap2_trip_8.4.2017.JPGevap2_trip_8.4.2017[2].JPGevap2_trip_8.4.2017[3].JPGevap2_trip_8.4.2017[4].JPG

Marla Cervantes wrote:

 Monday, July 31, 2017,  

Pellets previously pressed by Marla and Pauline. 

Pellets are placed inside a small graphite container.

Graphite container loaded with 5 pellets was loaded into Ta-boat previously coated with TaC.

Ta-boat is wrapped with 3 Ta heat shields.

Loaded in evaporator 2.


 Tuesday, August 01, 2017,

Chamber pumping down.


 Wednesday, August 02, 2017, 16:03

HS water valves were opened, no leaks were detected.

Current was tapped manually to 40 A.

After the stabilization of the vacuum auto ramping was set up to 0.5 A/min.

Up to a final set up point of 300 A.

Final desired temperature ~1700 C.


 

 Friday, August 04, 2017, 10:20

evap2 tripped twice yesterday.

1st trip) there was a power bump which caused a trip at ~4:20pm, this can be seen in the striptool image attached.

-TGHT spiked to zero, but immediately went back to the ~420A it was sitting at at the time.

-This did not initiate a full trip of everything, but a visual spike in the system can be seen

-Oddly this was not picked up in archives - happened so fast and must have been in the small time frame it was not picking up information

-Did TGHT actually drop to zero followed by then applying an immediate 420A?

-Or did it simple not register a reading due to power bump?

2nd trip) IGP1 stopped communicating at ~5:45pm, this can be seen in both the archives, striptool and evap2 control screenshot images attached

-IGP1 was fine, vacuum was good

-Registering good vacuum in epics - can see in screen shot vacuum was still good but IGP1 turned yellow as if turned off

-This resulted in TP followed by BV tripping off due to no longer getting a vacuum reading making the TP think there was a bad vacuum.

-Possible miscommunication with PLC?

-This is the same scenario that happened on mon - see elog i.d. 381

Will follow up when more information acquired...


 

    Reply  Friday, August 04, 2017, 14:09, Laura Lambert, , 40282-5, TARGET BOAT, Done, Sintering La(OH)3/C pellets 

Laura Lambert wrote:

Marla Cervantes wrote:

 Monday, July 31, 2017,  

Pellets previously pressed by Marla and Pauline. 

Pellets are placed inside a small graphite container.

Graphite container loaded with 5 pellets was loaded into Ta-boat previously coated with TaC.

Ta-boat is wrapped with 3 Ta heat shields.

Loaded in evaporator 2.


 Tuesday, August 01, 2017,

Chamber pumping down.


 Wednesday, August 02, 2017, 16:03

HS water valves were opened, no leaks were detected.

Current was tapped manually to 40 A.

After the stabilization of the vacuum auto ramping was set up to 0.5 A/min.

Up to a final set up point of 300 A.

Final desired temperature ~1700 C.


 

 Friday, August 04, 2017, 10:20

evap2 tripped twice yesterday.

1st trip) there was a power bump which caused a trip at ~4:20pm, this can be seen in the striptool image attached.

-TGHT spiked to zero, but immediately went back to the ~420A it was sitting at at the time.

-This did not initiate a full trip of everything, but a visual spike in the system can be seen

-Oddly this was not picked up in archives - happened so fast and must have been in the small time frame it was not picking up information

-Did TGHT actually drop to zero followed by then applying an immediate 420A?

-Or did it simple not register a reading due to power bump?

2nd trip) IGP1 stopped communicating at ~5:45pm, this can be seen in both the archives, striptool and evap2 control screenshot images attached

-IGP1 was fine, vacuum was good

-Registering good vacuum in epics - can see in screen shot vacuum was still good but IGP1 turned yellow as if turned off

-This resulted in TP followed by BV tripping off due to no longer getting a vacuum reading making the TP think there was a bad vacuum.

-Possible miscommunication with PLC?

-This is the same scenario that happened on mon - see elog i.d. 381

Will follow up when more information acquired...


 

 Friday, August 04, 2017, 14:05

Vented in air and transferred to glove box today.

Container did not break.

Some wires in PLC were not creating a good contact - could be problem re: IGP1 tripping off.

Wires replaced by Gelo.

Put back under vacuum with nothing loaded over weekend to see how things run...


 

Entry  Tuesday, September 12, 2017, 13:08, Aaron Schmidt, , , , , Window shutter added 

 Tuesday, September 12, 2017, 12:00:

The coated back window was changed to a shuttered window.

On star-point flange bolt interfered with the shutter, however it was removed, shortened, and re-installed.

The installation is complete. Awaiting roughing pump to leak check.

Entry  Thursday, November 23, 2017, 15:10, Laura Lambert, , 41882-4, TARGET BOAT, Done, Graphite insert test 6x

 Thursday, November 23, 2017, 14:54

Graphite insert loaded into previously TaC coated target boat.

One endcap removed to allow for outgassing: left side out, right side in.

Weight of graphite tube + single endcap = 10.2012g

Same Ta heats shields remain on container from sintering TaC coating.

Currently pumping down in evap2.


Friday, November 24, 2017, 11:31

IGP1 = 4.52e-7 Torr

IGP2 = 3.43e-7 Torr

OMEGA slope = 0.98

Good vac at 3.0e-4, bad vac at 8.0e-4 Torr.

HS water valves have remained open since the last time evap2 was used.

No leak check done.

Tapped up manually to 50A.

Vacuum stable.

IGP1 = 5.34e-7 Torr

IGP2 = 5.54e-7 Torr

Initiating auto ramp for TGHT @ 0.2A/min to a max setpoint of 300A

Once max setpoints achieved, will tap up manually to final desired temperature of 2000C

Uranium targets go to a max temperature of 1950C online, so graphite insert should be tested to 2000C


 Monday, November 27, 2017, 10:15

IGP1 = 2.5e-7 Torr

IGP2 = 1.9e-7 Torr

Reached 300A, 4.61V

OMEGA = 1298C

Tapped up manually to 485A, 8.46V

OMEGA = 1808C

Remained at this setpoint for a day


Tuesday, November 28, 2017, 15:41 

IGP1 = 3.88e-7 Torr

IGP2 = 3.58e-7 Torr

Tapping up to 2000C...


Tuesday, November 28, 2017, 16:10 

TGHT = 570A, 10.20V

OMEGA = 2005C

IGP1 = 9.64e-7 Torr

IGP2 = 1.05e-6 Torr

There was a minor drop in voltage at 540A, 9.58V - dropped to ~9.4V then slowly went back up to 9.58V [see photo]

Will remain at this setpoint overnight and cool down in the a.m.


 Wednesday, November 29, 2017, 08:48

Voltage increased slowly while sitting at max setpoint of 570A [see photo]

TGHT = 570A, 11.20V --> voltage increased by 1.0V over ~16.5hrs

OMEGA = 2114C

IGP1 = 6.6e-7 Torr

IGP2 = 6.5e-7 Torr

Initiating auto-cool at 2.0A/min


 Wednesday, November 29, 2017, 16:15

Vented in air and removed today.

Will update tomorrow with results and photos.


 

Entry  Monday, December 11, 2017, 14:22, Laura Lambert, , , , Maintenance, Interlock limits updated to 500mTorr 

 Monday, December 11, 2017, 14:21

Dave updated evap2 interlock limits to 500mTorr for TGHT and TBHT on friday


 

Entry  Wednesday, April 25, 2018, 07:21, Aaron Schmidt, , , , Done, HS swap evap 2 

Wednesday, April 25, 2018, 07:05: TGHT & TBHT off

Wednesday, April 25, 2018, 07:15: BV1 & TP1 off

Wednesday, April 25, 2018, 07:17: PV1 & BP1off

Wednesday, April 25, 2018, 07:19: Begin venting

Wednesday, April 25, 2018, 07:22: Full venting.

Wednesday, April 25, 2018, 07:29: HS waterlines purged.

Wednesday, April 25, 2018, 07:48: Aurelia's test ta target assembly was removed. The blank target heating heat shield for evap 2 was reinstalled. shields in but empty.

Evap 2 Doors closed.

Entry  Friday, June 08, 2018, 08:33, Aaron Schmidt, , , , Problems resolved, Chiller tripped / Alarm 

Alarm noted on passing Hot Lab. RPG notified, no radiological hazards. ISAC ops contacted, drop in DI water last night.

Entered w/ PPE. Chiller alarming. Evap 1 running ok

Friday, June 08, 2018, 08:30: Chiller turned on/off. Reset. No alarm.

Entry  Tuesday, September 11, 2018, 10:47, Aaron Schmidt, , , , , Evap 2 step discrepancy  PS_Check.docx

 Tuesday, September 11, 2018, 10:45:

TGHT: 53.4 A   TBHT: 57.75

Actual

TGHT: 60.0A  TBHT: 59.0A

Uploaded the rest to Word doc. Screenshots included.

Entry  Thursday, November 22, 2018, 10:19, Marla Cervantes, , 43630-7 , , Done, Graphite insert test #2 

 Thursday, November 22, 2018, 10:12

A previously sintered tantalum tube with 3 layers of shielding was loaded with a graphite insert.

The tube was loaded in evaporator 2 on Wednesday 21/11/2018 and pumped down

The graphite insert will be heated to 2000 C


current pressure IGP1 =  4.2e-7 Torr

TGHT manually tapped to 40 A

Autoramp set to 2 A/min on TGHT to 400 A aiming for 1800 C


 Thursday, November 22, 2018, 17:13

TGHT 401.25 A, 6.79 V

Temperature 1780 C

IGP1 7.89e-7 Torr

Tapping manually to reach 1800 C, final current 407.2 A, 6.96 V


  Friday, November 23, 2018, 17:13

Tapped manually to TGHT 469.0 A, 8.64 V

Temperature 2019 C

IGP1 2.68e-7 Torr


Thursday, November 29, 2018, 08:03

TGHT 469.0 A, 8.945 V

Temperature 2061 C

IGP1 2.12e-7 Torr


 Tuesday, December 04, 2018, 07:53

TGHT 469.1 A, 8.814 V

Temperature 1983 C

IGP1 1.52e-7 Torr


Wednesday, December 05, 2018, 21:30

 TGHT 469.1 A, 8.75 V

Temperature 1983 C

IGP1 1.22e-7 Torr


Thursday, December 06, 2018, 12:25

 TGHT 468.9 A, 8.66 V

Temperature 1977 C

IGP1 1.42e-7 Torr


Friday, December 07, 2018, 17:59

  TGHT 468.9 A, 8.80 V

Temperature 1977 C

IGP1 1.42e-7 Torr


Wednesday, December 12, 2018, 12:18 

TGHT 469.2 A, 8.7 V

Temperature 1945 C

IGP1 1.10e-7 Torr


Thursday, December 13, 2018, 10:42

TGHT 469 A, 8.7 V

Temperature 1939 C

IGP1 1.04e-7 Torr

Ramping temperature down at -2 A/min


 Friday, December 14, 2018, 10:42

TGHT 0.0 A, 0.051 V

IGP1 4.36e-8 Torr

Entry  Thursday, December 20, 2018, 10:27, Marla Cervantes, , 43630-6, , Done, Tantalum tube heating 

Thursday, December 20, 2018, 10:24

A tantalum tube was loaded in evaporator 2 on Wednesday 19/Dec/2018.

It is going to be heated to 2000 C during 3 weeks 

Pressure IGP1 =  4.88e-7 Torr

TGHT manually tapped to 40 A

Autoramp set to 2 A/min on TGHT to 400 A aiming for 1800 C

The system tripped due to a power outage.

the current went from 57 to 0 A.

The tube did not show damage signs.


 This experiment will be postponed.
Entry  Wednesday, January 23, 2019, 13:06, Marla Cervantes, , 43630-2, , Done, Graphite insert test #3 

 Wednesday, January 23, 2019, 13:01

A previously coated tantalum tube with 3 layers of shielding (Details in e-log 426) was loaded with a graphite insert. 

The tube was loaded in evaporator 2 and pumped down

The graphite insert will be heated to 2000 C for 3 weeks


 Thursday, January 24, 2019, 10:04

Pressure = 3.66e-7 Torr

TGHT manually tapped to 45 A

Final pressure = 3.8e-7 Torr

Set autoramp to 350 A @ 2A/min

TGHT = 1643 C

Set autoramp to 400 A @ 2A/min

TGHT = 1790 C

Started to tapped manually at approx 5 A every 30 s

Final TGHT => 1896 C, 8.16 V, 480.46 A

The current will stay at 480 A until temperature stabilizes. 

The current was reduced to 476 A to stay at 1900 C


Friday, January 25, 2019, 17:16

Pressure = 3.22e-7 Torr

TGHT = 8.17 V, 477.65 A, 1882 C 


Monday, January 28, 2019, 09:09 

Pressure = 1.67e-7 Torr

TGHT = 8.07 V, 477.65 A, 1859 C 

The temperature readings are fluctuating between 1880 and 1859 C


Tuesday, January 29, 2019, 07:32

Pressure = 1.55e-7 Torr

TGHT = 8.17 V, 477.75 A, 1880 C 


Tuesday, January 29, 2019, 11:34

 Pressure = 1.55e-7 Torr

TGHT = 8.27 V, 477.56 A, 1897C 


Tuesday, January 29, 2019, 12:47 

 Pressure = 1.53e-7 Torr

TGHT = 8.19 V, 477.75 A, 1899C 


Tuesday, January 29, 2019, 13:38

 Pressure = 1.55e-7 Torr

TGHT = 8.25 V, 477.75 A, 1905C


Thursday, January 31, 2019, 16:12  

 Pressure = 1.40e-7 Torr

TGHT = 8.4 V, 476.81 A, 1918C


Thursday, January 31, 2019, 22:32

Pressure = 1.39e-7 Torr

TGHT = 8.37 V, 476.71 A, 1914C

The current will be ramped down @1 A/min


Friday, February 01, 2019, 09:58

 Last 22 A tapped to 0 manually

Tantalum tube was removed from the EVAP2

Entry  Wednesday, February 13, 2019, 10:08, Darwin Ortiz Rosales, , 43630-1 , , Done, Graphite insert test 3b 

 Wednesday, February 13, 2019, 10:04

A previously coated tantalum tube with 3 layers of shielding (Details in e-log 426) was loaded with a graphite insert. 

The tube was loaded in evaporator 2 and pumped down

The graphite insert will be heated to 2000 C for 1 week

IGP1=1.37e-07 Torr


 Wednesday, February 13, 2019, 10:27

IGP1= 1.46e-07 Torr

Manual tapping to 40A on TGHT

TGHT 40.7A, 0.104V

Autoramp started at 1A/min up to 400 A

Good Vacuum = 3.00e-05, Bad Vacuum = 5.00e-05


 Thursday, February 14, 2019, 08:42

IGP1= 2.2e-07 Torr, T=1705 C, TGHT 401A, 6.7 V

Manually tapping to 2000 C (Slow ~1 A/min) in 5 A increments followed by waiting for equillibrium


Thursday, February 14, 2019, 10:54

IGP1 = 1.4e-06 Torr, T = 2003 C, TGHT 500A, 9.1 V

Waiting for equillibrium

manually tapped TGHT to 503A,  T = 2003 C

Will leave for 1 week


Wednesday, February 20, 2019, 08:44

 IGP1= 1.37e-07 Torr, T=1943 C, THGT= 503 A, 8.9 V

Ramp-down @ 2A/min

 


Wednesday, February 20, 2019, 14:02  

1 hour since TGHT = 0 A

Venting will proceed.


 

Entry  Wednesday, March 13, 2019, 15:43, Marla Cervantes, , 43630-6, , Done, Graphite insert test #4 

 Wednesday, March 13, 2019, 15:41

An uncoated tantalum tube was loaded with a graphite insert (with conical caps).

3 tantalum foils were wrapped around the tantalum tube and a Ta cap was added.

EVAP2 is currently pumping down

The tube will be hated for 5 days at 2000 C


Thursday, March 14, 2019, 10:07

IGP1 = 5.37e-7 Torr

The TGHT will be tapped manually to 50 A  

After aprox 1 hour IGP1 = 5.08e-7 Torr, TGHT=46.5 A, 0.224 V

Autoramp is set to 1A/min to 300 A

 Autoramp is set to 1A/min to 450 A

Autoramp was stopped at 425 A when 2000 C were achieved


 Sunday, March 17, 2019, 00:25

IGP1 = 2.03e-7 Torr

TGHT=424.2 A, 7.117 V, temp 1976 C


Sunday, March 17, 2019, 15:04 

IGP1 = 21.6e-7 Torr

TGHT=424.1 A, 7.085 V, temp 1967 C

cooling down -1 A/min

ELOG V2.9.2-2455